B09-Amed1_2-RFIs_0002.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
A250 Emergency Repairs to Pier 1
Solicitation number
140P4326R0001
Issued by

About this file

This is a Request for Information (RFI) and Answers document for solicitation 140P4326R0001, addressing 30 contractor questions regarding emergency repairs to Pier 1 at Boston National Historic Park's Charlestown Navy Yard. The RFI clarifies specification and design intent issues for concrete and steel beam repairs, sinkhole remediation, and miscellaneous structural work scheduled for completion by June 12, 2026.

Key clarifications provided include: existing reinforcement shall be retained and cleaned rather than removed, with corrosion removal required unless section loss exceeds 20%; all new steel hardware and fabrications must be hot-dipped galvanized per ASTM A-123/A-153; stainless steel wire fabric is required for underdeck spall repairs while hot-dipped galvanized wire fabric applies elsewhere; bollard cleats must have minimum 25-ton capacity; sinkhole excavations should not exceed 10 feet depth unless field conditions warrant deeper repairs, with 1:1 slopes and potential reuse of excavated soils on-site if separated by filter fabric and not placed below 24 inches of existing grade; ready-mix concrete and marine-grade grouts (such as 5-Star Special 120 mix) are acceptable for repairs, with Section 03 30 00 specifications for non-seawater contact repairs and Section 03 31 30 for marine environments; shotcrete and deck-penetrating concrete deposit methods are prohibited; and pricing should be based on current drawing conditions with modifications evaluated as demolition reveals actual conditions. The government confirmed only two bollard replacements are required, clarified beam flange repair dimensions, and stated the USS Cassin Young will not be relocated during work.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

140P4326R0001 - BOST Pier 1 A250
RFI NumberQuestionGovernment Response
1Details on Sheet S7 for Repair Types 1,2 & 3 show new reinforcement being installed, but does not show existing reinforcement. Will existing reinforcement be cut out of the way, or will the existing reinforcement be chipped around, left in place and cleaned?Per the Specs, Section 030100 pg 15, "Clean existing reinforcement that will remain. Remove corrosion and/or other laitance and notify the Contracting Officer if section loss is greater than 20%." Assuming the reinforcement materials do not have greater than 20% loss, they will be retained and coated per ASTM780/A780M.
2Detail C/S7 for repair Type 3 indicates the installation of bolted angle iron/plate at bottom of existing beam.The detail does not show the bottom flange of the existing beam. Are contractors to assume it is not there, or does it need to be cut off?On Sheet S5, Detail B, it specifices to "cut corroded beam flange"
3Please confirm if steel angle/plates should be Hot Dipped Galvanized. It is unclear in the detailsPer Sheet G1 under Structural Steel and Miscellaneous Metals, "All New steel hardware and fabrications shall be hot dipped galvanized and conform to astm a-123 and/or A-153 unless otherwise noted.
4Is it required that the steel angles/plates be one continuous length of the repair? If not, what is the minimum required length?
5Detail D/S7 indicates Stainless Steel WWF for underdeck spall repairs. All other repairs indicate Hot Dipped Galvanized WWF. Please confirm SS WWF is required for underdeck spall repairsSS WWF is the requested material for underdeck repairs.
6Detail D/S7 indicates “NEW ?” S.S. HDG HOOKED REBAR”. Please clarify if hooked bars shall be S.S. or HDGHDG Hooked Rebar is the requested material for the repair in D/S7
7Detail 3/S8, is it the intent for the concrete repair to be 9 ft down the face of concrete, or is the repair just at the top and the detail is just showing that the bollard has to be drilled 9’ into the concrete? Please confirm18” dia round core hole is acceptable in lieu of square 18”x18” footing as shown on the drawing.The details #2 & #3 on S8 do reflect that the bollards must be set 9' into the pier. The 18"x18" c.i.p. Repairs need only to be "squared" within the top 12" of repair. Below the 12" c.i.p. Repair, a 18" diameter bore for the 12" bollard is acceptable.
