This Statement of Work (SOW) details a project for Cape Cod National Seashore (CACO) to establish fiber optic internet service at three locations: Headquarters, Salt Pond Visitor Center, and Nauset Ranger Station. The primary objectives are to improve network speed, reliability, and security, enhance the park's Land Mobile Radio system, and support cost reduction in IT infrastructure. The contract requires a turnkey fiber optic internet service with 24x7 connectivity, minimum symmetrical speeds of 100Mbps, at least 2 static IP addresses, no data caps, and uninterrupted technical support.
The project scope includes one year of service at the Marconi Headquarters Complex, with options for up to four additional years of service at each location. The contractor must provide all necessary infrastructure, equipment, and installation, with underground fiber optic lines minimizing site disturbance. Delivery is expected within six months of contract award, with potential extensions for permitting and compliance. Technical requirements include terminating fiber service in designated network spaces, providing all necessary documentation, and submitting circuit identification numbers. The contractor must be registered in SAM.gov, comply with all local and federal regulations, and be prepared for potential archaeological monitoring during ground-disturbing work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09-Attachment_2-_Bid_Schedule-_0004.docx | DOCX document | |
| Sol_140P4325Q0073_Amd_0004.pdf | ||
| Sol_140P4325Q0073_Amd_0003.pdf | ||
| Sol_140P4325Q0073_Amd_0002.pdf | ||
| Sol_140P4325Q0073_Amd_0001.pdf | ||
| Sol_140P4325Q0073.pdf | ||
| A06-SF299-expires_1-31-2027.pdf | ||
| A04-CACO_Fiber_Optic_Internet_Service_SOW_v2.docx | DOCX document | |
| A06-Attachment_2-_Bid_Schedule-.docx | DOCX document | |
| A06-MappingNewInfrastructure.pdf | ||
| A06-NPS_10-930_Application_for_SUP_(Long_Form)_2024_OMB_Approved.pdf | ||
| B03-WD-2015-4045-Rev33-8_6_25.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Fiber Optic Internet Service to three CACO Facilities
CAPE COD NATIONAL SEASHORE
99 Marconi Site Rd., Wellfleet, MA 02667
07/24/2025
Background Cape Cod National Seashore (CACO) seeks to establish turnkey fiber optic internet service to three facilities. The purpose of this service is to improve network speed, reliability and security to better meet the operational and business requirements of park operations in support of DOI/NPS/CACO mission.
Furthermore, increased bandwidth and performance will enhance the park’s Land Mobile Radio (LMR) system that is critical to public safety, and support cost reduction in IT hardware, as well as improve cybersecurity through more timely updates and vulnerability patching.
Objectives The goal of this project is to establish fiber optic internet service at three CACO locations.
Scope This project is to bring fiber optic internet service to the following three locations:
1. Headquarters - 99 Marconi Site Road, Wellfleet, MA 02667; 41°54'17.1"N 69°58'44.2"W
2. Salt Pond Visitor Center (Option 1) - 50 Nauset Road, Eastham, MA; 02642; 41°50'14.2"N
69°58'21.7"W
3. Nauset Ranger Station (Option 2) - 1050 Nauset Road, Eastham, MA 02642; 41°50'51.8"N
69°57'48.9"W
4. One year of fiber optic internet service at the Marconi Headquarters Complex.
There will be separate one year-options for up to four additional years of service each location.
The contractor will provide ongoing fiber optic internet service, ensuring 24x7 connectivity and technical support. The contractor will provide all labor, materials, equipment, services and hardware necessary to deliver complete fiber optic internet service to the specified locations including and any related to “last mile delivery.” The installation of last mile infrastructure shall be underground and concealed to the greatest extent possible, with fiber terminated at designated network points within each facility. All work performed under this contract shall be done in accordance with applicable local, State, and Federal codes, bylaws and ordinances in effect at the time of this work. The contractor must minimize disturbance to the site to the greatest extent possible unless directed otherwise.
The park will use existing interior office network cabling for distribution of internet service to computers and other networked equipment within the locations.
Technical Specifications
• 24x7 Fiber Optic Internet Service.
• Terminate Fiber Optic Service in designated network space at each facility.
• The service must include minimum symmetrical speeds of 100Mbps with options for increased speed.
• The service will not be subject to data caps or throttling.
• The service must include at least 2 Static IP addresses configured at the location.
• The contractor is responsible for on-site maintenance and repair of all provided equipment, ensuring uninterrupted service.
Site Visit: The government highly recommends all potential offerors schedule and complete a site visit.
