- DEMOLISH UTILILITY INFRASTRUCTURE BUXTON Federal contract opportunity
- Solicitation number
- 140P5324R0022
About this file
This document is a Statement of Work for a federal contract opportunity to demolish utility infrastructure in Buxton, North Carolina for the National Park Service at Cape Hatteras National Seashore.
The key details are:
- The National Park Service requires the demolition of multiple utility support buildings, an elevated water tower, a concrete above ground water storage tank, chain link fencing, lift stations, asphalt pavement, and underground utility lines located in Buxton, NC.
- The contract has a period of performance from 8/1/2024 to 12/31/2024 and is a 100% Small Business set-aside with a NAICS code of 238190.
- The acquisition is a Firm-Fixed Price Request for Proposal that closes on 7/9/2024, with a question cutoff date of 6/24/2024. Proposals must be submitted via email to Ashley_Warcewicz@nps.gov.
- A site visit is scheduled for 6/21/2024 at 11:00 am EST at the project location.
- The contractor must provide a work schedule, safety plan, on-site supervision, and coordinate with the Contracting Officer's Representative for final inspection and acceptance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5324R0022_Amd_0003.pdf | ||
| 140P5324R0022__-_Demo_Questions_and_Answers_Amend_2__0002.pdf | ||
| Sol_140P5324R0022_Amd_0002.pdf | ||
| Loggerhead_Lane___NESHAP_Report_USFin_0002.pdf | ||
| Sol_140P5324R0022_Amd_0001.pdf | ||
| 140P5324R0022__-_Demo_Questions_and_Answers__0001.pdf | ||
| Sol_140P5324R0022.pdf | ||
| B08__-_Attachment_1_-_SOW_Demolish_Utility_Infrastructure_in_Buxton_Revised.pdf | ||
| Attachment_3_-_Relevant_Prior_Experience_2_pages.pdf | ||
| A2_-_SCA_Wage_Determination.pdf | ||
| B08_-_Attachment_5_-_Limitation_on_Subcontracting_Report_Template.xlsx | XLSX spreadsheet | |
| B08_-_Attachment_4-_Past_Performance_Questionnaire.doc | DOC document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Demolish Utility Infrastructure, Buxton NC Page 1
CAPE HATTERAS NATIONAL SEASHORE
Outer Banks Group
Scope of Work
Demolish Utility Infrastructure, Buxton, NC
1. INTRODUCTION
1.1. The National Park Service (NPS) at Cape Hatteras National Seashore (CAHA) needs to demolish multiple utility support buildings, an elevated water tower, a concrete above ground water storage tank, chain link fencing, a few lift stations, a small section of asphalt pavement, and underground utility lines that are all located in Buxton, NC on
Loggerhead Lane, and Lighthouse Road.
2. DEMOLITION SITE LOCATIONS
2.1. This project involves removal of multiple structures, utilities, and associated assets in four different but geographically very close locations, all in Buxton NC. These 4 sites are all easily accessible from Highway 12 in Buxton NC.
