Text version

Site #

Width
Length
Cu FT
Est. Cu Yards
$ Per Cu Yd
C33
13
43
279.5
11
C34
12
36
216
8
C35
12
42
252
10
C36
13
37
240.5
9
C37
13
48
312
12
C38
12
41
246
9
C39
14
45
270
12
C40
12
39
234
9
C41
14
42
294
11
C42
12
43
258
10
C43
12
47
282
11
C44
12
45
270
10
Cu FT 3154
Est. Cu Yards 122

Cost to remove Asphalt, grub site, form pad, pour and broom finish cement.