B09-Attachment_12_-_RFIs_1-74_0004.xlsx
XLSX spreadsheet 26 KB Posted
- Solicitation number
- 140P4326R0021
About this file
This is a Requests for Information (RFI) Q&A document containing 74 numbered inquiries and government responses related to a National Park Service construction rehabilitation project at Boston National Historical Park in Charlestown, Massachusetts (Solicitation 140P4326R0021). The project involves rehabilitation work on four buildings: Charlestown Building 1 (base scope), Building 124 (Option 1), USS Constitution Museum (Option 2), and Commandants House (Option 3).
Key clarifications from the RFI responses indicate that electrical work on Building 1 has been removed entirely from the contract scope, eliminating numerous electrical service, panel, conduit, and wiring questions. For Building 1 masonry work, contractors must remove all dense vegetation from the west elevation and complete approximately 10% repointing; no new weeps should be added. Regarding windows and roofing, ACM-containing materials are being addressed separately for remediation and no ACM exists on the roofing system to be replaced; mold remediation mentioned in the SOW was included in error and is not in scope. New roof drains shall connect to existing interior drainage piping. For Building 22 and 28 museum work, bedding glazing removal is required, interior casings and moldings are excluded except for damaged sash stops, and linseed oil paints shall be used. Contractors have discretion on window removal quantities provided temporary coverings are installed and operational convenience is maintained. Building 124 requires coordination with existing jersey barrier relocation, and no active electrical power currently exists at the site. The contractor must remove all materials from Building 124 and coordinate with the Contracting Officer's Representative regarding relocation to adjacent Building 24. The proposal submission deadline was extended to July 28, 2026, at 10:00 a.m. EDT, and award options will be determined within 60 days of contract award with concurrent work anticipated if all CLINs are funded.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| BOST Rehabilitate Buildings | |||
| 140P4326R0021 | |||
| RFI # | RFI | Government Response | Referance |
| 1 | There is no west elevation provided on the plans. The only note regarding the west elevation is on the Roof Plan A1.1 which states "REMOVE VEGETATION ALONG STONE WALL, ASSUME 10% REPOINTING REQUIRED" . Please confirm that all vegetation (very dense) shall be removed from the west elevation, entire elevation shall be cleaned and repointed 10%. | On Sheet A1.1 of the Building 1 plans, the note regarding vegetation and pointing is accurate. Vine growth has created maintenance issues on the roof and complete removal from the west elevation is required to improve future maintenance of the roof. It is anticipated that as vines are removed, some tuck pointing may be necessary. The 10% pointing is based on this assumption. |
| 2 | E101 indicate (2) new 4" conduits shall be provided from the manhole to building 1, however E100 indicates existing conduits and manholes shall be reused to pull new feeders to building 1. Please advise. | Electrical Work on Building 1 has been removed from the scope. |
| 3 | Please advise is the contractor will be responsible for Utility Company charges for the new transformer. Please be advised it will be impossible to get actual cost estimate from the Utility Company prior to bidding. For bidding purposes, should an allowance be included for Utility Company charges so all bidders are carrying the same cost for this currently undetermined item? | Electrical Work on Building 1 has been removed from the scope. |
| 4 | Please clarify if doors 01,02,06 and 07 are to be replaced in their entirety. | No replacement is included in this project. Please review A2.0 and A6.0 for paint and repair requirements for these doors and openings. |
| 5 | Please confirm overhead garage doors are existing to remain. What is the extent of the repair? | Garage doors are to remain. Extent of repairs are limited to rails, stiles and panels of doors 3, 4 & 5. Review A2.0 and A6.0 for repair notes. |
| 6 | Is there a detail for the lintel repairs? | No. Keynote #1 on sheet A2.0 just states "replace jacked lintel in kind". Assume materials and installation to remain identical to original. Review specifications section 055000, subpart 2.06 "loose steel lintels" for information on lintel materials. |
| 7 | Please clarify window scope. D1.2 indicates ACM window glazing, however the drawings do not indicate any scope relative to the windows. | Windows highlighted with ACM are being addressed separately for remediation. |
| 8 | Please clarify skylight scope. D1.2 indicates ACM window glazing, however the drawings do not indicate any scope relative to the skylight. | Skylight highlighted with ACM are being addressed separately for remediation. |
| 9 | Please confirm there is no ACM relative to the exiting roof to be demolished. 070150.19 has several mention of asbestos abatement, but I don't see any information indicating ACM associated with the existing roofing to be demolished. | No ACM is known to exist on the roofing system to be replaced under this contract. Should ACM be discovered in the course of work, any removal would be addressed as a contract modification. |