2.2. Cape Point Elevated Water Tower Site- Loggerhead Lane (figure 4)
2.2.1. Elevated Metal Water Tower – 85 Feet Tall
2.2.2. Asphalt Removal – 350 SQFT
2.2.3. Chain Link Fence – 120 LF
2.2.4. Miscellaneous Rubbish Concrete Pieces – 4 to 6 pieces
2.3. Cape Point Utility Infrastructure Site - Loggerhead Lane (figure 4)
2.3.1. Above Ground Water Storage Tank – 27’ diameter – 20 ‘tall
2.3.2. Lab Building – 20’ x 20’
2.3.3. Pumphouse Building – 21’ x 35’
2.3.4. Generator Building – 10’ x 10’
2.3.5. Small Ground Concrete Decant Filter Tank – 6’ x 8’
2.3.6. Small Fire Pump Woodshed Building – 6’ x 8’
2.3.7. Distribution System Components – 3 Pump/Lift Stations and PVC Lines
2.3.8. In Ground Lines – Approximately 350 LF
2.3.9. 3 Abandoned Underground Pump/Lift Stations
2.3.10. Chain Link Fence – Approximately 400 LF
2.4. Cape Point Housing Water Pump Building – Loggerhead Lane (figure 4)
2.4.1. Water Pump Cinder Block Building – 6’x 6’
2.4.2. Distribution System Components – In ground lines and tank
2.5. Old Coast Guard Sewer System and Generator Building – Lighthouse Road (figure 3)
2.5.1. Above Ground Concrete Tanks – (3 each) 6’x 8’
2.5.2. Chain Link Fencing – 210 LF
2.5.3. Generator Building – 12’x 12’
2.5.4. Concrete Pad 12’x 12’
2.5.5. Radio Tower Anchor Blocks – (4 each) 2’x 2’
Demolish Utility Infrastructure, Buxton NC Page 2
3. BACKGROUND AND EXISTING CONDITIONS
3.1. Asbestos and Lead Based Paint Testing is required prior to demolition.
3.1.1. A lead-based paint analysis was accomplished on the Water Tower, the Water
Storage Tank and all 3 water treatment site buildings on Loggerhead Lane. The results show no lead-based paint or asbestos on any of the structures and are attached below.
3.1.2. Asbestos testing was accomplished on the Water Tower, Water Plant, Water
Tank, Pump House Building, and the Coast Guard sewer system components. The results show no lead-based paint or asbestos on any of the structures and are attached below.
4. Cape Point Elevated Water Tower Site
4.1.1. The Elevated Water Tower has a total diameter of approximately 27’ and is approximately 85’ tall. The tower is made of steel metal. The top portion (sphere) is ¼” thick steel. The Plate Ring sections are 1” thick. The pedestal area of the tower has 4 section – two sections are 9/32” thick and the other two sections are
5/16” thick. The Base cone is 11/32” thick. The water tower is empty. Any remaining electrical lines coming to the tower must be disconnected and properly capped at least 3 feet from the structure and buried. The tower shall be demolished or dismantled in a “top down” order/method. Any non-mature pine trees may be cut or trimmed as needed to make space for the tower demolition. Do not cut down any mature trees, you may trim some as needed. The water tower rests on a 12 x 12 concrete pad that will also need to be removed. Inside the tower, there is a vault that is approximately 6’x8’ in the ground that shall be removed. There are 18 timber piles under the concrete pad that are equally spaced on a 24’ diameter circle, that support the tower, they shall be removed. After the site is clear of debris, the ground shall be leveled and reseeded.
Demolish Utility Infrastructure, Buxton NC Page 3
4.1.2. There is approximately 350SQFT of asphalt pavement on the side of the tower adjacent to the chain link fence that needs to be removed leveled and re-seeded with local grass seeds.
4.1.3. There is approximately 120 LF of chain-link fencing to be removed.
4.1.3.1.
4.1.4. There are 4 broken small approximately 3’x4’ slabs of concrete that need to be picked up disposed of offsite. Like the picture below.
4.1.4.1.
4.2. Cape Point Utility Infrastructure Site
4.2.1. The Above Ground Water Storage Tank is made of concrete and is approximately
27’ in diameter and approximately 20’ tall. The tank has been inspected inside and out and does contain some water. This tank when full can hold 75,000 gallons of water. The tank will need to be pumped out completely and all water removed from the site before demolition can begin on this structure. The tank extends below ground approximately 2 ft including its concrete foundation. Access to the tank is direct from Loggerhead Lane. Clearing brush around this structure shall be limited to 15 feet. This site, to include all structures and contents, will be demolished down to the soil and disposed offsite. The disturbed ground will be leveled and reseeded.
Demolish Utility Infrastructure, Buxton NC Page 4
4.2.1.1.
4.2.2. The Lab Building is made of concrete/cinder block and is approximately 20’x 20’ and needs to be demolished and removed completely. The disturbed ground will be leveled and reseeded. This building is attached to the Generator Building. There is an electrical line connected coming from a nearby utility pole to this building with a power meter mounted to the side of the building. The electrical line will need to be disconnected from the building and terminated with the local power authority (Cape
Hatteras Electric) prior to demolishing this building.
4.2.2.1.
