This document is a solicitation for a firm fixed-price construction contract to repair and preserve the front, side, and rear porches and balcony at the Gambrill House located in Frederick, Maryland. The estimated contract value is between $250,000 and $500,000. The work includes replacing roofing, gutters, and downspouts, as well as repairing and painting the wood surfaces on the porches. The solicitation is set aside for small businesses, with a proposal due date of August 13, 2024. The contract will be awarded on a best-value trade-off basis. Key dates include a site visit on July 17, 2024, and a question deadline of July 24, 2024. The contract completion period is 201 calendar days after the notice to proceed. The solicitation incorporates various FAR clauses, including requirements related to the Buy American Act, liability insurance, and past performance reporting.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2124R0051 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
WA2
Frederick MD 21704 4801A Urbana Pike DOI, NPS, Historic Pres Trng Ctr
PWA
Denver CO 80225 P.O.Box 25287 MS WCP NPS, WASO - WCP Contracting
08/02/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/03/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of amendment 0002 is to update, change or remove the following (All changes within documents are in red font):
1. Extend proposal due date to August 13, 2024, by 12:00 pm Mountain Time, (2:00 pm Eastern
Time)
2. Incorporating Revised Scope of Work (Attachment 1), dated 07-25-2024.
3. Incorporating Revised Specifications (Attachment 2), dated 07-25-2024.
4. Removed Option 2 from the solicitation in its entirety. Note: Project magnitude remains unchanged.
5. Attaching RFI questions and answers, to include photographs.
6. Updated Section L: Paragraph L-5 Proposal Submittal & L-8 Volume II: Past Performance.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
David Clark
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 41
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2124R0051/0002
7. Updated Section M: Evaluation Factor (4) -
Past Performance
8. Incorporating Updated Wage Determination, Frederick County_MD20240051 (Attachment 4), dated
08-02-2024.
7. Incorporating Revised Past Performance
Questionnaire (Attachment 5). Note: Any Past
Performance Questionnaires already received will be accepted.
8. Incorporating Revised Cost Proposal
(Attachment 6). Previous Cost Proposal attachment will not be accepted.
9. Updated Section J, Attachments.
All other terms and conditions remain unchanged.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
# Questions Answers
Is it acceptable to submit previously completed PPQ’s in a different format as long as pertinent information is represented? If so, is it acceptable to send the previously completed PPQs to you directly (or include in the technical proposal) instead of the former client/owner’s rep submitting it to you (per the instructions on Attachment 5).
Yes, it is acceptable. Section L & M have been amended to reflect changes.
Past Performance, do we need to complete Attachment 5 PPQ if the past project has a CPARS evaluation available?
It is encouraged, but not required. Section L & M have been amended to reflect changes.
Can previously obtained Past Performance forms and/or CPARs be used in place of the Past Performance Questionnaires associated with this solicitation?
Yes, it is acceptable. Section L & M have been amended to reflect changes.
Please confirm that cover pages, cover letters, table of contents, tabs for organization, and key personnel certifications are not included in the page count.
Confirmed. See section L‐6 of the solictation.
5 Will the government increase the page limits for Volume I?
No. Section L‐6 excludes specific pages. For this reason, the Government determines 15 pages is a sufficent maximum amount of pages for the
Technical Submission.
Please provide description of additional option proposal required if any.
Solicitation has been updated with a revised scope and price schedule for the base requirement and subsequent option line items.
7 Please provide site visit sign in sheet Site visit sign‐in sheet will not be sent out.
In our past experience with NPS some projects have tax exemptions for buying materials while others do not. Will NPS be providing the winning contractor a Maryland Sales Tax
Exemption Letter?
Exemption letter may be given at time of award. However, the letter does not guarantee tax exemption via government contracts. It will be up to the vendor, i.e. for materials/supplies, if they honor it. Be advised, your pricing should not be based on the possibility of tax exemption. This will be a Firm Fixed Price Contract.
Please clarify if a scaffold builder is a carpenter wage rate or a skilled laborer wage rate or which labor classification should be used for scaffold builder.
