B08_Attachment_1_REVISED_SOW_Replace_Sewage_Pumps_CACL_0001.pdf
PDF 523 KB Posted
- Attached to
- CACL - REPLACE SEWAGE PUMPS
- Solicitation number
- 140P4526R0032
About this file
This is a Statement of Work (SOW) for replacing sewage pumps and control systems at Castle Clinton National Monument in Battery Park, Manhattan, New York, issued by the National Park Service (NPS).
The project requires the contractor to remove and replace two existing submersible sewage ejector pumps and repair/replace the associated float control system and electrical infrastructure. The contractor must conduct field verification of existing site conditions prior to procurement, including wet-well dimensions, discharge piping configuration, electrical service availability, and control panel specifications. Replacement pumps must be compatible with the existing duplex pumping system, capable of handling normal, high-use, and backup operating conditions. The contractor shall submit detailed pump specifications for NPS approval prior to procurement, including manufacturer certification curves, proposed operating points (GPM and TDH), motor specifications (horsepower, voltage, phase, frequency), and compatibility documentation. The scope includes replacing approximately 20 linear feet of electrical wiring between pumps and control panel, repairing or replacing the float control box and associated components, ensuring all electrical work complies with applicable codes, and performing comprehensive testing and commissioning of the completed system. The contractor must provide all labor, materials, equipment, supervision, and tools necessary for project completion, coordinate work to minimize impacts to visitor services with potential temporary restroom closures, maintain strict resource protection and construction support standards including quality control, safety protocols, and proper debris disposal. Project closeout requires submission of complete operation and maintenance documentation, pump record documentation with nameplate photographs, and an in-person orientation meeting with facility staff prior to final acceptance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revision 01, revised 8/19/2026
CASTLE CLINTON NATIONAL MONUMENT
Battery Park, Manhattan, New York
Replace Sewage Pumps and Control System at Castle Clinton
Statement of Work (SOW)
NATIONAL PARK SERVICE (NPS)
1.0 PROJECT INTRODUCTION
Project Title: Replace Sewage Pumps and Control System at Castle Clinton In accordance with terms and conditions of the Contract, the Contractor shall perform the work of this Statement of Work (SOW) for the National Park Service (NPS) as described below.
1.1 LOCATION
This project is located at Castle Clinton National Monument, Battery Park, in the financial district of New York City.
1.2 BACKGROUND
Castle Clinton National Monument is a historic structure located in Battery Park in New York City. It serves as the primary ticketing location for ferry operations providing access to the Statue of Liberty and Ellis Island and receives nearly 4 million visitors annually. The project will remove and replace two sewage ejector pumps and re-wire the control panel at the site in order to transport sewage from the public restrooms to the city sewage system.
2.0 SCOPE OF WORK
The contractor shall provide all labor, materials, equipment, supervision, tools, transportation, disposal, and incidental services necessary to perform the following:
1. SEWAGE PUMP REPLACEMENT
• Verify all existing site conditions prior to commencement of work and procurement of replacement pumps
• Remove and properly dispose of the two existing submersible sewage ejector pumps
• Furnish and install two new heavy-duty commercial submersible sewage ejector pumps suitable for the existing wastewater service and duplex pumping system o Replacement pumps shall be compatible with the existing wet-well, discharge piping, guide-rail/slide-rail or quick-removal system, electrical service, and duplex controls o Replacement pumps shall provide hydraulic performance appropriate for the existing system and shall be capable of reliable automatic operation under normal, high-use, and backup operating conditions o Historical documentation identifies 1 HP motors for the prior replacement installation. This information is provided as historical reference and does not establish a mandatory replacement motor horsepower. Contractor shall select motor horsepower based upon the manufacturer’s certified pump performance data and the actual system requirements
• Reconnect pumps to existing piping, electrical connections, and controls, including modifications necessary to accommodate the approved replacement pumps
• Verify proper pump rotation, operation, and alternating sequence
• Confirm that the duplex pump system provides normal alternating operation, high-use supplemental pumping capacity, and backup capability
2. FLOAT SYSTEM AND CONTROLS REPAIR
• Remove failed float control wiring and associated defective components as required
• Replace and rewire the float switch system responsible for activating pump operation
• Replace or repair sensors, relays, wiring, and associated control components as required for reliable operation
• Test automatic pump activation and alarm/control functions
3. ELECTRICAL WORK