8Please confirm rebar required for details on S8. Some show epoxy, some don’t specify. Should it be assume that all rebar is HDG?All rebar specified per Sheet G1 under Structural Steel and Miscellaneous Metals, "All New steel hardware and fabrications shall be hot dipped galvanized and conform to astm a-123 and/or A-153 unless otherwise noted. The epoxy note refers to the embedding method for new rebar and not for use of epoxy coated rebar.
9Is there a basis of design for the new 30” cleat?The cleat shall have a minimum 25 ton capacity. Options from Trelleborg and Schoellhorn-Albrecht should be available to meet this requiement.
10Detail 1/S8 indicates excavation for sink hole repair shall be at least 10ft deep with 1/1 slopes: Many of the sink holes are small at the surface. Following this detail will make the repair area of each sink hole very large (at least 25’x25’ at the surface). Please confirm this is the intent of the detail.Repairs for each sink hole will likely not need to be 10' in depth but should not exceed 10' depth. The note in the detail for the 10' limit for excavation includes the condition, "UNLESS OTHERWISE AGREED IN THE FIELD TO REPAIR THE SETTLEMENT IN THE ASPHALT."
11The detail indicates removal of existing soil and replacement with ?” crushed stone. If done according to detail, a significant amount of excess soil will be generated. Given the history of the site, are there any known contaminated soils? Should soil be tested prior to disposal? If found to be contaminated how will that be handled?We are not currently aware of specific contaminants in these areas. Soils may be deposited on site within an area surrounded by fence at the center of Pier 1. Excavated soils can be reused in the backfill material for sinkhole repairs so long as they meet these conditions: 1. That reused soils are separated out from any compacted stone by installing a filter fabric between the two materials and the soil is adequately compacted prior to relaying asphalt. 2. That reused soils are not utilized below 24" of existing grade.
12As it is impossible to know the cause of the sinkholes until they are excavated, to what extent will the contractor be responsible to repair the cause such as broken utility, structure, etc? This is difficult for a contractor to quantify at the bidding stage without additional information.Once the cause of the sinkhole is discovered, potential repairs will be evaluated and may be addressed by modification to adequately cover any increase in scope.
13Details on S7 indicate the use of a manufactured repair mortar for concrete repairs, however the specifications appear to only specify a ready mix concrete. Please clarify if a manufactured repair mortar is acceptable and a list of acceptable products or specification.Ready mix concrete is acceptable. Grouts such as 5-Star Special 120 mix or other approved equals that are formulated for marine environments are also allowable.
14There are two specifications for concrete, 03 30 00 CAST-IN-PLACE CONCRETE and 03 31 30 MARINE CONCRETE. Please clarify which spec section is relevant.Section 03 30 00 concrete spec is acceptable for all surface level repairs that are not in regular contact with seawater such as the delamination repairs near the Cassin Young. Section 03 31 30 marine concrete shall be used in all other locations including the underdeck repairs and repairs made along the Pier edge.
15Is the use of shotcrete for concrete repairs acceptable.Use of shotcrete will not be approved for this project.
16Will cutting or drilling of holes in the concrete deck for the purpose of depositing concrete into the underdeck forms be permitted?Drilling or cutting holes in the deck for pumping or depositing concrete will not be approved for this project.
17To what extent shall the existing steel beam be cleaned of corrosion?Per the Specs, Section 030100 pg 15, "Clean existing reinforcement that will remain. Remove corrosion and/or other laitance and notify the Contracting Officer if section loss is greater than 20%." Metal shall be stable and all loose materials must be removed. Metals do not need to be "bright" in order to meet the requirements but will need to be prepared in accordance with the repair mortar manufacturers instruction for the concrete bonding agent.
18Note 3 on S4 states “ “REPAIR TYPE 1 MAY BECOME REPAIR TYPE 2 OR REPAIR TYPE 3 BASED ON DEMOLITION FINDINGS”. Repair types are clearly indicated on the plans and the project has been solicited as a Lump Sum project. How will these changes be handled on the fly, especially given the extremely tight work schedule? Please note many of the individual USACE spec section provided in the project documents indicate measurement and payment is unit price, however project is lump sum. Please advise.Pricing for this contract should be based on the conditions currently detailed in project drawings. As demolition occurs and conditions are better understood, any potential modifications based on significant changes in repair treatments will be reviewed at that time.