The Wage Determination lists all categories that have specific wage rates.
If a discipline is not listed, follow the guidance per the Executive Orders on the first page.
Please confirm water sources and power sources will be provided on site
Normal use needs of water and electric will be provided by the government. Any needs above and beyond will be the contractors responsibility.
In regards to Painting of Wood Surfaces, In the SOW each Porch
Section has the same comment of the requirement to prepare and paint all wood surfaces. Is the painting scope of this project just limited to the porches or does it apply to other areas of the building specifically the doors, windows, soffit and fascia?
The painting requirements of this project are limited to the porches.
Soffit and facia are in scope on all porches and balconies.
The East and West porches have two different types of Gutters, is it the intent to keep that difference and replace those two different styles in kind or is it the intent to replace both gutters to match only one of the styles?
The intent of this project is to replace in kind and to retain the historic characteristic of all work.
Gambrill House Porches/Balcony Preservation (HPTC)
140P2124R0051
08/02/2024
Pertaining to Lead Based Paint Removal, Section 02090 1.1A says to verify with COR what level of abatement is required but
1.1D states the means and methods are the sole responsibility of the contractor. To accurately price this we would need to know the level of abatement required on this project? In our past experience on historic preservation projects we are allowed to follow the RRP rules and only remove, by the gentlest means possible, the deteriorated paint to enable proper adhesion for the new paint finishes however if a total abatement down to bare wood is required that would significantly increase the cost.
What level of LBP removal is required for this contract?
This is not an abatement project. There may be residual lead paint in substrate and care shall be required for repairs and preparation.
Abatement work was complete in other campaigns of work to this structure. It is the contractor responsibility to test as need to protect employees, staff and visitors to this structure.
Please verify or state the quantity by SF of the new flat seam metal roofing to be installed on the front/north porch?
Please verify or state the quantity by LF of lead coated copper gutter to be replaced on the front/north porch?
Please verify or state the quantity by SF of the side/east porch roof?
Please verify or state the quantity by LF for new gutter and downspout to be replaced on the east/side porch?
Considering the date of the RFP submission on Aug 5, 2024 and the time it will take for contract award, the 201 day completion schedule will put the project into cold weather conditions that are not favorable for certain aspects of this project. Will NPS accept delaying start of work until spring 2025 to allow for continuous operation of the project in favorable weather conditions?
We would like the work to begin prior to the cold season. However, if the weather becomes unfavorable for work conditions, a stop work order will be issued, and work can resume once weather is favorable. We cannot delay the project until next spring due to fiscal law.
Are the bay window and downspout on the East face of the building included?
The bay windows are not in scope. The gutters and downspouts on the
East porch are in scope.
20 Are manlifts acceptable to perform the work?
Manlifts are allowed with the use of equipment matting and a COR approved work plan/safety plan due to historic landscape and power lines.
21 Whose responsibility is restrooms? Restroom and handwashing stations are contractor responsibility.
22 Which gutters are included in the work, and which aren't?
Gutters, downspouts, and gutter guards are in the scope on the
Front/North Porch, the Side/East Porch, and the Rear/West Porch.
23 Is anything above the east porch roof included? Roof coating on any flashing that may be at the transition to the house.
The statement of work for the side / east porch states, “Repair, prepare, prime and paint metal handrails.” The existing handrail base plates appear beyond repair. Please see below images.
Please advise how we’re to proceed.
Repair/replace handrail bases as needed.
This intent of the site visit was for offerors to measure/estimate quantities. No estimations from the Government are given. The site is available for offerors to obtain measurements. Per the Statement of
Work all measurements will be verified prior to work commencement.
25 Are man‐lifts allowed for building access?
Manlifts are allowed with the use of equipment matting and a COR approved work plan/safety plan due to historic landscape and power lines.
Amendment #1, dated 07/10/2024, includes Removal and
Disposal of Lead Based Paint. I do not see a Hazardous Material
Inspection Report for us to quantify the extent of this work.
