A06_Attachment_0006_Div_1_Construction_Specs_44016199_0001.pdf
PDF 2 MB Posted
- Attached to
- Equipment Replacement - Replace Tour Road Gates - Federal contract opportunity
- Solicitation number
- 140P5125R0010
About this file
This document is a comprehensive set of construction specification documents for a project to replace tour road gates at Guilford Courthouse National Military Park in Greensboro, North Carolina. The project involves removing and replacing three manually operated wood swing gates and one automatic swing gate along tour roads and at the visitor center entrance. The new gates will be automatic, equipped with sensors to detect traffic and automatically open/close, and include a manual override feature and backup battery system. Each gate will be integrated into a unified system and require electrical power, which will be sourced from existing underground and overhead lines near the park.
The contract will be awarded as a single Firm-Fixed Price Contract using a Lowest Priced Technically Acceptable (LPTA) source selection procedure. The project is categorized under NAICS code 332323 with a small business size standard of 500 employees. The estimated period of performance is 180 days, and prospective offerors are strongly encouraged to conduct a site visit before submitting a quote. The contract price schedule includes options for installing entrance gates and a gates maintenance plan, with base items covering the installation of automatic exit gates and additional bid options for entrance gates at different locations.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5125R0010_Amd_0002.pdf | ||
| A06_Attachment_0008_Product_Files_44016199_0001.pdf | ||
| Sol_140P5125R0010_Amd_0001.pdf | ||
| B08_Attachment_0010_Questions_and_Answers_Gates_0001.pdf | ||
| A06_Attachment_0007_Div_2_Construction_Specs_44016199_0001.pdf | ||
| A06_Attachment_0009_Drawings_44016199_0001.pdf | ||
| B03_Attachment_0002_WDOL_Wage_Determination_140P5125R0010.pdf | ||
| B08_Attachment_0004_Past_Performance_Questionnaire_140P5125R0010.pdf | ||
| A04_Attachment_0001_SOW_44016199.pdf | ||
| B08_Attachment_0003_Price_Schedule_140P5125R0010.xls | XLS spreadsheet | |
| Sol_140P5125R0010.pdf | ||
| B08_Attachment_0005_Site_Visit_Information_140P5125R0010.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VOLUME 1 OF 2
GUCO – 227790B TABLE OF CONTENTS - 1
TABLE OF CONTENTS
DIVISION, SECTION & PARAGRAPH NUMBERING
The numbering and lettering of sections and paragraphs in this Project Manual are merely for identification.
Sections included are listed in this Table of Contents together with the number of pages in each section.
The Contractor shall check their copies of the Project Manual against this Table of Contents and confirm there are no missing pages or sections.
NUMBER TITLE NO. OF PAGES
00 01 10 Table of Contents
00 01 15 Index of Drawings
00 01 20 Contract Price Schedule
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 11 40 Work Restrictions
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Price Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 32 33 Photographic Documentation
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 42 00 References
01 50 00 Temporary Facilities & Controls
01 57 19.12 Noise & Acoustics Management
01 57 23 Temporary Storm Water Pollution Control
01 67 00 Product Requirements
01 73 29 Cutting & Patching
01 73 40 Execution
01 74 19 Construction Waste Management & Disposal
01 77 00 Closeout Procedures
01 78 23 Operation & Maintenance Data
01 79 00 Demonstration & Training
01 81 13 Sustainable Design Requirements for Non-LEED Projects
01 91 14 Total Building Commissioning
Appendix A – Submittal List
Appendix B – Closeout List
See Specifications Volume 2 for required Division 2 through 49 work.
