Sol_140P4326R0024_Amd_0002.pdf

PDF 3 MB Posted

Attached to
COLONIAL NATIONAL HISTORICAL PARK - REPLACE HVAC Federal contract opportunity
Solicitation number
140P4326R0024
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This is Amendment 0002 to a federal solicitation for HVAC replacement services at Colonial National Historical Park's Jamestown Historic Research Center facility.

The amendment corrects a technical posting issue with Amendment 0001 and provides an amended Project Manual that revises air handler requirements from 4-ton units to 5-ton units. The contract scope includes replacement of two existing split HVAC systems with new 5-ton heat pumps and compatible multi-position air handlers, each with 10kW heating elements. Work includes connecting new equipment to an existing control system, integrating with existing ductwork (with modifications as needed), mounting heat pumps to existing pedestals, flushing and reusing existing line sets if appropriately sized, performing proper refrigerant charging, ensuring equipment breakers and disconnects meet manufacturer specifications, and conducting industry-standard installation procedures including nitrogen pressure tests and vacuum line set procedures to sub-500-micron levels. All equipment must be from a single manufacturer and fully compatible. The contract requires proper disposal of removed equipment and recovery of refrigerants per applicable regulations. The project location is 1365 Colonial National Historical Parkway, Williamsburg, Virginia 23185. The performance period runs from July 1, 2026 through December 30, 2026, with work conducted between 7:00 AM and 4:30 PM. Contractor must provide liability insurance, warranty information, equipment specifications, and equipment manuals. A minimum 1-year warranty against defects and 1-year warranty for workmanship are required. The contracting officer is Jason Albright at Boston National Historical Park (NPS, NER). A pre-bid site visit was conducted on May 28, 2026, with attendees listed in the amendment documentation.

View the file

Other files for this federal contract opportunity

Other files attached to COLONIAL NATIONAL HISTORICAL PARK - REPLACE HVAC, newest first.
File Type Posted
B08_Solicitation_Attachment_4_Project_Manual_Amended_0001.docx DOCX document
Sol_140P4326R0024_Amd_0001.pdf PDF
B08_Solicitation_Attachment_3_Construction_Contract_Administration.docx DOCX document
Sol_140P4326R0024.pdf PDF
B08_Solicitation_Attachment_1_Project_Manual.docx DOCX document
B08_Solicitation_Attachment_2_DOL_Wage_Determination_VA20260157.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Jason Albright

See continuation page

NPS, NER - NE MABO

Boston National Historical Park Charlestown Navy Yard Building I-1 Boston MA 02129-4543

PNN

140P4326R0024

05/28/2026

05/14/2026

1 14

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P4326R0024/0002

Colonial National Historical Park - Replace

HVAC at Jamestown Historic Research Center

The purpose of this amendment is to correct a technical issue that prevented Amendment 0001 from posting to SAM.Gov, and to include information provided in Amendment 0001:

The purpose of Amendment 0001 is to provide an amended Project Manual/Summary of Work and provide the list of attendees to the organized pre-bid site-visit, conducted on May 28, 2026.

Therefore:

1. Attachment 4 - Project Manual_Amended is provided as an attachment to this amendment.

This amended Project Manual revises the requirements for the Air Handlers from 4-Ton units to 5-Ton units.

2. List of attendees to the May 28, 2026, site visit is attached.

Period of Performance: 07/01/2026 to

12/30/2026

COLO PMIS 226934 AMENDED May 28, 2026

COLONIAL NATIONAL HISTORICAL PARK

Yorktown, Virginia

Replace HVAC at Jamestown Historic Research Center

PROJECT MANUAL

Summary of Work

NATIONAL PARK SERVICE

AMENDED May 28, 2026

STATEMENT OF WORK

Replace HVAC at Jamestown Historic Research Center

1365 Colonial Nat’l Hist. Parkway Williamsburg VA 23185 Colonial National Historical Park (COLO)

Virginia

PART 1 - GENERAL

1.01 DESCRIPTION OF WORK

A. This contract provides for the replacement of two existing split systems. The units being replaced are a 5-ton HVAC Liebert air handler (up-flow, multi speed), 5-ton Carrier air handler, and 2 Goodman heat pumps.

Newly installed equipment will be connected to an existing control system. All new equipment shall be from a single manufacturer and fully compatible with all components in the system.

1. The building is a two-story office with additional crawl space. The structure was built in 2006.

2. The building will be occupied during this contract.

B. The contract work includes:

Base Work:

• Replacement of two existing split systems with new 5-ton heat pumps and compatible multi position air handlers.

• Both air handlers require heating elements of 10kw.

• New air handlers must be tied in with existing ductwork which may require some modification and add-ons.

• Downstairs air handler unit will require a plenum box & additional ductwork to connect wall return to air handler unit

• 2 new heat pumps must be mounted to existing pedestals.

• Existing Line set for units must be flushed and new equipment tied into existing line set if size is in accordance with manufacturer. If line set is not appropriately sized new line set must be installed.

• Once new units are installed proper charge of refrigerant must be confirmed in accordance with manufacturer’s specifications.

• Ensure equipment breakers and disconnects are rated to manufacturer’s specifications.

• All units must have appropriate disconnects with line voltage monitoring and surge protection.

• All equipment must be from a single manufacturer and fully compatible with all features.