Please confirm all areas included in the base contract scope of work are to be abated by a licensed hazardous material abatement company, including any selective demolition required to complete the exterior repairs.
The amount of lead paint based materials based on weight will be below the threshold for hazardous material and may be disposed of normally.
Are we to provide any additional site supervision other than a
Superintendent (i.e., QC Manager, Safety Manager, etc.)?
Contractor supervision is up to the contractor. Although the QC plan and
Safety plan will be provided by the contractor as a submittal. The one single point of contact can be responsible for all aspects of work under this contract.
Spec 07600 states, “Furnishing and installing new chimney flashing” and “Furnishing and installing sacrificial copper strips in the field of the new wood shingle roof per drawings.”
Please confirm there’s no work associated with any chimneys.
Please confirm there’s no work associated with wood shingle roofing.
There are no chimneys nor wood shingles in this scope of work.
Are we to provide any 3rd party testing? If yes, please describe in full.
No third party testing is required on this project.
The Statement of Work, section 3 Front/North Porch states:
“…Remove center bay breast beam trim to expose structural beam within. Repair /replace damaged or deteriorated decking/sheathing (estimated to be 30% of the decking area).
Repair / replace damaged or deteriorated structural members
(estimated to be 30% of the roof area plus the center bay breast beam)…”
Please provide the dimensions of the structural members we’re to replace.
Please provide the details of the existing roof deck material.
Dimension of this material is unknown and should be estimated on the size of the roof and the historic materials and dimensions of the period.
The intentions of the park are to replace in kind.
The Statement of Work, section 5 Rear/West Porch states:
“Demo metal roof, gutter, and roof substrate.”
Please provide the details of the new roofing substrate we’re to install.
This material is unknown and should be estimated as a random width split sheeting.
On the Rear / West Porch we are removing and replacing the metal roof.
This porch work has been opted out of the contract.
33 What type of metal roof is it being replaced with?
Refer to specification 07600‐2 Flashing and Sheet Metal Part 2: Products section 2.1 Sheet Metal A and B.
Flat seam copper roof panels are the only roofing material listed in the specifications.
That is the only type of metal roof work required in this contract.
Solicitation No: 140P2124R0051
REQUEST FOR PROPOSAL
Gambrill House Three Porches & Balcony Preservation
4801 Urbana Pike, Frederick, MD 21704
Type of Contract: Construction, Firm Fixed Priced (FFP), Single Award Contract County: Frederick, Maryland Type of Construction: Building
Magnitude: $250,000 - $500,000 NAICS: 236220 Size Std: $45.0M Set-Aside: Total Small Business
Contracting Officer
Name: David Clark
Email: david_clark@nps.gov
Site Visit: July 17, 2024, at 8:00 am Eastern Time See Section L, Clause 52.236-27, Site Visit
Questions Due Date: July 24, 2024, by 12:00 pm Mountain Time, (2:00 pm Eastern Time) All questions shall be submitted in writing. No questions will be accepted via phone calls.
Proposal Due Date: August 13, 2024, by 12:00 pm Mountain Time, (2:00 pm Eastern Time)
Award Selection Process: Best Value Trade-Off
SECTION B – PRICE SCHEDULE – SUPPLEMENT TO SF 1442
ITEM
NO
DESCRIPTION QUANTITY UNIT AMOUNT
0010 All labor, material, equipment, mobilization, supervision, profit, overhead, bonds, subcontractors, etc.
as applicable for complete and functional project in accordance with specifications and drawings for the repair and preservation of the front and side porches and balcony at the Gambrill House.
1 Lump Sum
GRAND TOTAL
Offerors shall complete and submit both Section B Price Schedule (supplement to SF 1442) and Revised Cost Proposal (Attachment 6).
(END OF SECTION)
SECTION C: SPECIFICATIONS/DRAWINGS
CLAUSES INCORPORATED BY REFERENCE
Clause Title Date
52.236-21, Alt 1 Specifications and Drawings for Construction February 1997, April 1984
52.236-2 Differing Site Conditions April 1984
52.236-3 Site Investigation and Conditions Affecting the Work April 1984
See Section J for additional attachments to include project specifications and drawings.