• Control panel system shall be field verified by the Contractor. Contractor shall verify compatibility of the proposed replacement pump motors with the existing electrical service and control system o Where the approved replacement pumps have electrical characteristics that differ from the existing installation, Contractor shall provide all required modifications to motor starters, overload protection, circuit protection, conductors, disconnecting means, control components, wiring, and associated equipment necessary for a complete and code-compliant installation o All modifications necessary to accommodate the approved replacement pumps shall be included in the Contractor’s work
• Replace approximately 20 linear feet of electrical wiring between the sewage pumps and control panel
• Replace conduit, watertight fittings, junction boxes, and accessories as required
• Repair or replace the float control box and re-wire all connections
• Ensure all electrical work complies with applicable codes and safety requirements
• Verify connection to the alarm system
4. TESTING AND COMMISSIONING
• Perform startup and operational testing of the completed sewage pump system
• Verify:
o Automatic pump activation o Alternating pump operation o Operation during simulated high-use conditions o Float switch functionality o Control panel operation o Alarm activation o Proper discharge to the municipal sewer system
• Provide documentation confirming successful completion of testing and commissioning
2.1 EXISTING PUMP INFORMATION
• Available historical project specifications identify the original sewage pumps as Weil Pump Co. Model 4-250216, originally supplied under SO# 310.602. Historical specifications associated with a subsequent pump replacement project identify submersible slide-rail sewage ejector pumps with the following characteristics:Motor horsepower: 1 HP
• Speed: 1,150 RPM
• Voltage: 208 VAC
• Phase: 3-phase
• Frequency: 60 Hz
• Motor construction: Hermetically sealed, air-fitted
The Government does not have complete as-built documentation or current pump nameplate information of the pumps presently installed at the site. Historical information is provided for reference and shall not be interpreted as establishing the exact model, horsepower, hydraulic duty, or required operating point of the replacement pumps.
2.2 FIELD VERIFICATION
Prior to procurement of replacement pumps, the Contractor shall field verify existing conditions necessary for proper pump selection and installation.
Field verification shall include, at a minimum:
1. Wet-well/pump pit dimensions and configuration;
2. Existing pump dimensions and available clearances;
3. Discharge piping size, configuration, and connection;
4. Pump discharge connection and elevation;
5. Existing guide-rail/slide-rail or quick-removal system configuration and dimensions;
6. Available electrical service;
7. Existing control panel and motor-control equipment;
8. Pump float/control configuration;
9. Pump lifting arrangement and access requirements; and
10. Other physical, hydraulic, mechanical, or electrical conditions affecting pump selection and installation.
Field verification shall be completed prior to procurement of replacement pumps.
The Contractor shall notify the Contracting Officer of any existing condition that would prevent installation of the proposed equipment in accordance with the requirements of this SOW.
2.3 MATERIAL LISTS
Submittals are required for all materials and equipment intended for use in this Contract. Submit to Park Facility Manager, Christopher_Wang@nps.govPump Selection and Submittal Prior to procurement, the Contractor shall submit the proposed replacement pump information to the Government for review and approval.
mailto:Christopher_Wang@nps.gov
The pump submittal shall include, at a minimum:
1. Manufacturer;
2. Exact model number;
3. Motor horsepower;
4. Voltage;
5. Phase;
6. Frequency;
7. Full-load amperage (FLA);
8. Motor RPM;
9. Pump discharge size;
10. Certified manufacturer pump performance curve;
11. Proposed operating point, including GPM and TDH;
12. Pump dimensions;
13. Pump weight;
14. Solids-passage capability;
15. Impeller, cutter, or grinder configuration;
16. Guide-rail/slide-rail or quick-removal system compatibility;
17. Motor starting requirements;
18. Electrical requirements;
19. Control-panel requirements and compatibility; and
20. Manufacturer's installation requirements.
The certified pump curve shall clearly identify the proposed operating point.
The Contractor shall not procure replacement pumps until the Government has reviewed and approved the pump submittal.
Government review and approval of the pump submittal shall not relieve the Contractor of responsibility for proper pump selection, system compatibility, or successful operation of the completed installation.
3.0 RESOURCE PROTECTION
• Visitor Experience: The contractor shall coordinate all work with the Park to minimize impacts to visitor services. Temporary restroom closures may be required during pump removal, installation, electrical work and system testing. The contractor shall coordinate work sequencing to minimize the duration of restroom outages.
Closure or rerouting of visitor areas should be avoided. Any necessary closures would be for the minimal time required to complete the work activity and must be approved by the Park.