4.2.3. The Pumphouse Building is made of concrete and cinder block and measures approximately 21’ x 35’ and needs to be demolished and removed completely.
There are in ground 2” PVC pipes coming from this building that are going to the
Lab Building that will also need to be removed. There are two in ground lift stations that will also need to be removed completely. There are two small concrete walking paths (4’x5’ & 12’x4’) in front of this building that will need to be
Demolish Utility Infrastructure, Buxton NC Page 5 demolished and removed. Inside this building there are water filters and PVC piping, gauges, water softener tanks, a brine tank and other apparatus that will need to be removed and disposed. The disturbed ground will be leveled and reseeded.
4.2.3.1.
4.2.4. The Generator Building is 10’ x 10’ and needs to be demolished and removed completely. The disturbed ground will be leveled and reseeded. There is a working generator switching unit in this building that may be repurposed. There is a concrete walking pad (4’x5’) in front of this building that also needs to be removed.
The generator has already been removed. This building is attached to the Lab
Building.
4.2.4.1.
4.2.5. The Small Ground Decant Filter Concrete Storage Tank is approximately 6’ x 8’ and needs to be demolished and removed completely. There is a lift station on the front side of this filter that also needs to be removed in its entirety. The disturbed ground will be leveled and reseeded.
Demolish Utility Infrastructure, Buxton NC Page 6
4.2.5.1.
4.2.6. The Small Woodshed Building is approximately 6’ x 8’ and needs to be demolished and completely removed. The disturbed ground will be leveled and reseeded.
4.2.6.1.
4.2.6.2. There is an abandoned lift station under this shed that needs to be removed to a minimum of 3 feet under the surface and capped with a flowable grout/gravel mix.
4.2.7. This area contains another small, wooden shed 6’ x 8’ that needs to be demolished and completely removed. The disturbed ground will be leveled and reseeded.
Demolish Utility Infrastructure, Buxton NC Page 7
4.2.7.1.
4.3. Cape Point Housing Area Small Water Pump Building Site
4.3.1. The abandoned water pump / cinder block building is approximately 6’ x 6’ and will be demolished and completely removed. The disturbed ground shall be leveled and reseeded.
4.3.1.1.
Demolish Utility Infrastructure, Buxton NC Page 8
4.3.2. There is a 6’ x 6’ Lift Station Concrete Cover and junction box in the ground that needs to be completely removed and disposed. This box extends into the ground approximately 5 feet. All existing wiring shall be removed, and conduit lines capped. Back fill the hole with completely local suitable fill. The ground shall be leveled and then reseeded.
4.3.2.1.
4.4. Old Coast Guard Sewer System and Generator Building – Lighthouse Road
4.4.1. Above Ground Concrete Tanks – (6 each) Approximately 6’x 8’
4.4.1.1. These Above ground concrete storage tanks and all associated pipes within the fenced in area shall be completely removed and disposed of offsite. The tanks are behind some fencing that also needs to be removed. The tanks are covered in minor brush that must also be removed. Do not remove any mature trees. Leave behind only the mature trees. One of the tanks is in the ground approximately 6‘deep and it will also be completely removed. Only mature trees shall remain on this small site, all other debris other than the trees shall be removed.
The ground shall be leveled and then reseeded.
4.4.1.2.
Demolish Utility Infrastructure, Buxton NC Page 9
4.4.2. Chain Link Fencing
4.4.2.1. Remove all dispose of all chain link fencing around the 6 above ground tanks. There is approximately 210 LF of chain link fence to be removed. The ground shall be leveled and then reseeded.
4.4.2.1.1.1.1.
4.4.2.1.1.1.2.
4.4.3. Generator Building
4.4.3.1. The abandoned generator building is approximately 12’ x 12’ and will be demolished and completely removed. The abandoned unserviceable generator and associated parts on site will also need to be removed and disposed of offsite. The generator is not operational. If any fuel or oil remains in the generator, it must be removed prior to demolition. No fuel or oil may be leaked onto the ground. Any fuel or electrical lines coming to the building must be properly capped or
Demolish Utility Infrastructure, Buxton NC Page 10 terminated 3 feet from the structure and buried. The disturbed ground shall be leveled and reseeded.
