This document contains a series of questions and answers related to Solicitation #140P4524Q0020 for Boat Ramp and Barge Transportation Services for the Statue of Liberty National Park (STLI). The solicitation is for the transportation of waste removal trucks, equipment, and various materials to and from the Park.

Key details include:

  • The contractor is required to provide a ramp barge and means of transporting the barge. The government will provide the waste containers to be transported.
  • The contract is expected to be for more than one year, but the exact duration is still being determined.
  • The government estimates an average of 2 round trips per month for waste transportation, plus up to 21 additional round trips for other purposes.
  • The quote submission deadline will not be extended, as the current contract expires on March 31st and the new contract needs to be in place by April 1st.
  • The solicitation includes attachments with details on the work scope, delivery locations, and example ramp barge pictures.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract: Barge Follow-On

Solicitation# 140P4524Q0020

Number Question Solicitation Reference Response Date

Request for extension on the submission required in the attachments, please confirm extension of the deadline.

Solicitation pg. 6

Please submit your questions as soon as possible and we’ll do our best to respond to them. However, at this time we are hesitant to extend the deadline for quote submissions with the need date for services being 1 APR 2024.

Could you please clarify what you mean by the submission requirements in the attachments? Do you mean the quote submission date in the solicitation? Or are you referring to Attachment 2 Park ID info, because that won’t be required until after award.

3/21/2024

Please clarify if we are to provide the barge and the vessel to transport or just provide transportation?

SOW Paragraph 3.1.1.

The use of vessel refers to the barge itself. To remove any ambiguity, the word "vessel" has been removed. Additional information has been included in Attachment 1, SOW Rev1, paragraph 2.3, to clairfy the Contractor shall provid a ramp barge and provide means of transporting the barge to and from the Park. In addition, see Attachment 4, Example Ramp Barge Pictures for the ramp barge requirements.

3/21/2024

In reference to item 3.1.1: Please confirm the waste containers are being provided by the client.

SOW Paragraph 3.1.1.

This requirement is for transportion of equipment and materials such as the waste containers. Supplying or providing waste containers is not the responsibility of the Contractor on this requirement. The Waste Containers are the property of the waste management Contractor and they will be responsible for providing the trucks and containers to manage the waste.

3/21/2024

In reference to item 3.2: Please clarify that the Contractor is providing the vessel.

SOW Paragraph 3.2 Yes. The Contractor is responsible for providing the barge ramp and the barge vessel to transport tools, equipment, etc. The Contractor is not responsible for providing and of the items requiring transportation.

3/21/2024

5 Who provides the barge? SOW Paragraph 2.3 The Contractor provides the barge. Paragraph 2.3, 3.2, and 3.3 have been updated to provide clarity.

3/21/2024

6 Better idea of how often round trips will be required? N/A

The frequency of trips varies; however historically we've had an average number of 2 trips per month for waste transportation. All other trips are dependent upon variable requirements, which is why the Government will use service calls IAW Attachment 1, SOW Rev 1, Section 5.0. Historically service trips occur more frequently in the warmer months of the year when more visitors are accesing the Park and construction and facility repairs and modifications are able to be completed.

3/21/2024

7 What was the previous award amount and information? N/A

IDIQ Contract #: 140P4518D0004 IDIQ Ordering Period (Base +4 & 6-mo extension (5.5 years): 07/01/2018 - 12/31/2023 PoP: Orders not to exceed 12 months from order date IDIQ Ceiling: $432,000.00 Awardee: Miller's Launch, Inc.

3/21/2024

This only a 1 year contract. Will it be a base year with (4) 1 year option periods after this 1 year agreement?

N/A The Government does intend to complete a contract that will be for more than a year;

however, the exact number of years, type of contract, etc. is still in discussion. This information will be provided at a later date as a part of the follow-on solicitation.

3/21/2024

9 Quote submission date being extended five (5) days from now? SF 18, Block 10, and page 5.

Unfortunately we are not able to extend the submission due date. The current contract expires on March 31st and we need to have the new contract in place by April 1st.

3/21/2024

10 What location are picking up at the Statue? SOW, Section 3.0.

Locations are listed in Attachment 1, Statement of Work Rev. 1, Section 8.0. In addition, we've included Attachment 3, Beach Landing and Dock Location to better identify the locations. 3/22/2024

We can start to look at other locations to off-load however we will need a few more days to put bid together

SOW, Sections 2 and 3, and SF 18, page 4

Attachment 1, Statement of Work Rev. 1, paragraph 2.3 was revised to require the location of the mainland boat ramp be provided after contract award. Solicitation page 4, Technical Approach has also been revised as follows to remove the requirement to provide the boat ramp location and instead requires Contracrors to provide evidence they will be able to provide access to a mainland boat ramp. Additionally, FAR Provision 52.212-2, has been revised to state technical acceptability for the boat ramp location will be based on the Contractor submitting evidence they will provide a mainland boat ramp, rather than already having access to one.

3/22/2024

12 Is it a total of 42 trips on a set schedule?

SOW, paragraph 2.2, and SF 18 Block 11, Schedule and page 4.

The number of trips varies depending on work projects, such as construction requiring transport of equipment, etc., being done at the Park locations. Our estimated number of roundtrips to transport waste material averages to approximately 2 per month for a total of 24 per year. For the other 21 estimated roundtrips, those we are uncertain whether we will need them or not. Due to this we have revised the CLIN structure to have two CLINs, one for the 24 trips we are pretty certain of, and one set up as an IDIQ for the other CLIN with an NTE of 21 roundtrips. See Attachment 1, Statement of Work Rev. 1, paragraphs 2.2, 3.1.1 and 3.1.2.