SECTION D: PACKAGING AND MARKING
D.1 Payment of Postage and Fees
All postage and fees related to submitting information forms, reports, etc., to the CO or the COR shall be paid by the contractor.
D.2 Marking
All information submitted to the Contracting Officer or the Contracting Officer's Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.
SECTION E: INSPECTION AND ACCEPTANCE
52.246-12 Inspection of Construction August 1996
52.246-13 Inspection -- Dismantling, Demolition, or Removal of Improvements August 1996
52.246-21 Warranty of Construction March 1994
FINAL INSPECTION AND ACCEPTANCE
Final completion of the punch list items, submission of all required submittals, and final cleanup of the project site shall be accomplished before the contract’s required completion date. The Contracting Officer or his/her designated representative will perform final inspection. Acceptance of the work will occur only upon written notice of acceptance by the Contracting Officer or any other warranted Contracting Officer at the National Park Service (NPS) performing authorized duties in conjunction with this contract. The contract required completion date is 201 calendar days after receipt of the notice to proceed.
SECTION F: DELIVERIES OR PERFORMANCE
52.242-14 Suspension of Work April 1984
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK April 1984 ALTERNATE 1 April 1984
The Contractor shall be required to
(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 201 calendar days after receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR April 1984
The Contractor shall perform on the site, and with its own organization, work equivalent to at least fifteen percent (15%) of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
SECTION G: CONTRACT ADMINISTRATION DATA
DIAR 1452.201-70 AUTHORITIES AND DELEGATIONS September 2011
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The Contracting Officer's Representative will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G-1 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM December 2015
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b) Your comments should focus on objective facts in the AO's narrative and should a)provide your views on the causes and ramifications of the assessed performance.
c) All information provided should be reviewed for accuracy prior to submission.
d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in
PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
G-2 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP) February 2021
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System
(IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is:
https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice date and government contract number.
2. Billing period specified with beginning and ending dates. The beginning date must not be later than the completion date or within any previous billing dates.
3. The accounting must follow the approved schedule of values as described in the specification attachment.
4. Total amount due for the billing period.
5. Certification of progress payment.
6. Weekly Payrolls.
7. Substantiation of subcontractor payment.
8. 52.223-9 Certification with final payment request.
9. A Release of Claims (See 1452.204-70) with a request for final payment.
A Progress Report shall be submitted to support each invoice and shall include a summary of work performed during the period of performance identified on the invoice, which at a minimum must include:
1. Activity: Description of the previous month’s project activities and the planned activities for the next month. Describe the activities performed on contingency task(s), task or deliverable schedule, and identify any issues or concerns that may affect the performance and/or completion of the task(s).
2. Percentage Complete: In accordance with the accepted Schedule of Values, identify the percentage complete during the previous month and the cumulative percentage completed for each task/deliverable.
3. Schedule: Reconcile progress of each task/deliverable with the schedule identified for each. Submit a revised schedule as required.
4. Issues or Concerns: Identify issues and/or concerns that may affect the project Statement of Work or schedule.
5. Other Information: Any other information required in the contract to be included in the Progress Report.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
G-3 TECHNICAL DIRECTION
The performance of the work required herein shall be subject to the technical direction and surveillance of the COR or his designee. As used herein, "technical direction" is direction to the Contractor which requires pursuit of certain lines of inquiry, filing in details or otherwise serving to accomplish the contract specifications. The technical direction, to be valid:
(a) Must be issued in writing consistent with the general scope of the work set forth in the contract;
(b) May not constitute a new assignment of work changes to the expressed terms, conditions, or specifications incorporated into this contract;
(c) Shall not constitute a basis for extension of the contract delivery schedule.
Nothing contained in this part authorizes the Contractor to incur costs in excess of the contract price or other limitation of funds set forth in the contract due to extra work performed in response to informal directions, suggestions, or instructions (oral or written) given by representatives of the CO, unless prior to commencing such work, the Contractor: 1) directly notifies the CO;
2) requests a formal contract modification; and 3) receives written authorization to proceed from the CO.
