This is a Statement of Work (SOW) for the National Park Service's United States Park Police to replace a domestic hot water heater at the Anacostia Operations Facility located at 1901 Anacostia Drive, SE, Washington DC 20020.

The contractor must remove and dispose of the existing 250-gallon 199 MBH gas-fired water heater and supply and install one new PVI 225-gallon 199 MBH gas-fired water heater in its existing location. Additional work includes supplying and installing a new thermal expansion tank; all required pipe, valves, and fittings to connect to existing plumbing within 5 feet of the new heater; all pipe and fittings to connect to the existing gas line; insulation to wrap all contractor-installed pipes; rigging and removal services for the old heater and placement of the new unit; electrical connection to existing power supply with new conduit run to the electrical panel within 50 feet; and filling, leak checking, and startup of the system. The period of performance runs from June 22, 2026 through August 31, 2026. All materials and equipment must be delivered, inspected, and approved prior to work commencement, with delivery schedules coordinated with the Contracting Officer's Representative. The facility is a secured United States Park Police station requiring proper identification at all times. Government-furnished electrical power will be provided at existing outlets for contractor use.

View the file

Other files

File Type Posted
Sol_140P3026Q0011_Amd_0001.pdf PDF
Sol_140P3026Q0011.pdf PDF
B08_-_Price_sheet_AOF_Replace_Domestic_Water_Heater_xls.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT of WORK

For

NATIONAL PARK SERVICE

United States Park Police

Anacostia Operations Facility 1901 Anacostia Drive, SE

Washington DC 20020

REPLACE DOMESTIC HOT WATER HEATER

1.0 Background

The Anacostia Operations Facility (AOF) located at 1901 Anacostia Drive at the southern end of Anacostia Park adjacent to Marion Barry Boulevard serves as headquarters for the Special Forces, Criminal Investigations, and Training Branches. The major areas of patrol include Anacostia Park, the Suitland Parkway, Fort Dupont Park, Kenilworth Aquatic Gardens, and Fort Washington Park, Frederick Douglass Historic Home and the remaining NPS reservations in the District of Columbia east of the Anacostia River.

2.0 Purpose

The building’s domestic hot water heater system at AOF was designed with two gas-fired water heaters, each with a 225-gallon capacity, providing a total of 450 gallons of hot water for the entire 75,730 sf.

facility. The intention of the hot water design was to deliver redundancy, allowing the system to continue operating if one of the water heaters fails. Water Heater #2 failed, forcing water heater #1 to carry the entire load. The failure of water heater #1 due to the increased load would result in the complete disruption of hot water, posing significant risks to health, hygiene and essential operations at

AOF.

3.0 Scope

National Park Service (NPS) requires all labor, material, supplies, and equipment necessary to replace one (1) new PVI 225-gallon 199 MBH gas-fired water heater in the existing location. Replacing the water heater will return the hot water system to its original design, delivering redundancy to ensure continued uninterrupted supply of hot water.

4.0 Work to be Performed

• Contractor to remove and dispose of existing one (1) 250-gallon 199MBH gas fired water heater.

• Contractor to supply and install one (1) new PVI 225-gallon 199MHB gas fired gas fired water heater in its existing location. Supply and install new thermal expansion tank.

• Contractor to supply and install all required pipe, valves and fittings to connect to the existing plumbing within 5ft. of new water heater.

• Contractor to supply and install all required pipe and fittings to connect to the existing gas line.

• Contractor to supply and apply insulation to wrap all pipes contractor installed.

• Contractor to arrange for rigging, removal of existing one (1) old water heater and set (1) new water in place.

• Contractor to connect to existing power supply and run new conduit to the electrical panel in the next space within 50L.

• Contractor to fill, check for leaks, and start water.

5.0 Location of Work

United States Park Police Anacostia Operations Facility (AOF) 1901 Anacostia Drive, S.E. Washington, D.C. 20020.

6.0 Period of Performance

June 22, 2026 – August 31, 2026

7.0 Delivery Schedule

All material and equipment required to effectively replace one (1) gas-fired water heater at Anacostia Operations Facility must be delivered, inspected, and approved prior to beginning the work. Delivery schedules should be shared and approved by the Contracting Officer’s Representative (COR). Any delays in anticipated lead times should also be shared the Contracting Officer (COR).

8.0 Special Requirements

8.1 Government-furnished Property – Electrical power will be provided at existing power outlets for the Contractor’s use to operate such equipment as is necessary to complete their work.

8.2 Security – The Anacostia Operations Facility is a United States Park Police station;

therefore, proper identification must be always displayed while in and around the facility.

9.0 General Items

9.1 Index of Attachments

Attachment 1: Price Sheet

STATEMENT of WORK
For
NATIONAL PARK SERVICE
United States Park Police
Anacostia Operations Facility
1901 Anacostia Drive, SE
Washington DC 20020
REPLACE DOMESTIC HOT WATER HEATER
1.0 Background
3.0 Scope
4.0 Work to be Performed
Contractor to remove and dispose of existing one (1) 250-gallon 199MBH gas fired water heater.
Contractor to supply and install one (1) new PVI 225-gallon 199MHB gas fired gas fired water heater in its existing location. Supply and install new thermal expansion tank.
Contractor to supply and install all required pipe, valves and fittings to connect to the existing plumbing within 5ft. of new water heater.
Contractor to supply and install all required pipe and fittings to connect to the existing gas line.
Contractor to supply and apply insulation to wrap all pipes contractor installed.
Contractor to arrange for rigging, removal of existing one (1) old water heater and set (1) new water in place.
Contractor to connect to existing power supply and run new conduit to the electrical panel in the next space within 50L.
Contractor to fill, check for leaks, and start water.

File details come from the government source that posted it. Updated .