Rehabilitate First Bank Windows_0002.pptx

PPTX presentation 2 MB Posted

Attached to
Rehabilitate First Bank Windows, Sills and Trim
Solicitation number
140P4220R0019
Issued by

About this file

This document contains a presentation for a virtual pre-bid meeting for solicitation number 140P4220R0019 from the Department of the Interior National Park Service Northeast Region. The project involves rehabilitating the windows, sills, and trim of the First Bank of the United States building in Independence National Historical Park in Philadelphia, Pennsylvania. The scope of work includes rehabilitating the wood windows, sills, trim, aluminum interior storm windows, and restoring the wood basement level doors over the stairs. The presentation provides an overview of the project contacts, duration of 120 days, work hours, parking and restroom accommodations, security and site access requirements, and photos depicting existing conditions of the building interior and exterior.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rehabilitate First Bank Windows, Sills, and Trim Independence National Historical Park Philadelphia, PA

PRE-BID VIRTUAL SITE MEETING

VIRTUAL PRE-BID SITE MEETING

Independence National Historical Park

PROJECT SCOPE:

The Work includes but is not limited to the rehabilitation of the First Bank wood windows, sills, trim, aluminum interior storm windows, and restoration of the wood basement level doors over the stairs.

The First Bank of the United States, constructed 1795-1797, is a National Historic Landmark, and the windows were installed during the 1974 National Park Service rehabilitation of the building.

Refer to the plans and specifications for a full description of the project scope and the required work.

Independence National Historical Park

Project Contacts:

Contract Specialist:Dawn Hill
email: dawn_hill@contractor.nps.gov
Contracting Officer’s Representative (COR):Winston Clement
email: winston_clement@nps.gov
phone: (267) 582-9242

Independence National Historical Park General Information:

NOTE- All information concerning or affecting the bidding and contracting of this project will be issued through the Contract Specialist. The Contracting Officer’s Representative (COR) will answer any technical questions pertaining to the work in writing through the Contract Specialist. Contractors may ask the COR technical questions and/or questions pertaining to park operations directly but answers received are not official and do not affect the bidding or contracting of the project until issued by the Contract Specialist.

Contract Duration:120 Days
Work Hours:8:00 AM to 5:00 PM Monday thru Friday
Parking:No on site parking except for loading.

General Information (continued):

Restrooms – The contractor will be permitted to use the restrooms in the building.

Security – The contractor is required to secure the site from the public/park visitors and unauthorized staff. Note the temporary window enclosure details on drawing A8.4.

Project Meetings –Weekly site meetings with the COR are required.
The contractor is required to hold weekly safety meetingswith their personnel and sub contractors.
Site limitations –The sidewalks adjacent to the First Bank must remain open to thepublic.
All building entrances must be accessible to Park Staff.
Fire Hydrants and F.D. connections must remain accessible to theFire Department.
Provide protection for trees, plantings and paving within the workarea.

VIRTUAL PRE-BID SITE MEETING

Location: 120 S. 3rd Street, Philadelphia PA 19106

East (Third Street) elevation. The sidewalk is to remain open during construction. The building will be closed to the public during work, however the main entrance doors must remain accessible for staff use and during emergencies.

First Bank south elevation (left photo) and north elevation (right photo). Photos show cellar area-way door locations, which are included in the scope. Access to the north and south is constrained by the gates. See site plan drawing AS.1 for more details, including dimensions of gates and other encumbrances.

West elevation. Note existing wheelchair ramp, and location of brick retaining wall. The building will be closed to the public during work, however the entrance doors must remain accessible for staff use and during emergencies. See drawing AS.1 for more information.

Detail photographs of typical windows on East (Third Street) elevation.

Both photos show typical windows on south elevation.

The image on the left shows typical windows on the north elevation. The image on the right shows a typical window on the west elevation.

Typical interior basement window condition.

Photo shows window 015.

VIRTUAL PRE-BID SITE MEETING

Typical interior first floor window condition.

Photo shows window 124.

VIRTUAL PRE-BID SITE MEETING

Typical interior second floor window condition.

Photo shows window 214.

VIRTUAL PRE-BID SITE MEETING

Typical interior third floor window condition.

Photo shows window 315.

VIRTUAL PRE-BID SITE MEETING

Photo shows interior condition of window 209.

Questions are to be submitted in writing to Contract Specialist Dawn Hill (dawn_hill@contractor.nps.gov) prior to the cut-off date specified in the Solicitation.

Thank You for Your Interest in This Project.

VIRTUAL PRE-BID SITE MEETING