G.4 CORRESPONDENCE
Any correspondence initiated by the Contractor shall include the Contract Number and shall be addressed to the CO (original and one copy) at the address provided in the clause entitled "Contractor Administration".
G.5 CONTRACT PAYMENTS
The Contractor shall submit invoices to the Contracting Officer for the percentage of work completed. Contractor and COR at the site must agree on the percentage of work completed.
G.6 JOB SITE ADMINISTRATION
The COR will be available at the site to inspect the work as it progresses. The COR is authorized to make technical decisions or give technical directions, however, they are not allowed to make any decisions that would change the terms and conditions of the contract (to include anything that would effect pricing); the Contractor or the Contractor's Superintendent must contact the Contracting Officer regarding such decisions and directions if it will effect terms and conditions (pricing, etc…).
The Contractor shall have a competent superintendent (hereinafter referred to as the "Contractor's Superintendent") who is (i) deemed acceptable to the Government; (ii) authorized to act on the Contractor's behalf; and (iii) to be present on the job site at all times when contract work is being performed.
G.7 PAYROLL RECORDS
The Prime Contractor is responsible for furnishing the Contracting Officer with one (copy of the Weekly Payroll Form WH-347 or equivalent) to include payroll records for his/hers subcontractor's. Payroll records shall be submitted within seven (7) days after the close of the payroll period and numbered in consecutive order. The Prime Contractor shall review all subcontractors' payroll and ensure that all employees are paid in accordance with the Wage Determination, which is a part of this contract.
The Prime Contractor shall ensure that compliance is met. The Contractor is subject to the Wage and Hour Dept., U.S. Department of Labor.
G.8 GOVERNMENT POINT OF CONTACT
David Clark Contracting Officer Historic Preservation Training Center (HPTC) Phone: 602-989-9775 Email: David_Clark@nps.gov
SECTION H: SPECIAL CONTRACT REQUIREMENTS
H-1 WORK HOURS
Unless otherwise specified in the specifications, work hours shall be limited to the time between 7:00am-4:00pm, Monday through Friday, excluding government holidays. No work shall be done on Saturday, Sunday or Federal holidays unless authorized by the Contracting Officer. A request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.
H-2 FIRE DANGER SEASON
If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.
H-3 DRAWINGS
(a) Typical Drawings. Any drawings titled typical are general only and dimensions of each structure will be fixed by the Contracting Officer to adapt the design to existing conditions at the structure location.
(b) Reduced Size Drawings. Any drawings identified as "REDUCED SIZE DRAWINGS" appearing in the solicitation are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective bidders desiring to review a copy of the full-size drawings may contact the Contracting Officer identified in the solicitation.
H-4 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
(b) If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
(c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.
(d) The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
H-5 SAFETY AND QUALITY CONTROL PLAN
Within 10 days following contract award, the contractor must provide effective quality control/assurance and safety plans for acceptance by the Government.
H-6 FEDERAL HOLIDAYS
The following Federal legal holidays are observed:
New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Juneteenth Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
H-7 LIMITATIONS ON SUBCONTRACTING REPORTING
In accordance with 52.219-14 Limitations on Subcontracting, the prime contractor must perform at least 15% of the cost of the contract, excluding the cost of materials with its own employees and employees of a similarly situated subcontractor. A similarly situated subcontractor is a small business concern subcontractor that is a participant of the same SBA program that qualified the prime contractor as an eligible offeror and awardee of the contract. The contractor is responsible for ensuring compliance with the Limitation on Subcontracting.
At the conclusion of the period of performance and prior to final payment, the contractor shall submit a Limitation on Subcontracting Report directly to the Contracting Officer. The following information is required as part of the report: 1) the total amount paid to the Prime during the performance period broken out by labor and materials 2) list of Similarly Situated Subcontractors and the amounts paid to each during the performance period broken out by labor and materials 3) list of any other subcontractors and the amounts paid to each during the performance period broken out by labor and materials.
