Questions and Answers 140P5324R0005
1. Question: Is there an incumbent?
Answer: This requirement is posted for small business to provide proposals.
2. Question: Can you provide column titles for the A2 Vista Spreadsheet?
Answer: Revised Spreadsheet has been uploaded.
3. Question: Could the performance work period begin earlier than July?
Answer: No, see Special Instructions, no work shall be performed between May 1st and
August 15th.
4. Question: Is it expected that the work will be conducted throughout the year or in a specific season?
Answer: Specific time frames are required; no work Shall be performance between May
1st and August 15th.