If a vendor does not complete a site visit, it does not relieve them of the accuracy of their pricing.
Deliverables
• The contractor will provide ongoing fiber optic internet service, ensuring 24x7 connectivity and technical support.
• The contractor will provide necessary cabling and equipment for the fiber optic internet service to the specified locations.
• A cost estimate of the monthly internet service by location is required for budgetary planning and to determine the government’s ability to afford this internet service provider upon completion of construction.
• The contractor shall provide documentation on the hardware installation and any warranties electronically.
• The contractor shall provide all circuit identification numbers for each location electronically.
Options
1. Salt Pond Visitor Center (Option 1) - 50 Nauset Road, Eastham, MA 02642
2. Nauset Ranger Station (Option 2) - 1050 Nauset Road, Eastham, MA 02642
Delivery Schedule Up to six months for fiber optic service to be available at the specified locations after award of contract.
If more than six months is needed for permits, construction, or 106 compliance, it will be granted as necessary.
Payment Vendor will need to submit invoices through https://www.ipp.gov for payment approval and processing.
Contractor Requirements The contractor must be an internet service provider who is authorized to perform the utility work required to provide internet service. Contractor must be in SAM.gov prior to award of the contract. The Contractor shall be responsible for storage of all materials and equipment; the Park must approve contractor’s use of any space on the site in advance.
A) Regulations and Permitting
1) The contractor must comply with all regulations and permitting requirements.
2) Mapping Requirements for Permanent Infrastructure: As the Contractor will continue to occupy and operate the infrastructure footprint after construction is complete, a Right of Way (ROW) permit application and associated maps will be required. According to Reference Manual 53B, authorized under 54 USC 100902, and 36 CFR Part 14; ROW applications must be accompanied by maps and data that meet current mapping standards. To meet the mapping standards, the
Contractor will need to submit georeferenced AutoCAD, KMZ, or GIS files showing the footprint of the infrastructure being installed (centerlines, points, and buffers). The Contractor will also need to submit a pdf map showing the infrastructure within Park Boundaries. The data quality of both the electronic and pdf files must meet survey grade standards. The Contractor must provide a formal survey and legal description signed by a licensed surveyor.
3) While not expected, it is possible that buried archeological features or deposits may be located in the vicinity of the project. Work must be stopped immediately if there is discovery of any such articles, and the Contracting Officer’s Representative must be notified at once. A government Archeologist/Historian may monitor ground disturbing work and has the authority to stop the work if any potential archeological resources are unearthed.
B) On-Site Work Hours
1) Work shall generally occur between 7:00 a.m. and 5:30 p.m., Monday through Friday, unless otherwise approved. The contractor shall provide a work schedule to the Contracting Officer’s Representative (COR) to alert all staff and law enforcement personnel of work areas. Any building access will need to be coordinated with the COR
2) Weekend Work: Requires written request and Contracting Officer (CO) approval at least seven
(7) days in advance.
3) Early Morning Hours: Not permitted.
4) Noisy Work: Restricted to 8:00 a.m. to 5:30 p.m.
C) Barricades, Warning Signs, and Lights:
1) Comply with requirements of agency(ies) with jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
D) Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with
NFPA 241.
1) Vehicles and Equipment: Provide one extinguisher on each vehicle or piece of equipment.
2) Spark Arresters: Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the USDA Forest Service.
a) Written determinations of periods and areas of potential fire hazard will be issued by
Contracting Officer.
E) Existing Utilities
1) Utility Location and Coordination:
a) Notify the CO, utility companies, Dig Safe, and the contractor-retained utility locator prior to ground disturbance.
b) Conduct a Ground Penetrating Radar (GPR) survey of construction and impact areas in accordance with ASTM D6432.
c) Mark and map all identified utilities; submit the plan for CO Representative and maintenance staff review.
d) Participate in one on-site review meeting of the utility plan before starting site work.
2) Responsibility for Utilities:
a) Contractor is responsible for locating and protecting known utilities.
b) Utilities in conflict with new work must be reported to the CO.
c) Damage to known utilities shall be repaired at no cost to the Government.
3) Unknown Utilities:
a) If damage occurs to unknown utilities, the contractor shall repair them.
b) Compensation will follow the contract’s Changes clause.
F) Utility Interruptions
a) Do not interrupt active utility services without prior coordination and approval:
(1) Submit written notice to the CO at least 14 days in advance.
(2) Do not proceed without written authorization.
G) Smoking and Vaping
a) Smoking and vaping are prohibited on government property.