| 10 | Please clarify mold abatement scope of work if any. The Summary of Work 011100 and the Hazardous Materials report mention mol and/or mold remediation, however there is no scope on the drawings or corresponding spec sections for mold | 011100 does include mention of mold remeditation. That appears to be included in error and no mold remediation is included in this scope. |
| 11 | Please confirm new roof drains to be tied into existing piping. | Yes, new roof drains described on sheet P102 shall be connected to the existing interior roof drainage piping. |
| 12 | Is a duct bank detail available for new duct bank shown on E301? | Electrical Work on Building 1 has been removed from the scope. |
| 13 | Please confirm there is no window scope | No. The extent of repairs to openings is limited to openings 2, 3, 4, 5 for repairs to heads and jambs. |
| 14 |
Missing Drawings: E-002 and E-200
Additional Drawings no in Drawing List: E-201, E-300 and E-301
| Electrical Work on Building 1 has been removed from the scope. | Clarification on Drawings for Building 1. | ||
| The spare 4" conduit from the new utility transformer to Building #1 is labeled (C420N), which indicates 4#600kcmil+1#2g-4"c. Should this be labeled as an "Empty Spare" instead? | Electrical Work on Building 1 has been removed from the scope. | Refer to E300 - | |
| Branch Panel APL-1 shows a Main Breaker Rating of 200a, but the one-line diagram directly below shows the same panel with a 400a Main Circuit Breaker. Could you please clarify which is correct? | Electrical Work on Building 1 has been removed from the scope. | Refer to E300 - | |
| Also, it shows New Panel APL-2 What size is this panel? And there is No reference for Sub Feed Panel (C210N) Please clarify? | Electrical Work on Building 1 has been removed from the scope. | ||
| 15 |
| Please clarify painting scope for Building 22 and 28 | Painting details can be found on sheets, A2.1 through A6.5. Linseed oil paints shall be utilized for this work. | Building 22 | ||
| 16 | Please specify if it is the intention to remove all bedding glazing as well. This would require complete removal of all panes of glass which drastically increases the likelihood of breakage and cost. | Yes, per contract drawings, bedding glazing shall be removed as well. | Building 22. Please reference specification section 02 82 00 para 1.2.A.4.b and drawing sheets AD1.1 thru AD1.4. | |
| 17 | Window Repair Schedule. Please confirm if the interior windows casings/moldings are included in the scope of work and that they should be restored per the Restoration Treatment column for interior. | Interior casings and mouldings are not part of this scope. The only exception are interior sash stops if stops are missing, or damaged beyond repair. | Bldg 22 & 28 - Museum: Refer to Dwg A6.1 & A6.4. | |
| 18 | Can another site visit be accommodated for bidders? | No. With exception of some interior areas, the majority of the areas within the project scope are viewable from the exterior every day of the week. | ||
| 19 | Will the project testing requirements be performed in accordance with the INTERNATIONAL BUILDING CODE and the INTERNATIONAL EXISTING BUILDING CODE | Yes, NPS standards follow ICC and not Boston or State of Massachusetts code requirements. | ||
| 20 | Confirm that the slate roofing and felt underlayment has been tested for ACM | For the Commandant's House, the underlayment has not been tested for ACM. | ||
| 21 | Provide the maximum quantity of wood windows that can be removed and restored at any given time . | This is up to the discretion of the vendor. All windows that are removed will need to have temporary coverings installed and the facility will remain occupied and open to the public throughout this work. The number of windows removed shall not create an operational inconvience for the museum and its employees. | ||
| 22 | Can full elevations of wood windows be removed and restored at the same time? | Yes, but, All windows that are removed will need to have temporary coverings installed and the facility will remain occupied and open to the public throughout this work. The number of windows removed shall not create an operational inconvience for the museum and its employees. | ||
| 23 | E300 one-line drawing shows the service size as 400Amps. The panel schedule shows the main breaker as 200Amp. The SOW, section 1.2 part B 2 also calls for the size to be 200Amp.Need to know the correct size service they want for both the new and future. | Electrical Work on Building 1 has been removed from the scope. | ||
| 24 | E300 one-line shows two panels (APL-1 & APL-2). They only show one panel schedule for APL-1. Can you request the characteristics of APL-2. | Electrical Work on Building 1 has been removed from the scope. | ||
| 25 | E300 one-line shows a second conduit from the manhole for a future service. Do we need to include wiring in this conduit back to the transformer or will an empty conduit with pull string be acceptable. | Electrical Work on Building 1 has been removed from the scope. | ||
| 26 | E300 one-line shows a new disconnect switch. Should that disconnect be fused or non-fused | Electrical Work on Building 1 has been removed from the scope. | ||
| 27 | The SOW, section 1.2 part B 2 states no new electrical wiring or outlets. Drawing E101 shows a new receptacle installed next to the panel. Drawing E201 shows new recess lighting. Should we include this work? | Electrical Work on Building 1 has been removed from the scope. | ||
