RFQ_140P4322Q0073_Q_As_20220916_0003.pdf
PDF 184 KB Posted
- Attached to
- CACO-HIGH-SPEED INTERNET SERVICE-5 SITES
- Solicitation number
- 140P4322Q0073
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P4322Q0073_Amd_0003.pdf | ||
| NPS_ROW_Permit_Mapping_Standards_0003.pdf | ||
| Sol_140P4322Q0073_Amd_0002.pdf | ||
| Abstract_-_Price_Breakout_Rev_1_0002.xlsx | XLSX spreadsheet | |
| RFQ_140P4322Q0073_Q_As_20220915_0002.pdf | ||
| Sol_140P4322Q0073_Amd_0001.pdf | ||
| RFQ_140P4322Q0073_Q_As_20220914_0001.pdf | ||
| Sol_140P4322Q0073.pdf | ||
| B08_Sol_140P4322Q0073.pdf | ||
| Abstract_-_Price_Breakout.xlsx | XLSX spreadsheet | |
| CACO_High-Speed_Internet_SOW.pdf | ||
| DOL_WD_SCA_2015-4045_Rev_23_6_27_2022.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 140P4322Q0073
CACO High-Speed Internet Services
Q&As 9/16/2022
Q. The SOW refers to "mapping standards template provided by NPS". Where can this be found? I ask just so I can adequately include any surveying cost.
A. The mapping standards template will be included as an attachment in an amendment.
Q. Is 9/22 a hard start of service date or an estimate?
A. Per the 1449 Continuation page it states, “the intended award date is 9/22/2022 (or the day after award, whichever happens last).” The Government needs the awardee to initiate the process to begin installing the services to the locations starting on the date of award.