If the Contracting Officer review of the report finds that the contractor is not in compliance for the period of performance, the contractor will be notified in writing. Penalties for failure to comply are described in 13 CFR 125.6(h) which states:
Whoever violates the requirements set forth in paragraph (a) of this section shall be subject to the penalties prescribed in 15 U.S.C.
645(d), except that the fine shall be treated as the greater of $500,000 or the dollar amount spent, in excess of permitted levels, by the entity on subcontractors. A party's failure to comply with the spirit and intent of a subcontract with a similarly situated entity may be considered a basis for debarment on the grounds, including but not limited to, that the parties have violated the terms of a Government contract or subcontract pursuant to FAR 9.406-2(b)(1)(i) (48 CFR 9.406-2(b)(1)(i)).
SECTION I: CONTRACT CLAUSES
52.202-1 Definitions June 2020
52.203-3 Gratuities April 1984 52.203-5 Covenant Against Contingent Fees May 2014
52.203-7 Anti-Kickback Procedures June 2020
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity May 2014
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity May 2014
52.203-12 Limitation on Payments to Influence Certain Federal Transactions June 2020
52.203-17 Contractor Employee Whistleblower Rights November
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements January 2017
52.204-9 Personal Verification Contractor Personnel January 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards June 2020
52.204-13 System for Award Management Maintenance October 2018
52.204-14 Service Contract Reporting Requirements October 2016
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities
July 2018
52.204-27 Prohibition on a ByteDance Covered Application June 2023 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition December 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors
Debarred, Suspended, or Proposed for Debarment November
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters October 2018
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations November
52.215-2 Audit and Records – Negotiation June 2020
52.215-8 Order of Precedence – Uniform Contract Format October 1997
52.215-21 Requirements for Certified Cost or Pricing Data and Data Other than Certified Cost or Pricing Data – Modifications
November
52.219-6 Notice of Total Small Business Set Aside November 52.219-8 Utilization of Small Business Concerns February 2024
52.219-14 Limitations on Subcontracting October 2022
52.219-28 Post-Award Small Business Program Representation February 2024
52.222-1 Notice to The Government of Labor Disputes February 1997 52.222-3 Convict Labor June 2003
52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation May 2018
52.222-6 Construction Wage Requirements August 2018
52.222-7 Withholding of Funds May 2014 52.222-8 Payrolls and Basic Records July 2021
52.222-9 Apprentices and Trainees July 2005
52.222-10 Compliance with Copeland Act Requirements February 1988
52.222-11 Subcontracts (Labor Standards) May 2014
52.222-12 Contract Termination-Debarment May 2014
52.222-13 Compliance with Construction Wage Rate Requirements and Related Act Regulations May 2014 52.222-14 Disputes Concerning Labor Standards February 1988
52.222-15 Certification of Eligibility May 2014
52.222-21 Prohibition of Segregated Facilities April 2015
52.222-26 Equal Opportunity September
52.222-27 Affirmative Action Compliance Requirements for Construction April 2015
52.222-35 Equal Opportunity for Veterans June 2020
52.222-36 Equal Opportunity for Workers with Disabilities June 2020
52.222-37 Employment Reports Veterans June 2020
52.222-40 Notification of Employee Rights Under the National Labor Relations Act December
52.222-50 Combating Trafficking in Persons November
52.222-54 Employment Eligibility Verification May 2022
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 January 2022
52.223-3, Alt 1 Hazardous Material Identification and Material Safety Data February 2021, J l 199552.223-5 Pollution Prevention and Right-to-Know Information May 2024
52.223-21 Foams June 2016
52.225-13 Restrictions on Certain Foreign Purchases February 2021
52.227-1 Authorization and Consent June 2020
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement June 2020
52.227-4 Patent Indemnity – Construction Contracts December
52.228-2 Additional Bond Security October 1997
52.228-5 Insurance – Work on a Government Installation January 1997
52.228-11 Individual Surety—Pledge of Assets February 2021
52.228-12 Prospective Subcontractor Requests for Bonds December
52.228-14 Irrevocable Letter of Credit November
52.228-15 Performance and Payment Bond – Construction June 2020
52.229-3 Federal, State and Local Taxes February 2013
52.232-5 Payments under Fixed-Price Construction Contracts May 2014