4.4.3.2. The generator building sits on a double thick concrete pad that is approximately 12’ x 12’ and has a small 4’ x 6’ concrete pad on the side of the buildings, it must also be removed and disposed of offsite.
There is a small concrete walking path approximately 10 ‘long and 4
‘wide that needs to the removed. The disturbed ground shall be leveled and reseeded.
4.4.3.3.
4.4.3.4.
4.4.3.5.
Demolish Utility Infrastructure, Buxton NC Page 11
4.4.4. Radio Tower Anchor Blocks – 3 Each
4.4.4.1. There are three old abandoned concrete radio tower anchor blocks that are approximately 3’ x 3’ on site. These must be demolished and removed offsite. The disturbed ground shall be leveled and reseeded.
4.4.4.2.
Demolish Utility Infrastructure, Buxton NC Page 12
Figure 1: General Locations of the Buxton Abandoned Utility Infrastructure Sites (Shaded Green)
Figure 2: Directions from US 12 in Buxton to Utility Demolition Sites
Demolish Utility Infrastructure, Buxton NC Page 13
Figure 3: Old Coast Guard Sewer System and Generator Building
Figure 4: Loggerhead Lane Abandoned Utility Infrastructure
Demolish Utility Infrastructure, Buxton NC Page 14
5.0 SCOPE OF WORK
This Statement of Work is not meant to be an all inclusive to do list for the project, but a list of the main items involved in the project. The contractor can use this list to assist him with the cost estimate for the project. The contractor will provide all technical support, materials, tools, equipment, and manpower to demolish all the structures and associated utilities or appurtenances in this Scope of Work. The contractor must abide by the specifications which are associated with this Scope of Work. The major project components are listed below but are not limited to the following:
5.1 Furnish all labor, material, and equipment necessary and required to perform the complete demolition, removal, and disposal of all structures identified in this scope of work. Any brush clearing to obtain access to any structures will be kept to a minimum and will be limited to 15 ft around the perimeter of any structure. Any brush removal, matting for equipment, or additional work to obtain safe access to the any structure scheduled for complete demolition is included within this project. All construction/demolition site debris must be removed. No burying or abandoning in place any portions of the tank, tower, pumphouse, lifts stations, shacks, or any associated building materials in this scope of work. Ground pipes must be removed to at least 3 feet below the surface.
5.2 No explosives may be used to demolish the tower or any other structures in the project. The contractor may use man lifts, telescopic booms, scaffolding, excavators, or other similar tools to remove the top of the tower and the large above ground tank.
Other alternative methods of demolition are possibly acceptable, and your proposed alternative methods shall be discussed clearly in the safety plan and proposal submittals.
5.3 Upon completion, all disturbed areas must be restored which may include but not limited to backfilling, leveling, and reseeding all disturbed areas. All debris on the ground must be picked up. No debris larger than a quarter should be left behind or on the ground. If paint chips fall off the tower or any structure during demolition, they must be cleaned up.
5.4 Provide hydroseeding to the disturbed areas, including and ruts or other disturbance created by construction work. Fill ruts or low areas with suitable material. Continue to water the grass until 75% of the area has seeded and growing.
a. Seed shall be suitable for the following:
i. Mostly shade location.
ii. Residential lawn
iii. Mowing operations with hand operated push or riding mowers
iv. Sandy soils
v. Septic Field coverage (roots that do not grow deeper than 24 inches)
vi. No weeds (dandelion, Bahia, pennywort)
vii. No exotic species.
Demolish Utility Infrastructure, Buxton NC Page 15
b. Hydroseed. Add a cover crop of grain rye at 30 lbs./acre. Rake broadcasted seed mix into the soil and saturate with water 2 – 3 times per day for 7 days, or until 75% of the area has seeds germinated and growing at least 1 inch high. Hydroseeded area may be observed for 7 days or until 75% of the area has growing seeds. If after 7 days, the area is less than 75% covered with new growth, overseed again and water 2-3 times per day until 75% of the ground is covered with growth.