• Air and Water Pollution Control:
Minimize tailpipe emissions, do not leave construction equipment idling longer than necessary for safety and mechanical reasons. Vehicle idling shall comply with New York City and New York State anti-idling laws.
Take necessary reasonable measures to reduce air and water pollution with material or equipment used during construction. Keep volatile wastes in covered containers.
• Construction Debris:
Construction debris shall be collected in appropriate containers and transported outside the park and properly disposed of at an approved off-site location(s) in accordance with federal, state, and local regulations. Visitor areas will remain free of any construction equipment, materials or debris.
Noise, dust, and odor-producing activities shall be controlled and minimized.
4.0 CONSTRUCTION SUPPORT
Staging Areas Limit construction storage to smallest feasible area that is not visible to visitors. Staging areas must be coordinated and approved by the Park prior to any mobilization.
Construction Zones Before construction activity, use construction plastic barriers, approved by Contracting Officer, to define construction zone/minimum area required for construction. Clearly state protection measures in the staging plan and instruct workers to avoid conducting activities beyond construction zone.
Protection of Public Use freestanding fence, barricade, or other means to block immediate work area and prevent unauthorized entry.
4.1 CONSTRUCTION COORDINATION
The Contractor shall work with Park Project Team and develop communication plan. Contractor shall coordinate all material deliveries, staging, and disposal activities with facility management.
The contractor shall provide the Park with the project schedule prior to mobilization.
Notifications Contracting Officer provides necessary written notification and/or direction to the Contractor.
On-site Contracting Officer’s Representative from the Park coordinates the Contractor’s construction efforts with daily operations and transmits/receives correspondence.
4.2 QUALITY CONTROL
The Contractor is responsible for quality of work. Independent testing laboratory is responsible for testing. Inspect and test work as needed to ensure quality of materials, workmanship, construction, and finish, and to ensure functional performance is in compliance with applicable scope of work.
The Contractor accepts ultimate responsibility, liability and duty to control quality of services provided to the Government as stipulated in FAR Part 36.609-2. Contractor shall be responsible for professional quality, technical accuracy and other services furnished by the Contractor, their Employees, Agents, Assignees, and Subcontractors under the contract. Contractor shall, without additional compensation, correct or revise any errors or deficiencies.
The Contractor shall demonstrate existence of a Quality Control (QC) system used for work submitted to NPS. Contractor and Subcontractors shall use this QC system and, at a minimum, include:
• Coordination of all construction work required.
• Verification that documents to be submitted are accurate and correct.
• Checklists for internal review of construction work, and cost estimates.
o Required documents for each submission are included and complete per contract requirements.
o Required documents have been through a QC review. NPS requires documentation and submittal of QC work performed.
• CQC Supervisor will complete CQC Daily Reports.
Testing Laboratory and Equipment:
• Person performing tests will complete test reports.
• Contracting Officer may designate test locations.
Quality Control Staff Requirements
• CQC Manager, designated by the Contractor, shall be on project site whenever contract work is in progress.
• Contractor's job supervisory staff may assist CQC Manager, as necessary, by adding certified testing technicians.
Testing Laboratory and Equipment:
• Employ certified independent laboratories to perform sampling and testing. Testing laboratory organization shall be certified for type of testing work.
• Calibrate measuring devices, laboratory equipment, and instruments at established intervals against certified standards according to National Bureau of Standards (NBS) requirements.
Quality Control Submittals:
Quality Control Plan Prior to Preconstruction meeting, submit written CQC plan for approval.
If plan requires revisions or corrections, the Contractor shall resubmit plan within 10 days.
Government reserves right to require changes to the plan during contract period as necessary to obtain quality specified.
No change in the approved plan may be made without written concurrence by Contracting Officer.
The plan shall include:
• A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
• A copy of a letter of direction to CQC Manager outlining assigned duties.
• Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
• Methods of performing, documenting, and enforcing quality control of work.
• Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
Execution of Quality Control Notify Contracting Officer at least 24 hours in advance of initial and follow-up phases.
Off-Site-Control Items fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
On-Site Control Notify Contracting Officer at least 48 hours in advance of preparatory phase meeting.
Quality Control Phases Preparatory Phase: Perform before beginning each feature of work.
• Review control submittal requirements with personnel directly responsible for quality control work. At a minimum, CQC Manager and Superintendent responsible for the feature of work shall attend.
• Ensure copies of referenced standards, related to sampling, testing, and execution for the feature of work, are available on site.
• Ensure provisions were made for field control testing.