• All installations must be to industry standard including nitrogen pressure tests for leak tests and braising, pulling of vacuum line set to sub-500-micron level.

• All removed equipment must be disposed of properly.

• All removed refrigerants must be recovered and disposed of by all applicable regulations.

C. All work will be performed under a single contract.

D. Work and materials shall adhere to the following mitigations:

1. All Parts and Equipment must operate effectively and efficiently together.

2. Materials shall be stored at work location.

1.02 LOCATION AND ACCESS

A. The project site is located at 1365 Colonial Nat'l Historical Pkwy, Williamsburg, VA 23185.

1.03 CONTRACTOR-FURNISHED ITEMS

A. The Contractor shall furnish all necessary supervision, personnel, equipment, transportation, materials, and incidentals required to complete the contract requirements.

B. Contractor shall provide proof of liability insurance for all personnel working in completion of this project.

1.04 WORK CONDITIONS AND LIMITATIONS

A. FACILITY USE

1. There are open public restrooms within walking distance of work location.

B. REQUIRED PERFORMANCE PERIOD

1. Work performance period is to be determined; all work shall be performed between 7 AM – 4:30 PM.

C. CONTRACTOR’S USE OF PREMISES

1. Confine on-site material storage, equipment and vehicle parking, and staging to paved parking areas or other areas specifically designated by the Contracting Officer’s Representative (COR).

2. Keep job site clear of trash and debris. Dispose of any trash, debris and other unusable material legally at authorized facilities on non-Federal land.

D. FIELD VERIFICATION

1. The measurements and quantities specified are estimates and provided for information only. The Contractor must verify all locations, dimensions and conditions affecting the work.

1.05 QUALITY ASSURANCE

A. All proposed materials and methods must meet or exceed the current local, state, and federal codes, standards, and regulations applicable to the contract work.

B. All personnel performing work shall be fully qualified and experienced in the type of work they will execute.

1.06 WARRANTIES

A. Building components: Minimum 1-year warranty against defects. Provide a minimum 1-year warranty for workmanship.

B. Prior to beginning work, report to the COR work scheduling or material availability before proceeding with the work.

1.07 MATERIAL HANDLING

A. Deliver materials to the job site as per COR instructions. Comply with all manufacturers’ recommendations for storage, protection and handling.

PART 2 - MATERIAL

2.01 GENERAL

A. Use new materials except as otherwise approved by the Contracting Officer (CO).

2.02 REQUIRED SUBMITTALS AND APPROVALS

A. LIST OF REQUIRED SUBMITTALS

1. Contractor Liability Insurance

2. Warranty Information

3. Equipment Specifications

4. Equipment Manuals/Operation Guides

5. Final Walkthrough with designated park staff for operational check

B. CHANGES TO MATERIAL REQUIREMENTS

1. Any proposed changes by the Contractor to the construction materials shall be submitted in writing to the

COR

PART 3 - EXECUTION OF WORK

3.01 GENERAL

A. SERVICE INTERRUPTION

1. Indicate by work schedule expected periods of construction to avoid conflict with operations.

B. SITE INVESTIGATION

1. The Contractor is responsible for investigating site conditions in the vicinity of the required work for any hazards or obstacles which may increase time or cost of the work.

C. CHANGES TO CONSTRUCTION METHODS

1. Any proposed change by the Contractor to the specified construction methods and manufacturer’s instructions must be submitted in writing to the CO along with the justification for the proposed change.

Approval from the CO is required for changes in specified construction methods.

D. PROTECTION OF WORK SITE

1. Work site is not protected and is open with no fencing.

2. Maintain the work area and approaches clean and free from trash and debris to reduce interference with ongoing maintenance operations.

3. Provide a safe bypass for NPS employees, and contractor’s personnel.

3.02 PROJECT CLOSEOUT

A. CLEANUP

1. Remove all tools, equipment, excess materials, construction debris, and trash from the project site. Leave project site clean and ready for use at the time of final inspection.

2. Legally dispose of all excess and unusable materials at authorized disposal facilities.

B. FINAL INSPECTION AND ACCEPTANCE OF WORK

1. When all work including any site restoration and cleanup has been completed, the Contractor shall contact the COR to arrange the final inspection.

2. The Contractor shall be notified of any deficiencies found during the final inspection. After all deficiencies have been corrected and all required closeout submittals have been forwarded to the COR, the CO will issue a letter of final acceptance and request the release of claims.

C. CLOSEOUT SUBMITTALS

A. Provide to the COR the following closeout submittals and any other closeout submittals required by the CO:

1. Cut-Sheet Binder: Submit one binder with all manufacturer product information and cut-sheets for all materials installed under this contract. Label binder with project title and include one “contents” page.

PART 4 – PAYMENT

1. Final payment shall be processed upon confirming all noted contractor performance deficiencies have been satisfactorily corrected.

PART 5 – POC’s

1. Project COR will be Joseph Lamm, Supervisory Facility Operations Specialist, Colonial National Historical Park, Cell: 757-272-9847, Email: Joseph_Lamm@nps.gov

2. Alt POC Matt Henderson, Supervisory Facility Operations Specialist, Colonial National Historical Park, Email: Matt_Henderson@nps.gov

Statement of Work (SOW)

Attachment A

Project Site Map

Attachment B

Photos of Existing Conditions

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110