5.5 Use this Seed Mix for restoration of demo location soil. Vegetation restoration of highly developed areas should be restored using the turf grasses already present as appropriate (such as “Outer Banks” Seed Mix)
5.4 The Contractor must provide receipts from the landfill or recycling disposal location showing the volume and/or weight of the material, name of the facility receiving the debris, address, point of contact, and phone number.
NOTES:
1. The contractor is responsible for verifying exact dimensions, quantities, materials, measurements, existing conditions, and access to the site prior to submitting a proposal.
2. The contractor is responsible for coordinating with all private or public parties and obtaining demolition permits as required to complete the project.
3. The contractor shall be responsible for and follow all federal and state safety protocols for safe demolition of the identified structures.
4. The contractor must complete a utility locate for all areas that have structures planned for demolition to ensure no active live lines are cut or damaged. Mark all lines clearly before starting demolition. The contractor will be responsible for repair or replacement of any damage to marked and unmarked utilities.
Demolish Utility Infrastructure, Buxton NC Page 16
5. Work hours are Monday Through Friday from 8AM to 5PM. If work is needing to be accomplished outside this time, the COR may approve if requested in writing.
6. Given the proximity of the demolition site to park housing, the contractor shall take actions that will minimize the environmental impacts to the area.
7. Loggerhead Lane Site Layout Drawing-
6.0 CONTRACTOR REQUIREMENTS
The contractor (including General Contractor, and sub-contractors) shall have proven experience and expertise in:
• Demolition of Structures
Prior to the Contractor submitting a bid for the project a site visit is available and highly recommended. The contractor shall be responsible for visiting the site and verifying access and measurements prior to work start. Site visits will be coordinated with the Park Contracting
Officer’s Representative (COR) - David Tongue, with the approval of the Contracting Officer
(CO). The COR’s contact information is listed below. An established time for a site visit is not yet determined.
7.0 DELIVERABLES
The Contractor must supply the Contracting Officer and COR with all submittals as included in this statement of work.
8.0 TRAVEL
Demolish Utility Infrastructure, Buxton NC Page 17
The Contractor will be responsible for all travel related expenses for this project, including mobilization of equipment, tools, materials, manpower, lodging, meals, and per diem and will be in accordance with Federal Travel Regulations.
9.0 ACCEPTANCE OF DELIVERABLES/TECHNICAL POINTS OF CONTACT
David Tongue – COR/Project Manager
National Parks of Eastern North Carolina
Cape Hatteras National Seashore
1401 National Park Drive
Manteo, NC 27954
Cell: 252-423-8933
E-mail: david_tongue@nps.gov
10.0 CONTRACTED SERVICES STATEMENT
Contractor employees performing services under this order will be controlled, directed, and always supervised by management personnel of the contractor. Contractor management will ensure that employees properly comply with the performance of work standards outlined in the statement of work, specifications, and contract documents. The tasks, duties, and responsibilities set forth in the Scope of Work and associated specifications may not be interpreted or implemented in any manner that results in any contractor employee creating or modifying
Federal policy, obligating the appropriated funds of the United States Government, overseeing the work of Federal employees, providing direct personal services to any Federal employee, or otherwise violating the prohibitions set forth in Parts 7.5 and 37.1 of the Federal Acquisition
Regulation (FAR).
11.0 PROGRESS/COMPLIANCE/SUBMITTALS
The government requires the following from the contractor to monitor progress and ensure compliance.
• The Contractor will be required to submit a schedule in the form of a graph or chart which shows the proposed work schedule for the various aspects of the work. The schedule should include beginning and ending dates for each aspect or phase of the work, to track the progress of the contract work.
• Submit a safety plan to the contracting officer for the entre project from start to finish for the park to review before we grant notice to proceed.
• The contractor shall provide onsite supervision of the contract work, including work that may be accomplished using subcontractors. The onsite supervisor shall be the contact and liaison with the National Park Service. The contractor shall provide this contact information to the contracting officer prior to getting notice to proceed.
• A final inspection shall be accomplished by representatives of the contractor and the
National Park Service (COR). This inspection will serve as final determination of the completion and workability of the contract work. Final payment will not be made without a final inspection resulting in final acceptance of the work by the
National Park Service.