• Examine work area to ensure preliminary work completed.
• Verify field dimensions and advise Contracting Officer of discrepancies with contract documents.
• Ensure necessary equipment and materials are at project site and comply with approved shop drawings and submittals.
• Document preparatory phase activities and discussions on CQC Daily Report.
Initial Phase: As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship.
• Review control testing procedures to ensure compliance with contract requirements.
• Document initial phase activities and discussions on CQC Daily Report.
Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.
Follow-Up Phase: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
Additional Preparatory and Initial Phases: May be required on the same feature of work for the following reasons:
• Quality of on-going work is unacceptable.
• Changes occurred in applicable quality control staff, on-site production supervision, or work crew.
• Work on a particular feature of work is resumed after a substantial period of inactivity.
Enforcement Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by quality control staff or Contracting Officer.
4.3 WORKING HOURS
Limit work and deliveries to weekday hours of 7:00 AM to 5:00 PM unless otherwise approved by Contracting Officer. Any requested work on holidays or weekends requires approval from the Contracting Officer.
4.4 ACCESS
Coordinate construction efforts with Contracting Officer towards minimal impact to the work of NPS personnel and to the visiting public.
4.5 PRESERVATION OF ADJACENT FEATURES
Confine operations to work limits of project. Prevent damage to surroundings. Restore damaged areas outside work limits, repair or replace damage at no additional expense to NPS.
4.6 EXISTING UTILITIES
Construction procedures shall include preventing accidental disruptions to facilities outside project limits by investigating existing utilities and protection during construction. Accidental disruptions shall be remedied at no cost to NPS.
4.7 ACCIDENT PREVENTION
Accident Prevention Program Prior to Preconstruction Meeting, submit accident prevention program. Program must be accepted by NPS before work on site begins and shall comply with Occupational Safety and Health Administration (OSHA) and project requirements. Include:
• Name of responsible Safety Manager to carry out the program. Submit a complete resume.
• Daily safety meetings.
• First aid procedures.
• Outline of each phase of work, hazards associated with each phase, and methods proposed to ensure property protection and safety of the public, NPS staff, and DB Construction Contractor employees.
• Training
• Planning for possible emergency situations.
• Housekeeping and fire protection.
Safety
• Perform all confined-space work in accordance with applicable safety requirements
• Provide sewage exposure protection measures, including appropriate personal protective equipment, training, and safe work practices
Accident Reporting: Report incidents to the Park
• Any accident resulting in injury to contractor’s personnel, NPS employees, or the public regardless of severity
• Any incident that causes damage to property or equipment
• Fires shall be reported immediately.
Quality Assurance Ensure employees are physically qualified to perform assigned duties safely. Do not allow employees to work if their abilities are impaired. Operators of equipment shall be able to understand signs, signals and operating instructions, and capable of operating such equipment.
Accident Prevention Products
• First aid facilities.
• Personnel protective equipment shall meet requirements of NIOSH and MSHA (National
Institute for Occupational Safety and Health and Mine Safety and Health Administration).
• Emergency instructions including telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and park police. Place in conspicuous locations at work site.
• Adequate egress at all times according to Standard for Safeguarding Construction, Alteration, and Demolition Operations (NFPA 241).
• Hard hats for employees and for up to six visitors.
• Designate and post signs in hard hat areas.
4.8 CONTRACTOR PROVIDES EQUIPMENT AND SERVICES
The contractor shall provide all personnel, services, vehicles, transportation, tools, equipment, materials, supplies, facility supervision, administration supervision and any other item(s) necessary to perform and accomplish this service. The contractor shall be familiar with all the terms, conditions, and requirement herein contained. All work must comply with federal, state and local regulations.
4.9 TEMPORARY CONTROLS
• Housekeeping: Keep project neat, orderly, and in safe conditions at all times.
4.10 PROJECT CLOSE-OUT
Project Record Documentation Maintain one complete record of all construction documentation. Clearly mark changes, deletions and additions, using NPS standards to show actual constructed conditions. Certification of accuracy and completeness are required for monthly payment requisitions. On completion of total project, submit complete project documentation.
Cleaning Before scheduling final inspection, remove tools, equipment, surplus materials, and rubbish. For surfaces damaged due to work performed under this contract, restore or refinish to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.
Remove construction debris from site. At time of final inspection, project shall be thoroughly clean, and all construction debris disposed outside of the park.
Before submitting request for final inspection, submit:
• Project Documentation: As specified above.
• Guarantees and Bonds: As specified in Performance Requirements.
