Cosby_Water_Line_Repl_Proj_-_Questions_-_Responses_0003.pdf
PDF 840 KB Posted
- Attached to
- Great Smoky Mts. NP:COSBY WATER LINE REPLACEMENT
- Solicitation number
- 140P5321R0015
About this file
This document contains vendor questions and customer responses regarding Solicitation # 140P5321R0015 for the Great Smoky Mountains NP: COSBY WATER LINE REPLACEMENT project. The customer responses provide specifications for 1" combination air release valves, 4' diameter concrete air release vaults, and indicate that specifications for automatic flushing stations will be provided the following week. Additional responses confirm that all fusion on HDPE pipe will be butt-fused, excess spoil can be dumped on site pending verification of location, and HDPE saddles can be fused on new HDPE pipe where services are required.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # 140P5321R0015
GRSM Waterline Project: Cosby
Vendor Questions/Customers Responses
Vendor Question #6
We need drawing and specifications on l" Combination Air Release.
Customer Response #6
See attachment regarding air release valve. (page 4)
Vendor Question #7
We need drawing and specifications on 4' Diameter Concrete Air Release Vault.
Customer Response #7
See attachment regarding air release valve vault. (page 4)
Vendor Question #8
We need drawing and specifications on Automatic Flushing Station.
Customer Response #8
To be provided next week
Vendor Question #9
Is all fusion on HDPE butt-fused?
Customer Response #9
Yes
Vendor Question #10
Is there any place to dump excess spoil's on property? If so how far away from campground?
Customer Response #10
Yes, but need to verify location
Vendor Question #11
Can a HDPE saddle be fused on new HDPE pipe where a service is required?
Customer Response #11
Yes