GUCO – 227790B INDEX OF DRAWINGS - 1
INDEX OF DRAWINGS
PAGE SHEET
NO. NO. TITLE OF SHEET
GENERAL INFORMATION
1 G0.0 COVER SHEET
2 G0.1 LEGEND & ABBREVIATIONS
3 G0.2 GENERAL NOTES
4 G1.0 TOPOGRAPHIC SURVEY
CIVIL
5 C1.0 DEMOLITION PLAN – GATE 1
6 C1.1 SITE PLAN – GATE 1
7 C2.0 DEMOLITION PLAN – GATE 2
8 C2.1 SITE PLAN – GATE 2
9 C3.0 DEMOLITION PLAN – GATE 3
10 C3.1 SITE PLAN – GATE 3
11 C4.0 DEMOLITION PLAN – GATE 4
12 C4.1 SITE PLAN – GATE 4
13 C5.0 DETAILS
ELECTRICAL
14 E0.0 ELECTRICAL COVER SHEET
15 E1.0 NEW SITE PLAN
16 E1.1 SITE PLAN – GATE 1
17 E1.2 SITE PLAN – GATE 2
18 E1.3 SITE PLAN – GATE 3
19 E1.4 SITE PLAN – GATE 4
20 E6.0 SINGLE – LINE DIAGRAM
21 E6.1 SINGLE – LINE DIAGRAM II
END OF SECTION
GUCO – 227790B CONTRACT PRICE SCHEDULE - 1
CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER:
PARK - PMIS: GUCO – 227790B
DEVELOPED AREA: Guilford Courthouse Military Park
PROJECT TITLE: Replace Tour Roads & Visitor Gates
Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern.
Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government.
CONTRACT
LINE-ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI) TITLE QUANTITY
UNIT OF
MEASURE
UNIT PRICE TOTAL PRICE
1 Install New Automatic Exit Gate 1 1 LS $
2 Install New Automatic Exit Gate 3 1 LS $
TOTAL BASE PRICE (Contract Line-Item Number 1-4) ---------------------------------------------------------------- $
3 Bid Option 1 – Install Entrance Gate 2 1 LS $
4 Bid Option 2 – Install Entrance Gate 4 1 LS $
5 Bid Option 4 – Gates Maintenance Plan 1 LS $
TOTAL PRICE FOR ALL OPTIONS (Contract Line-Item Number) --------------------------------------------------- $
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line-Item Numbers 1 through 5) -------- $
DIVISION 01
GENERAL REQUIREMENTS
GUCO – 227790B 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Contractor use of the site.
4. Public use of the site.
5. Buildings.
6. Work Restrictions.
7. Special Construction Requirements.
8. Work under other contracts.
9. Government Furnished Materials.
10. Occupancy requirements for buildings.
11. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: This project is located near Greensboro, North Carolina. The Guilford
Courthouse Military Park automatic gate system project is located at 2332 New Garden Road, Greensboro, NC 27410.
B. The work consists of the following:
1. This project will remove and replace three large, manually operated wood swing gates, each over 30 years old and one, automatic swing gate operator and steel gate. Located along the tour roads and at the visitor center entrance, these gates currently control park access after-hours. The project involves replacing the existing gates and bollards with new automatic gates equipped with opening and closing systems. Sensors will be installed near the gates to detect traffic and automatically open to allow visitors to exit the park and/or staff to enter. The gates will include a manual override feature, inaccessible to the public, and a backup battery to ensure operation during electrical or system failures. Additionally, the gates located at the entrance to the Visitor’s Center and the tour loop, Gates 2 and 4, respectively, will include an emergency access control for emergency vehicles. All gates will be integrated into a unified system for seamless operation across the park.
2. The new gates will require electrical power for operation. The existing power for Gate
1 is supplied by overhead lines along Old Battleground Rd, which transition to underground power. Gate 2 will receive power from a junction box near the Visitor
Center, with lines running through the forested section of the park to the gate. For Gates
3 and 4, an existing underground power line near Gate 3 will be utilized to provide the necessary power.
