OBRI 140P5322Q0029 Survey

Vendor Questions # 3- # 7

3. Period of Performance (POP), can this be extended thru 3/18/23 to take advantage of “leaf off” season for speed and efficiency?

Park Response: The Period of Performance will be extended to 3/31/23.

3. Park Response:

4. Can you provide the existing surveys and deeds that you have on record from when the park was established? Or can we review these documents at the Local Park office in TN?

4. Park Response:

Although surveys and deeds are not on hand for every tract, the ones which are on hand will be made available to the surveyor for viewing at the park office in Wartburg, TN upon request.

5. Are there any known or current conflicts with neighbors in these areas that we need to be aware of?

5. Park Response:

There are no known conflicts with neighbors in these areas.

6. Are these tracts new acquisitions that were not part of the original purchase?

6. Park Response:

Obed Wild and Scenic River was established as a unit of the National Park Service in 1976. Tracts within the established boundaries have been acquired by the NPS on a tract by tract basis over the intervening decades. Out of the tracts covered by the Statement of Work for this project, Tract 103-08 was acquired in 2018. Every other tract covered by the Statement of Work was acquired more than twenty years ago.