This document contains questions and answers related to a solicitation for renovation and remodel work at the headquarters building of Everglades National Park. The solicitation seeks a contractor to complete break room and conference room renovations, including installation of new carpet tiles, millwork, epoxy flooring, and an adjustable mobile island with a 31x50 countertop and ADA compliant toe kick on one side. An allowance of $5,000 is included for a new conference room door. The selected contractor must complete the work within 120 days and can work between the hours of 7am and 5pm, with exceptions possible subject to notification. The related federal contract opportunity is for construction and renovation services at Everglades National Park headquarters to update the conference and break rooms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovation / Remodel Break and Conference Room – Everglades National Park HQ

1. Are the questions and answers still valid from the last solicitation?

Yes.

2. 1.3.2.8. states that NPS is providing the new carpet tiles for the conference room. Does this include the correct adhesive to install?

No. Contractor is responsible for installation and following manufacturer’s guidelines (Mannington)

3. Are you providing the master CSI format sheet for the price breakdown?

No. Contractor shall provide on their own sheet of preference.

4. Is the NPS providing the new conference room table? If so, what size will the new table be?

Table size is to be determined. There are two electric & data outlets called out at each of the tables two legs. The location of those outlets will be provided once the table is determined.

5. It was stated at the site visit that the countertops were going to be changed to granite instead of quartz, what will the new color/style be?

Color/Style shall match that which was specified in quartz.

6. It states in the millwork notes to use white melamine in all casement interiors, So outside of the cabinets in 7909-60 and the insides in the white melamine?

7909-60 shall be used both outside and inside of cabinets.

7. What epoxy system would you like on the concrete patio? primer/color with texture? primer/color/clear topcoat with aggregate? or something else?

Epoxy shall be clear top with non-slip texture.

8. What size is the mobile island? Do you want it to have an ADA toe kick on all sides? How big do you want the top to be?

The mobile island shall be 24x48 (cabinets), countertop shall be 31x50, one inch overhang on three sides, six inches on side opposite doors. Provide ADA toe kick on side with six-inch overhang.

9. What color/shade do you want the glass to be in the new doors and windows?

Clear, tempered as required.

10. It shows 2 microwaves in the plans, is this the correct amount?

Yes

Project Information Solicitation Number 140P5424R0003 Park Everglades National Park Project Title Everglades National Park HQ Break and Conference

Room Renovation / Remodel Period of Performance 120 Days

11. He stated that there would be an allowance of 5000.00 for a new door for the conference room, do we itemize this out in our quote?

Yes, there should be a $5,000 allowance for the conference room door. Door style and size to be determined by NPS and provided to contractor.

12. Work Hours?

Work hours shall be no earlier than 7am and no later than 5pm. Exceptions may be allowed for unusual circumstances. Contractor to notify COR if work requires any extended hours.