| 28 | Has the NPS verified the conduit sizes we are to repurpose shown on E301 | Electrical Work on Building 1 has been removed from the scope. | ||
| 29 | Please confirm the anticipated exercise date and bid hold period for each CLIN. | options will be awarded within 60-days of award | Sol. Form 330 | |
| 30 | Pending funds, is it the intent for all work to be awarded and completed concurrently? | yes | Sol. Form 330 | |
| 31 | Please clarify the required permits. | These permits typically relate to portions of the work that are not regulated by the awarding agency. This can include permits for disposal of hazardous materials, modifying a utility not owned by the agency or encumbering a public right-of-way that is outside the jurisdiction of th agency in order to accomplish the objectives of this contract. | Sol. Page 56 of 83 | |
| 32 | Please confirm the site supervision requirements if all CLINS are awarded concurrently. Can one person serve multiple hats, such as the superintendent also serving as the site safety officer? | Yes, one person can be assigned these roles. That individual however must meet the requirements for each role assigned. | 011000 | |
| 33 | Can the government provide clarification on if there are any exceptions to the Secretary's historical preservation guidelines that were pre-approved during the development of this solicitation. | There are no exceptions to the Secretary's guidelines. | 13591 | |
| 34 | Please provide the assumed weather days per month for the project weather calendar. | This is up to the contractor to determine how many days they want to schedule for potential weather related delays. | 13216 | |
| 35 | Please confirm the accepted schedule format, MS Projects, P6, etc. | NPS currently does not have approval to use either of these systems. Schedule format can be forwarded to the COR as MS Office Suite document or PDF. | 13216 | |
| 36 | Please advise if each CLIN, if awarded, will be turned over as the work is accepted. Will each CLIN have a separate warranty period based on final acceptance and punch out? | The contract as a whole will be the warranty period. Once the whole contract is complete and punch list items completted the warrantly period will start. | 017700 | |
| 37 | Please confirm coordination drawings are not required and that redline PDF as-builts are acceptable. | Redline PDFs for coordination and for as-builts will be acceptable | 013100 | |
| 38 | Please confirm any requirements that exist to conceal electrical panels, conduits, etc. to preserve historical character. | Electrical Work on Building 1 has been removed from the scope. | 013591 | |
| 39 | Please provide additional surveys or assumed quantities for mold remediation work. | 011100 does include mention of mold remeditation. That appears to be included in error and no mold remediation is included in this scope. | Bldg. 1 - 011000 SOW | |
| 40 | If no survey is available, will the contractor be responsible for an industrial hygiene survey prior to the mold remediation work to include air monitoring and sampling? | 011100 does include mention of mold remeditation. That appears to be included in error and no mold remediation is included in this scope. | Bldg. 1 - 011000 SOW | |
| 41 | Please clarify which repair condition will require mockup panels prior to the start of repairs. | Repairs noted on sheet A2.0, #1, #2, #3, & #4 should all have mockups provided for review and approval by COR. Mockups may be done in-situ where current repairs are called out on A2.0. If COR approves mockup, those repairs may proceed per requirements on A2.0 | 040322 Brick Masonry | |
| 42 | The existing brick does not appear to have weeps, please confirm no weeps should be added as part of the brick repairs. | No weeps shall be added to any masonry repairs conducted in association with work in this contract. | Bldg.1 - Site Photos | |
| 43 | SOW states to include utility work for electrical upgrades from 60 amp to 200 amp service and a provision for a 200 amp service panel. It explicitly excludes electrical wiring or outlets. Sheet E100-E300 depict significantly more scope. Please clarify the exact intent of the work. | Electrical Work on Building 1 has been removed from the scope. | Bldg. 1 - 011000 SOW; E100 | |
| 44 | Please advise if any new panelboards are required to have arc flash or ground fault breakers. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - 262416 | |
| 45 | Please confirm if an arc flash analysis and load study has been performed for the newly added service or if the contractor is required to perform these per NEC 220 and NFPA 70E. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - 260573 | |
| 46 | If an arc flash analysis or load study is required, please confirm the timeline, after award, that the government or Eversource will provide the available fault current data and maximum demand data for the utility feeder. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - 260573 | |
| 47 | Please confirm the coordination study, load studies, and arc flash analysis are to be performed by a registered engineer. Please advise if the engineer must be registered in the state of MA. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - 260573 | |
| 48 | Please advise if the utility meter can be installed in the same cabinet as the current transformers. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - E300 | |