52.232-17 Interest May 2014
52.232-23 Assignment of Claims May 2014
52.232-27 Prompt Payment for Construction Contracts January 2017
52.232-33 Payment by Electronic Funds Transfer-- System for Award Management October 2018
52.232-39 Unenforceability of Unauthorized Obligations June 2013
52.232-40 Providing Accelerated Payments to Small Business Subcontractors March 2023
52.233-1, Alt 1 Disputes May 2014 December
52.233-3 Protest After Award August 1996 52.233-4 Applicable Law for Breach of Contract Claim October 2004
52.236-5 Material and Workmanship April 1984
52.236-6 Superintendence by the Contractor April 1984
52.236-7 Permits and Responsibilities November
52.236-8 Other Contracts April 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. April 1984
52.236-10 Operations and Storage Areas April 1984
52.236-11 Use and Possession Prior to Completion April 1984
52.236-12 Cleaning up April 1984
52.236-13 Accident Prevention November
52.236-14 Availability and Use of Utility Services April 1984
52.236-15 Schedules for Construction Contracts April 1984
52.236-17 Layout of Work April 1984
52.236-26 Preconstruction Conference February 1995 52.242-13 Bankruptcy July 1995
52.242-14 Suspension of Work April 1984
52.243-4 Changes June 2007 52.244-6 Subcontracts for Commercial Products and Commercial Services February 2024
52.245-1 Government Property September
52.245-9 Use and Charges April 2012
52.248-3 Value Engineering – Construction October 2020
52.249-2, Alt 1 Termination for Convenience of the Government (Fixed-Price) April 2012
52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements
April 2012
52.249-10, Alt 1 Default (Fixed-Price Construction) April 1984
52.253-1 Computer Generated Forms January 1991
DIAR 1452.203-
Restrictions on Endorsements – Department of the Interior July 1996
DIAR 1452.204-
Release of Claims – Department of the Interior July 1996
DIAR 1452.215-
Examination of Records – Department of the Interior April 1984
DIAR 1452.236-
Prohibition Against Use of Lead-Based Paint – Department of the Interior July 1996
DIAR 1452.237-
Information Collection – Department of the Interior July 1996
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPEMENT November 2021
(a) Definitions. As used in this clause—
Backhaul means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network). Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).
Covered foreign country means The People’s Republic of China.
Covered telecommunications equipment or services means–
(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);
(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);
(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or
(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
Critical technology means–
(1) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;
(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of Federal Regulations, and controlled-
(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology; or
(ii) For reasons relating to regional stability or surreptitious listening;
(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);
(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal Regulations (relating to export and import of nuclear equipment and material);
(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part 121 of title 9 of such Code, or part 73 of title 42 of such Code; or
(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export Control Reform Act of 2018 (50 U.S.C.
4817).
Interconnection arrangements means arrangements governing the physical connection of two or more networks to allow the use of another's network to hand off traffic where it is ultimately delivered (e.g., connection of a customer of telephone provider A to a customer of telephone company B) or sharing data and other information resources.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of the producer or provider of covered telecommunications equipment or services used by the entity that excludes the need to include an internal or third-party audit.
Roaming means cellular communications services (e.g., voice, video, data) received from a visited network when unable to connect to the facilities of the home network either because signal coverage is too weak or because traffic is too high.
Substantial or essential component means any component necessary for the proper function or performance of a piece of equipment, system, or service.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. The Contractor is prohibited from providing to the Government any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract, or extending or renewing a contract, with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract.
(c) Exceptions. This clause does not prohibit contractors from providing—
(1) A service that connects to the facilities of a third-party, such…