19Considering the bid due date and experience with the Government procurement process, the absolute best case scenario for an NTP would likely be April 1st at the earliest. This would only leave approximately 72 calendar days to complete the work. Significant efforts will be required to gain access to the underdeck work areas. In addition, irregular work schedules may be required due to tides. These and other factors will make it extremely difficult to complete this work by June 12th. Meeting this schedule will likely result in significant additional expense and will require much more flexibility in regards to permissible work hours. Would the NPS consider prioritizing work to be completed prior to planned events and continuing work after the event has concluded?All work included in this scope must be completed by the end of the period of performance. This work is critical to providing safe pedestrian access and moorings for visiting ships ahead of key summer events.
20Please confirm Cassin Young will not be re-located to allow access to work areas immediately adjacent to the ship.The ship will not be relocated while this work is under way.
21Please clarify the number of bollard replacements required. S1 appears to require a bollard replacement in the area of Vault 12 however it only looks like a cleat replacement. Please advise.Only 2 bollards need to be replaced. Both are located adjacent to the Cassin Young. Only a cleat replacement is required at vault 12 and the cut-off bollard will remain as-is.
22Access to the underside of the Pier is very difficult and we are not able to easily access at this point to review the concrete repair work. Is there and engineering report, photos, or any other detailed information available that show the existing conditions of the underside of vaults 7, 12 and 13?We may have a report that we can share but will need permission from the party that has commission this work to release it.
23The Sinkhole Detail on Drawing S8 indicates a 10’-0” minimum excavation depth and a 5’-0” width at the bottom of the excavation with a 1 to 1 slope on one side of the excavation. However, many of the sinkholes identified on Drawings S1 – S3 are small in area and will need to be excavated to a greater width and length to reach a depth of 10’-0”. Please advise if sinkhole repair areas need to be excavated to 10’-0” deep and if so, will the extra area of excavation and restoration be paid as an additional cost beyond the Base Bid?Repairs for each sink hole will likely not need to be 10' in depth but should not exceed 10' depth. The note in the detail for the 10' limit for excavation includes the condition, "UNLESS OTHERWISE AGREED IN THE FIELD TO REPAIR THE SETTLEMENT IN THE ASPHALT."
24Some of the sinkholes in the paved area abut concrete walks that will be impacted by sinkhole repairs. Please advise on a detail for restoring sections of disturbed concrete.The only concrete areas adjacent to identified sink holes include 2 storm drains at the end of the Pier near Section AB-9. Neither section of concrete appears to be failing as a result of the sink holes and all efforts to retain and backfill underneath these sections is preferred in order to avoid concrete repairs or replacement.
25Some of the sinkholes are located over or adjacent to existing utilities. Please advise if the excavation for the repair is to extend below the bottom of the utility as their depth is likely less than 10’-0”.Excavation below a utility shall only be necessary if it can be positively identified that the uncovered utility was the source cause of the sink hole and the utility requires repair. The note in the detail for the 10' limit for excavation includes the condition, "UNLESS OTHERWISE AGREED IN THE FIELD TO REPAIR THE SETTLEMENT IN THE ASPHALT."
26The Sinkhole Detail on Drawing S8 indicates 4” bituminous concrete installed over crushed stone. Please advise if the bituminous concrete consists of binder and top courses and the thickness of each. Please also advise if the top 8” to 12” should be gravel/ dense graded crushed as a subbase for the asphalt.Detail 1 on S8 shows 4" layer of "bituminous pavement" not concrete.
27Will definitive quantities be provided for the Type 1/2 and Type 3 Beam Repairs as no depth is provided in the details and it is presumed that the repair depths vary by area. For the Type 3 Beam Repair, no dimensions are provided for the lengths and heights of the flanges to be repaired as well as the repair angles.Please review sheet G5 and S7, detail 3 for answers to your questions about dimensions for flanges and repair angles. Width of top flanges are detailed on G5 and replacement bottom flange width/thickness shall match the top flanges. Repair angles are shown on S7, detail 3 and are 8"x4" 1/2" thick.
28Please advise if there is a designated stockpile area(s) for material excavated from sinkholes.
29Is there any characterization of the soils that will be excavated in the sinkholes for determining how the material will be disposed of?