GUCO – 227790B 01 11 00 - 2
C. The project will be constructed under a single prime contract.
D. Project Contacts:
1. Contracting Officer (CO): Ashley Warcewicz; NPS, Contracting Operations East
2. Project Contracting Officer Representative (COR): Dennis Williams; Kings Mountain
NMP, 2625 Park Road, Blacksburg SC 29702; Telephone: (404) 670-8942; E-mail dennis_williams@nps.gov
3. Park Superintendent: Aaron LaRocca; 2332 New Garden Road; Greensboro, NC 27410;
Telephone (336) 288-1776 ext. 221; E-mail: alarocca@nps.gov
4. Park Point of Contract: Michael Lewter; 2332 New Garden Road, Greensboro NC
27410; Telephone (336) 288-1776; E-mail: mlewter@nps.gov
1.3 WORK PHASES
A. General: Contractor shall have use of the site for construction operations. Limit the use of premises to areas within the Contract limits indicated. Do not disturb portions of the Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations within the designated perimeter of the site as specifically delineated on the construction drawings.
2. Utilities to support construction activities by the contractor:
a. Water: Contractor to install NPS approved backflow preventer at NPS specified location.
b. Power: The contractor may use power from existing facilities while working directly on the facilities. Acceptable uses are for equipment associated with the direct construction of the project. The objective of allowing the contractor to utilize power at facilities is to limit the use of portable generators when possible, to reduce noise and greenhouse gases (carbon footprint of the project).
B. Storage of Materials: Confine storage of materials within the areas as approved by the
Contracting Officer, or as outlined in the preconstruction meeting.
C. Preservation of Natural Features:
1. All equipment shall be power washed and inspected before being off-loaded to ensure it is free of non-native weeds and/or seeds. Vehicles, tools, boots, and other personal protective equipment shall be inspected for and cleaned of weed seeds or mud that could harbor weed seed before entering the Park. In addition, sources of imported rock, sand, gravel, and soil shall be inspected for invasive non-native plants, weeds, and/or seeds.
The Contractor shall submit a list of proposed sources, end-use, and temporary storage requirements for imported material, 30 calendar days before delivery. The material must not be stockpiled at the quarry for more than 1 week after washing. If material comes from older stockpiles, the quarry must be certified weed-free by a qualified weed inspector designated by NPS. The weed inspector should receive 14 days’ notice that an inspection is needed. Imported material shall be free of non-native weeds and/or seeds.
Imported material shall be shipped directly from the source to the Park without intermediary storage or staging. Shipping vessels shall be covered, if necessary, to prevent spillage or blowing of their contents while in transit.
GUCO – 227790B 01 11 00 - 3
2. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
3. Provide temporary barriers to protect existing trees and plants and root zones.
4. Do not remove, injure, or destroy trees or other plants without prior approval.
5. Do not fasten ropes, cables, or guys to existing trees.
6. Erosion control measures will be following the approved UPPP.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize the use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: The establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park
Superintendent. A special permit will not relieve the Contractor of liability for damage that may result from the moving of equipment. It is the contractor’s responsibility that following bridge load limits are not exceeded.
1.4 CONTRACTOR USE OF SITE
A. General: The contractor shall have full use of the site for construction operations during the construction period. The contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of the Project.
B. Site Access: The contractor shall access the project site from Old Battleground Road in
Greensboro, NC. The contractor shall not drive vehicles off-road or access non-project areas without permission from the Contracting Officer and Contracting Officer Representative. The contractor shall also furnish a list of personnel with phone contact information.
C. Construction Time Period: Timing of work shall be coordinated with the Contracting Officer and Contracting Officer Representative and follow the approved Contractor’s work schedule.
D. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings.
This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
E. Staging and Storage: Confine storage of equipment and materials to the staging/lay-down/storage areas identified within the area designated by the Contracting Officer and
Contracting Officer Representative or as established at the preconstruction meeting.
GUCO – 227790B 01 11 00 - 4
F. Driveways and Entrances: Keep driveways, areas specifically designated by the Contracting
Officer and Contracting Officer Representative, and entrances serving premises clear and available to Government, Government employees, user groups, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize the use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for the storage of materials and equipment on-site.
G. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
6. Prevent damage to natural surroundings or historic features such as buildings and other structures that remain in the area near construction work zones.
H. Construction Camp: The establishment of a camp within the Park is not permitted.
I. Refer also to Section 01 11 40 Work Restrictions and Section 01 50 00 Temporary Facilities &
Controls.