• Operation and Maintenance (O&M) Data: As specified below
Operation and Maintenance (O&M) Data Prior to final inspection, provide a digital copy of O&M data to Submit to Park Facility Manager, Christopher_Wang@nps.gov and the Contracting Officer for review. Data shall include manufacturer’s standard literature, vendor-furnished as-built drawings, custom written data not included in manufacturer’s standard literature, schedules, warranties, parts lists, test results, and Subcontractor list.
After NPS completes review, incorporate comments. Submit two hard copies and one digital copy of O&M data to Park Facility Manager, Christopher_Wang@nps.gov and the Contracting Officer.
After final inspection, and before final acceptance of the project, the contractor shall schedule an in-person orientation meeting with the Park Facility Manager and facility staff, for operation of the new system.
Pump Record Documentation In addition to the O&M documentation, Contractor shall provide complete record documentation for each installed sewage pump.
Documentation shall include:
• Manufacturer;
• Exact model number;
• Serial number;
• Motor horsepower;
• Voltage;
• Phase;
• Frequency;
• Full-load amperage;
• RPM;
• Pump discharge size;
• Certified pump curve;
• Final approved operating point in GPM and TDH;
• Impeller/cutter configuration;
• Solids passage;
• Pump dimensions;
• Guide-rail/slide-rail or quick-removal system configuration;
• Motor and control requirements;
• Warranty information;
• Recommended maintenance and replacement parts; and
• Manufacturer's O&M literature
Contractor shall provide clear photographs of the nameplate of each installed pump and photographs of the completed control panel, including exterior and interior views.
The final approved pump submittal and commissioning records shall be incorporated into the project record documentation.
4.11 SUBSTANTIAL COMPLETION
Submit written certification to Contracting Officer indicating project, or designated portion of project, is substantially complete, and request inspection. Upon receiving certification, Contracting Officer and Contracting Officer’s Representative will proceed with inspection within 10 days or advise the Contractor of items preventing project from being designated as substantially complete.
When work is determined substantially complete, Contracting Officer will prepare a list of deficiencies (Punch List) for corrections before final acceptance and issue a Letter of Substantial Completion. If work is not determined substantially complete, Contracting Officer will notify the Contractor in writing. After completing work, the Contractor shall resubmit certification and request new final inspection.
Following final inspection, if work is determined substantially complete, Contracting Officer will prepare list of deficiencies for corrections before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete work described on list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, Contracting Officer may either replace or correct the work with an appropriate reduction in contract price or charge for re-inspection costs according to the contract’s Inspection of Construction clause.
Acceptance of the work: After deficiencies corrected, Contracting Officer will issue a Letter of Final Acceptance.
4.12 PROGRESS PAYMENTS Progress payments will be based on percentage of work completed on items listed in approved schedule of values. Actual construction completed and in place will form basis for payment. The Contractor shall verify percent complete under direction of the Contracting Officer Representative unless Contracting Officer waives this requirement in a specific instance. Contractor shall make computations for payment based on Government’s verification of work completed and in place for periods which progress payments are requested.
Update currently accepted construction schedule monthly. If the Contractor fails to provide monthly updates or revisions to currently accepted construction schedule, a portion of monthly payment may be retained until updates/revisions made.
APPENDIX
The below graphics are for informational purposes only and represent the existing duplex sewage pump system at Castle Clinton.
| 1.0 PROJECT INTRODUCTION |
| 1.1 LOCATION |
| 1.2 BACKGROUND |
| Castle Clinton National Monument is a historic structure located in Battery Park in New York City. It serves as the primary ticketing location for ferry operations providing access to the Statue of Liberty and Ellis Island and receives nearly 4 millio... |
| 2.0 SCOPE OF WORK |
| 2.1 EXISTING PUMP INFORMATION |
| 2.2 FIELD VERIFICATION |
| 2.3 MATERIAL LISTS |
| 4.0 CONSTRUCTION SUPPORT |
| 4.1 CONSTRUCTION COORDINATION |
| 4.2 QUALITY CONTROL |
| 4.3 WORKING HOURS |
| 4.4 ACCESS |
| 4.5 PRESERVATION OF ADJACENT FEATURES |
| 4.6 EXISTING UTILITIES |
| 4.7 ACCIDENT PREVENTION |
| 4.9 TEMPORARY CONTROLS |
| 4.10 PROJECT CLOSE-OUT |
| 4.11 SUBSTANTIAL COMPLETION |