B09-SOW-Replace_and_Install_For_(4)_Flagpole_0001.docx

DOCX document 28 KB Posted

Attached to
CACO-FLAGPOLE REPLACEMENT Federal contract opportunity
Solicitation number
140P4326R0035
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This is a Performance Work Statement (PWS) for the replacement and installation of flagpoles with lighting at four locations within Cape Cod National Seashore under the National Park Service. The contractor shall remove existing flagpoles and furnish and install four new 35-foot aluminum or fiberglass flagpoles with marine-grade, corrosion-resistant finishes rated for 90-120 mph winds at Salt Pond Visitor Center (Eastham, MA), Marconi Headquarters (Wellfleet, MA), Race Point Ranger Station (Provincetown, MA), and Provincelands Visitor Center (Provincetown, MA). Each flagpole installation includes a concrete foundation 5-7 feet deep with ground sleeve and drainage, LED lighting systems compliant with U.S. Flag Code (solar-powered or hardwired with photocell control), and complete site restoration including backfill, soil compaction, and landscape restoration.

The contractor is responsible for mobilization, utility protection coordination via Dig Safe/811, removal and offsite disposal of existing flagpoles, electrical work including trenching and conduit installation per NEC standards, testing and commissioning of all systems, and safety and environmental compliance per OSHA and NPS standards. The estimated project duration is 4–6 weeks with work sequenced to minimize disruption at visitor facilities. Contractor-provided materials include flagpoles, concrete, LED fixtures, electrical components, and excavation equipment. Warranty requirements include minimum 10-year manufacturer warranty for flagpoles, 3–5 years for lighting systems, and 1-year workmanship warranty. A mandatory site visit is scheduled for Tuesday, August 18, 2026, at 9:00 a.m. EDT at 99 Marconi Site Rd, Wellfleet, MA 02667.

View the file

Other files for this federal contract opportunity

Other files attached to CACO-FLAGPOLE REPLACEMENT, newest first.
File Type Posted
Sol_140P4326R0035_Amd_0002.pdf PDF
B11-_Attendance_Record_0002.pdf PDF
B09-RFIs_1-5_0001.docx DOCX document
Sol_140P4326R0035_Amd_0001.pdf PDF
Sol_140P4326R0035.pdf PDF
A04-Replace_and_Install_4_Flagpole_at_CACO.docx DOCX document
B03-WD-MA20260001-Mod3-7_28_26.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

Replacement and Installation of Flagpoles with Lighting

CAPE COD NATIONAL SEASHORE

National Park Service

1. PROJECT LOCATIONS

Work shall be performed at the following four (4) locations:

· Salt Pond Visitor Center – Eastham, MA

· Marconi Headquarters – Wellfleet, MA

· Race Point Ranger Station – Provincetown, MA

· Provincelands Visitor Center – Provincetown, MA

2. PROJECT DESCRIPTION

The Contractor shall provide all labor, materials, equipment, and supervision necessary to:

· Remove existing flagpoles (if present)

· Furnish and install four (4) new 35-foot flagpoles

· Install flagpole lighting systems compliant with U.S. Flag Code

· Restore all disturbed areas All work shall comply with National Park Service (NPS) standards, local codes, and applicable federal regulations.

A site visit is highly recommended.

3. SCOPE OF WORK

3.1 Mobilization & Site Preparation

· Mobilize personnel, materials, and equipment to each site

· Coordinate access with NPS staff

· Identify and protect existing utilities (call Dig Safe/811)

· Establish staging areas with minimal environmental impact

3.2 Removal of Existing Flagpoles

· Remove existing flagpoles, foundations, and associated hardware

· Properly dispose of materials offsite in accordance with regulations

· Backfill and temporarily restore areas as needed

3.3 New Flagpole Installation

Each location shall receive:

Flagpole Specifications

· Height: 35 feet

· Material: Aluminum (satin or anodized finish) or fiberglass (as approved)

· Type: External halyard with cleat or internal halyard (vandal-resistant preferred)

· Wind Rating: Minimum 90–120 mph (coastal compliant)

· Base: Ground-set or anchor base system

· Finish: Corrosion-resistant (marine/coastal grade) Foundation

· Concrete footing designed per manufacturer specifications

· Typical depth: 5–7 feet (or as required by soil conditions and wind load)

· Include ground sleeve and drainage gravel

3.4 Flagpole Lighting Installation

Lighting shall comply with U.S. Flag Code requiring illumination during nighttime display.

Lighting Requirements

· LED flagpole lighting fixture (ground-mounted or pole-mounted)

· Solar-powered or hardwired (as specified by site conditions)

· Photocell-controlled automatic operation

· Corrosion-resistant fixtures suitable for coastal environments

· Minimum illumination sufficient to fully light flag Electrical Work (if hardwired)

· Install conduit, wiring, and connections per NEC

· Provide weatherproof junction boxes

· Tie into existing electrical service (coordinate with NPS)

· TRENCHING will need to be done to run conduit and electrical to Flagpoles

3.5 Site Restoration

· Backfill excavations and compact soil

· Restore lawns, pavement, or landscaping to original condition

· Remove all debris and construction materials

· Ensure sites are clean and safe for public use

3.6 Testing and Commissioning

· Verify flagpole alignment (plumb and level)

· Test halyard operation

· Test lighting systems (day/night operation)

· Correct deficiencies prior to acceptance

4. MATERIALS & EQUIPMENT

Contractor shall provide:

· Flagpoles (35 ft, marine-grade)

· Concrete and reinforcement materials

· LED lighting fixtures and controls

· Electrical components (if applicable)

· Excavation and lifting equipment

5. SAFETY REQUIREMENTS

· Comply with OSHA standards

· Provide traffic/pedestrian control where required

· Use fall protection and proper rigging for pole installation

· Protect visitors and staff during construction

6. ENVIRONMENTAL PROTECTION

· Minimize disturbance to natural and cultural resources

· Prevent erosion and sedimentation

· Properly manage and dispose of waste materials

· Avoid impacts to sensitive coastal areas

7. SCHEDULE

· Estimated Duration: 4–6 weeks total

· Sequence work to minimize disruption at visitor facilities

· Coordinate schedule with NPS site representatives

8. SUBMITTALS

Contractor shall provide:

· Shop drawings and flagpole specifications

· Foundation design details

· Lighting cut sheets

· Work schedule

· Warranty information

9. WARRANTIES

· Flagpoles: Minimum 10-year manufacturer warranty

· Lighting systems: Minimum 3–5 years

· Installation workmanship: Minimum 1 year

10. ACCEPTANCE CRITERIA

Work will be accepted upon:

· Successful installation at all four sites

· Functional lighting systems

· Proper site restoration

· Submission of all documentation

11. EXCLUSIONS

· Utility upgrades beyond connection point

· Major site grading or drainage improvements

· Structural redesign due to unforeseen subsurface conditions