1.5 GOVERNMENT-FURNISHED ITEMS
A. The Government may furnish products and materials for incorporation into the work.
1. The government will arrange and pay for the delivery of government-furnished items to the project site based on the contractor’s approved construction schedule.
2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for a replacement.
3. The contractor is responsible for receiving, unloading, and handling government-furnished items at the project site for use in the work.
4. The contractor is responsible for protecting government-furnished items during storage, handling, and work, including damage from exposure to the elements.
5. If government-furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in kind.
GUCO – 227790B 01 11 00 - 5
1.6 PUBLIC USE OF THE SITE
A. General: All construction work including any or all related construction activities shall enable employees to conduct their daily activities with minimal impact and or disruption. The contractor shall coordinate all construction work including any or all related construction activities at least 72 hours in advance that have potential for impacts upon the facility operations with the Contracting Officer and Contracting Officer Representative to avoid potential negative impacts to area activities. Temporary closures may be permitted upon specific written approval of the Contracting Officer and Contracting Officer Representative.
1.7 BUILDINGS
A. Existing Buildings
1. Partial Government Occupancy: Cooperate with Government staff and visitors during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with the Government’s staff and visitors’ operations.
Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer and
Contracting Officer Representative.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
A. Limited Access: The contractor shall coordinate the scheduling of construction activities regarding limited access to the site with the Contracting Officer and Contracting Officer
Representative before and during construction.
1.9 REFERENCE DOCUMENTS/REPORTS
A. General: The following reference documents/reports are available upon request to supplement the information specified in the contract documents:
1. None.
1.10 OCCUPANCY REQUIREMENTS FOR BUILDINGS. (Not Used)
1.11 WORK UNDER OTHER CONTRACTS. (Not Used)
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
GUCO – 227790B 01 11 40 - 1
WORK RESTRICTIONS
SECTION 01 11 40
1.1 PARK REGULATIONS
A. General: The Contractor must comply with the following rules and conditions:
1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.
2. Ensure equipment is conspicuously marked for identification.
3. The Contractor shall restrict employees/representatives to the worksite and control travel directly to and from the worksite.
4. Restore all traffic/parking/security signs and markings, including space numbers, designations, and lines, to their original form if such signs/markings are defaced or deleted during construction/repair.
5. Control and provide security of Contractor-owned equipment and materials at the worksite. Report immediately missing/lost/stolen property to law enforcement and inform the Contracting Officer and Contracting Officer Representative.
6. Vehicles associated with the Contractor shall be waived the entrance fee upon entering a marked company vehicle or by providing the names of employees entering a personal vehicle(s). Please note that the entrance fee is waived only to report directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
a. The contractor will provide the Contracting Officer and Contracting Officer
Representative with a listing of its subcontractors and their associated vehicles and employees entering the park daily.
b. Contractor will provide the Contracting Officer and Contracting Officer
Representative with a listing of anticipated deliveries for each week.
7. Vehicles/Heavy Equipment:
a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings.
Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts to allow faster-moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks/pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only or as established at the preconstruction meeting.
c. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
GUCO – 227790B 01 11 40 - 2
d. Spills: The contractor shall be responsible for any cleanup efforts required by 40
CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous/industrial wastes. The contractor must immediately notify the
Contracting Officer and Contracting Officer Representative of spills.
e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.
f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to a driver with appropriate license class, medical examiner card as appropriate with license class, carrying 3 triangles or 3 flares, mounted fire extinguisher, and valid DOT safety sticker.
g. Slow Vehicles: The Contractor is to notify the Contracting Officer and Contracting
Officer Representative of slow vehicles that may cause traffic delays or extended traffic lines. Slow vehicles are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the centerline of the paved road).
Oversized vehicles must not exceed the clearances along the road corridor.
Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer and Contracting
Officer Representative of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Oversized vehicles are requested to enter the Park AFTER
2:00 p.m. and exit the Park BEFORE sunset.
i. Law Enforcement: Law enforcement will intervene if they perceive any unsafe or unlawful activity. The contractor must immediately comply with any instructions issued by law enforcement.
j. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR §
4.11). Comply with all legal load restrictions in the hauling of materials. Load restrictions on Park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on Park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve the
Contractor of liability for damage which may result from the moving of equipment.
8. Emergency Medical and Accident Reporting:
a. The Contractor or subcontractor shall contact 911 for any medical emergency or traffic accident occurring within the Park and then inform the Park Point of Contact or Contracting Officer Representative.
• Emergency number: Dial 911 as needed.
GUCO – 227790B 01 11 40 - 3
b. The Park Point of Contact or Contracting Officer Representative is called so that the entrance station will be prepared should any emergency vehicles (e.g., ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until the ambulance arrives.
c. The Contractor or subcontractor is required to report ANY personal injury and/or property damage incident occurring within the park. This report must be made to the Park Point of Contact or Contracting Officer Representative at the first available opportunity before leaving the Park:
9. Site Access
a. The contractor shall access the project site from Old Battleground Road off HWY
840 in Greensboro, NC. The contractor shall not drive vehicles off-road or access non-project areas without permission from the Contracting Officer and informing
Contracting Officer Representative. The contractor shall also furnish a list of personnel with phone contact information.
1.2 RESOURCE PROTECTION
A. General: The park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials before packing/loading. The park requires and will perform inspections to ensure non-transport of non-native species BEFORE arriving at the park entrance. Contact the Park Point of
Contact directly at least 3 days in advance of park entry to arrange for an inspection(s) at the loading dock or point of origin.
2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside the road. Contact the Contracting Officer Representative immediately if the animal is hit or injured or will not move off of the road.
3. Archaeological Resources: Archaeological resources are physical pieces of evidence of past human activity, including evidence of the effects of that activity on the environment.
Archaeological resources are found above and below the ground and underwater. The contractor shall appoint an archaeological monitor during all ground-disturbing activities in archaeologically sensitive areas. If the monitor discovers resources, the contractor shall stop work or relocate work to a non-sensitive area and contact the Contracting
Officer and Contracting Officer Representative immediately. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the Contracting Officer and Contracting Officer
Representative.
GUCO – 227790B 01 11 40 - 4
1.3 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during the hours of 7:00 AM to 5:00
PM, Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Same as On-Site Work Hours
2. Early Morning Hours: Same as On-Site Work Hours
B. Existing Utilities
1. Existing Utilities: Notify the Contracting Officer and Contracting Officer Representative and utility companies of proposed locations and times for excavation.
2. The contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made per the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer and Contracting Officer Representative not less 5 five days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: The existing utility systems may be non-operational, when required, upon specific approval of the Contracting Officer for a maximum of 4 consecutive hours. Shutdowns shall be scheduled to occur midday (e.g., 10 am – 2 pm) and mid-week (Tuesday – Thursday), if possible.
D. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
GUCO – 227790B 01 26 00 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 00
PART 1 - GENERAL
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e., structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on-site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Contracting Officer, Contracting Officer Representative
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
GUCO – 227790B 01 26 00 - 2
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e., Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions, staff and workers present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Comp – Policy and company calculation to be made available.
4) FUTA – Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA – Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
GUCO – 227790B 01 26 00 - 3
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee the satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the
Request for Proposal letter. Costs or delays resulting from the failure of the contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor, Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that they are included in the hourly rate shown, or the contractor is not requesting reimbursement.
The contractor may utilize the government provided Contractor Estimate Form or their form, provided that it contains the same information and level of detail as the
Government provided form.
http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
GUCO – 227790B 01 26 00 - 4
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction
Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. The contractor’s failure to submit within the specified time frame will be construed as the
Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. The contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing before submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include a built-in contingency.
B. Labor:
1. The contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each, and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be following the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State, or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown over $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use the latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
GUCO – 227790B 01 26 00 - 5
4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of a major overhaul is not included), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be following paragraph 1.3, D, 2, above. If the US Army
Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of the equipment costs minus any operating costs will be accepted.
