This document is an attachment containing questions and answers related to Amendment 1 of Solicitation 140P5424R0016 for the "Mill & Overlay Roadway-CANA" contract opportunity, issued by the Department of the Interior National Park Service Southeast Region.

The key details are:

  • The work area extends up to and 3 feet beyond the easternmost speed bump.
  • The demolished speed bumps will not be reinstalled, but the contractor should include new asphalt speed bumps in their proposal.
  • The striping must be thermoplastic, not standard traffic marking paint.
  • Any changes to the Statement of Work from these Q&As will be incorporated before award.
  • Acknowledgement of these answers demonstrates the offeror's receipt of the updated information.

View the file

Other files for this federal contract opportunity

Other files attached to Mill & Overlay Roadway-CANA, newest first.
File Type Posted
Sol_140P5424R0016_Amd_0001.pdf PDF
Sol_140P5424R0016.pdf PDF
Atch_2_DBA_WD-Brevard_County.pdf PDF
Atch_1_SOW.pdf PDF
Atch_4_Area_Layout_and_Photos.pdf PDF
Atch_3-Site_Visit_Info.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P5424R0016 Amendment 1 Attachment 1

Question #1: Does the work area extend up to or beyond the eastern most speed bump?

Answer: Yes, mill and overlay will end three feet beyond the eastern most side of the existing speed bump (see redline on photo below)

Question #2: Will the demo'd speed bumps be reinstalled? If so, is asphalt acceptable?

Answer: The demolished speed bumps will not be re-installed, please include asphalt speed bump on your proposal.

Question #3: Is the striping to be thermoplastic or standard traffic marking paint?

Answer: Yes, striping will need to be thermoplastic.