| 49 | Please confirm the utility meter does not monitor any other utility pulse inputs. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - E300 | |
| 50 | Please confirm the enclosure types for disconnects and CT cabinets. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - E100 | |
| 51 | Please confirm no surge protection device is required for the new electrical service panel. | Electrical Work on Building 1 has been removed from the scope. | Bldg.1 - E100 | |
| 52 | It is expected roof leaks at existing drains may have deteriorated the existing decking. Please confirm the contractor is not assume replacement of any decking. | Pricing for Building 1 roofing does not need to include deck replacement at this point. We will determine to what extent decking replacement is needed when it is exposed and address any replacement as a modification. | Bldg.1 - A1.1 | |
| 53 | Please confirm the owner or the owner's agent will be responsible for the listed special inspections and which apply to this project. | NPS will conduct inspections with either an agency employed structural engineer or one assisting the agency. Inspection of the work will be conducted prior to closeout and acceptance | Blg.124 - S000 Schedule of Inspection | |
| 54 | Can contractors provide completed CPARS in response to Factor 4 - Past Performance, in lieu of requesting references to complete a Past Performance Questionnaire? | Yes | Factor 4 - Past Performance | |
| 55 | Item E., Volume I, Technical Proposal, Factor 5 - Price, indicates the need for completing Section B of the solicitation. Item F. Volume II, Business and Price Proposal, Item 3, also requires Section B. Contract Price Schedule. Can the government please confirm if pricing belongs in both Volumes? | The contract price schedule in Section B - Bid scheudle needs to be filled out at a minumum. | Volume I & Volume II Requirements | |
| 56 | Item F. Volume II, Business & Price Proposal, Item 3, references FAR 9.104-1. Can the government please confirm if offerors are to provide a response to this General Reference? | Item F. Volume II, Business & Price Proposal, Item 3 | ||
| 57 | Can the government please confirm the NAISC code for this project? | NAICS: 236220, Commercial and Institutional Building Construction | NAISC | |
| 58 | If RFI responses are provided less than two weeks from the required proposal submission date, will the government provide at least a two-week extension to the proposal deadline? This would allow contractors to review, disseminate, and coordinate with subcontractors, ensuring a comprehensive proposal submission. | Proposal Due date has been extended to July 28, 2026 at 10:00am EDT | RFP Due Date | |
| 59 | Reference Building 124;Please provide legible drawing sheet S001 and S006 | Please re-download these files. All are legible. | ||
| 60 | Will the wind uplift analysis for building 124 be provided by the Structural EOR ? | It may be provided to the NPS structural engineer assigned to this project | ||
| 61 | .Is there currently an active electrical power source at building 124 | No. Power can be secured from a neighboring structure if needed for crews. | ||
| 62 | .Identify location to be used for relocating the jersey barriers at building 124 | Jersey barriers can be consolidated into a location underneath the #65 crane adjacent to building 124 | ||
| 63 | Will the government remove all materials, tools and equipment from building 124? | No, contractor should plan to remove all items from the building and coordinate with COR on a location in the adjacent building 24 to move items. | ||
| 64 | .Is this project Tax Exempt? | All federal contracts are tax exempt | ||
| 65 | Reference Building #1;Provide extent of repairs / replacements for windows and roof |
skylight, and if removal of ACM glazing compounds are required
| 66 | Reference Building #1; Drawing D1.1-Will CLIN #10 include the work identified as Alternate #1? | CLIN 010 includes Alternate #1 listed on drawing D1.1. This reference to Alternate #1 was incorporated into the scope. |
| 67 | Verify if Building #1 roof deck is wood , metal , or concrete | Building 1 roof deck is wood plank. |
| 68 | Provide detail for replaced jacked lintel at Building #1 | Lintel replacement will be done in-kind. When disassembly is conducted, document construction conditions for the lintels and replicate this work for replacement lintel and brick reinstallation. |
| 69 | Will steel lintels at Building #1 be painted under this contract? | Lintels shall be painted per section 055000 - 2.03 of the specification. |
| 70 | Will exposed to view underside of new roof canopy be painted at building #1? | Underside of roof canopy does not need to be painted. |
| 71 | Reference Building #1;Drawing P1O2 Plumbing General Note #1,Provide scope of work that |
| can be quantified | It should be assumed that approximately 3' of each drainage downspout draining into the Building should be replaced and connected to the existing cast iron drains. | ||
| 72 | Reference Building #1 ; Drawing E100;Confirm if secondary cables are required at building 265 and 269 | Electrical Work on Building 1 has been removed from the scope. | |
| 73 | What is the length of trench for the new 2/4” conduits that are shown on Drawing EIOO building #1 | Electrical Work on Building 1 has been removed from the scope. | |
| 74 | .Will the cast iron plates on the Commandants House be painted under this contract? |