7. If the equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the job site for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the job site but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented, and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in the FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups
(OH&P) for contractor self-performed work:
Overhead………………10%
Profit…………………..10%
2. The total aggregate limit of markup (OH&P) for contractors and subcontractors on modification work shall not exceed 20%. The NPS will not be responsible for the allocation of percentages between contractors and subcontractors.
3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3, E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS (not used)
PART 3 - EXECUTION (not used)
GUCO – 227790B 01 27 00 - 1
DEFINITION OF CONTRACT PRICE ITEMS
SECTION 01 27 00
A. This section intends to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Price Item No.1 – Remove Existing Manual Gate and Install New Automatic Barrier
Arm Operator at Gate 1.
1. This price item consists of furnishing all materials, equipment, and labor for the work described above, with the location of the gate and associated work detailed in the construction documents.
2. This price item includes the use of directional drilling, a trenchless method for installing utilities between the new gate and the existing power source.
3. No separate measurement will be made.
4. Payment will be made at the contract unit price Lump Sum.
B. Contract Price Item No.2 – Remove Existing Manual Gate and Install New Automatic Barrier
Arm Operator at Gate 3.
construction documents.
2. This price item includes the use of directional drilling, a trenchless method for installing utilities between the new gate and the existing power source.
C. Contract Price Item No.3 – Bid Option No.1 – Remove Existing Manual Gate and Install New
Automatic Swing Gate Operator at Gate 2.
construction documents.
GUCO – 227790B 01 27 00 - 2
2. This price item includes the use of directional drilling, a trenchless method for installing utilities between the new gate and the existing power source.
D. Contract Price Item No.4 – Bid Option No.2 –Install New Automatic Barrier Arm Operator at
Gate 4.
construction documents.
2. This price item includes the use of directional drilling, a trenchless method for installing utilities between the new gate and the existing power source.
E. Contract Price Item No.5 – Bid Option No.4 – Gates Maintenance Plan.
described above. The maintenance plan should include routine services and non-routine services.
2. No separate measurement will be made.
3. Payment will be made at the contract unit price Lump Sum.
GUCO – 227790B 01 31 00 - 1
PROJECT MANAGEMENT & COORDINATION
SECTION 01 31 00
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Construction Coordination.
2. Coordination Drawings.
3. Submittals
4. Requests for Information (RFIs).
5. Project meetings.
6. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting the Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including the establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure the efficient and orderly installation of each part of the Work.
Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in the sequence required to obtain the best results where installation of one part of the Work depends on the installation of other components, before or after its installation.
2. Coordinate the installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate the installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required, notices, reports, and a list of attendees at meetings.
GUCO – 227790B 01 31 00 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Commissioning activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of 1 week before the Preconstruction Conference. Contracting Officer will notify the Contractor of the tentative date for the Pre-Construction Conference.
1. The letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Storm Water Pollution Prevention Plan.
11. Indoor Air Quality (IAQ) Management Plan.
12. Contractors Commissioning Plan.
13. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
B. All items listed must be provided to the Contracting Officer and Contracting Officer
Representative before the Pre-Construction Conference is held. If all of these documents have not been received one week before the scheduled Pre-Construction Conference date, the conference will be canceled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to
Proceed has been issued
GUCO – 227790B 01 31 00 - 3
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: On discovery of the need for additional information or interpretation of the Contract
Documents, the Contractor shall prepare and submit an RFI utilizing the form designated by the Contracting Officer (CO).
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by the Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of the item needing information or interpretation and the following:
1. RFI number numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Contractor's suggested resolution. If the Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, the Contractor shall state impact in the RFI
Contractor’s signature.
7. Requested date for response.
8. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, and details of affected materials, assemblies, and attachments on the attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine the action required, and respond. Contracting Officer will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of the Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of the Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information, in which case time for response will date from the time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in the need for a change to the Contract
Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.5 PROJECT WEB SITE (NOT USED)
GUCO – 227790B 01 31 00 - 4
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before the start of construction, the Contracting Officer will arrange an on-site meeting with the Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .