1C_sign_in_Sheet_0003.pdf
PDF 4 MB Posted
- Solicitation number
- 140P2025R0032
About this file
This document is a Request for Proposals (RFP) for the ACAD 309000 Harden Farm Employee Housing Phase 1C project at Acadia National Park. The solicitation is a total small business set-aside under NAICS code 236116, seeking a contractor to construct new employee housing. The project involves building four multifamily housing units, specifically two 6-plex (1-bedroom, 1-bath) units and two 8-bedroom dormitories, along with associated site and utility improvements.
Key procurement details include a 540-calendar day period of performance, with a Notice to Proceed (NTP) expected on June 1, 2025. Proposals are due by 5 PM ET on July 18, 2025, and must be submitted via email to specified contracting officers. The contract will be awarded using a Best Value/Tradeoff method, with evaluation factors including project experience, technical approach, schedule, key personnel, and past performance. The solicitation requires a 15% self-performance requirement and includes Davis-Bacon wage requirements. Liquidated damages are set at $1,501 per day, and there are specific environmental considerations, including restrictions on tree removal to protect bat habitats.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-proposal Conference/Site Visit July 9th, 2025
Construct New Housing at Harden Farms (Phase 1C)
ACAD 309000
Solicitation Number 140P2025R0032
Request for Proposals No.1443N5010070901
INTRODUCTIONS
• NPS ACAD Staff
• Tony Jasper Contracting
Officer - NPS Denver Service Center
• Maggie Foley, Project Specialist – NPS DSC
• Participants
TODAY’S GOAL
• Provide offerors an opportunity to gain a better understanding of the project and the proposal submission/evaluation process.
• Provide potential offerors an opportunity for a thorough site investigation, in order to better understand some of the logistical constraints of the project.
• Questions are encouraged.
Questions shall be asked in the open for the entire group to hear.
Please no side-bar conversations.
Questions that can not be answered today will be answered via a solicitation amendment.
Agenda 8:30-9:30 – Meeting at Park Headquarters for a project overview, introduction.
9:30-10:30 – Meeting at the Harden Farm site
PROJECT BACKGROUND
This project includes the PMIS number (important for tracking)
– ACAD 309000
– See project specifications (Section 01 27 00 – Definition of
Contract Line Items) for detailed breakdown of CLINs
PROJECT BACKGROUND
Funding for this project is through multiple funding sources (HIP, Centennial, FOA, NPF)
The overall project will construct 8 new multifamily structures, associated site work, and reservice 2 existing structures
Phase 1c (green hatch) – Consists of the following: Two 6-plex (1-bedroom, 1-bath) units, two 8-bedroom dorms, and associated site and utility improvements
Note: Phase 1a and 1b – are currently under construction
PROJECT SCOPE
• Phase 1c will construct 4 multifamily employee housing units.
• Generally, the sites will require the following types of work (see specifications/dwgs for site-specific requirements):
– Erosion controls
– Utility removal, abandonment, and/or cut & cap
– New adjacent parking
– New site utilities
– Misc. other site work tasks
BATS
Presence of Federal and/or State listed bats has been observed or detected at multiple sites across the project area.
In coordination with USFWS, and in an effort to minimize disturbance to bat habitat, this project includes timing restrictions on all work at specific locations where bat presence has been confirmed.
Tree removal will be limited to prior to April 15 and after October 31) More information about bats can be found in spec section 01 11 00 1.7.I. (Special Construction Requirements).
Northern Long-eared Bat
NPS SENSITIVE SITE
• Contractor shall notify the CO at least 2 weeks in advance of any site work.
SOLICITATION KEY POINTS
• Released to SAM.gov on June 4th
• Procurement is being conducted as a Total Small Business
Set-Aside under NAICS code 236116.
• Period of Performance 540 calendar days after NTP
• One Firm-Fixed-Price contract will be awarded
• Source selection will be made using Best Value/Tradeoff method (see FAR 15.101-1)
CLIN STRUCTURE
Note that the scope is all base, no options are included, and offerors should carry $25K for CLIN 006
Key Solicitation Clauses
• Special Requirement 1 - Key Personnel
– PM, Superintendent, QC Manager and Safety Manager – no substitutions for first 120 days)
• Liquidated Damages ($1,501/day)
• Davis Bacon Wage Requirements apply – see Attachment 3
PROPOSAL INSTRUCTIONS
• Please read Section L thoroughly
• Email submissions to CO/CS on or before 5pm ET, July 18th, 2025
– Tony_Jasper@nps.gov, john_kotchian@nps.gov and CS_DSC_Proposal_Submission@nps.gov
• Make sure you verify receipt from NPS
• Pay attention to detailed page limitation requirements (10 page max technical approach, 4 page max schedule narrative)
• Offer Guarantee/Bid Bond is required – valid for 90 days
• Please submit your proposal as two separate pdf files – Volume 1:
Technical; Volume 2: Price
PROPOSAL EVALUATION
Basis of Award
• Evaluation process is explained in Section M
• The Contracting Officer (CO) will award a contract to the offeror who submits a proposal that conforms to solicitation requirements; offers fair and reasonable pricing; and provides the best value to the government considering all evaluation factors combined
• The Government may accept other than the lowest priced proposal when the perceived benefits of a higher priced proposal merit the price differential.
• All evaluation factors other than price (Factors 1-5), when combined are approximately equally important to price.
PROPOSAL EVALUATION
Basis of Award (Continued)
• NPS evaluates the technical volume first without knowledge of the offeror’s pricing. Once the evaluation team rates the technical volume, pricing is revealed. The team then determines which proposal offers the overall best value to the Government.
• NPS reserves the right to award a contract without entering into discussions. In the event that NPS chooses to enter into discussions, a competitive range will be established and the process described under FAR 15.306 will be followed.
PROPOSAL CONTENTS (Technical Volume)
• Technical Volume must contain the following five sections pertaining to each evaluation factor. These are listed in descending order of importance
Factor 1 – Project Experience Factor 2 – Technical Approach Factor 3 – Schedule Factor 4 – Key Personnel Factor 5 – Past Performance
PROPOSAL CONTENTS (Technical Volume)
Factor 1 – Project Experience – up to 3 relevant projects in the last 10 years. Use Project Experience Questionnaire form attached to the solicitation
Factor 2 – Technical Approach: 10 page narrative discussing your approach to THIS SPECIFIC PROJECT. Be sure to touch on things like protecting park resources, minimizing impacts to residents, phasing and sequencing.
Factor 3 – Schedule: Gantt Chart format schedule with NTP of June 1, and brief accompanying narrative.
Factor 4 – Key Personnel: Resumes for PM, Superintendent, QC Manager, and Safety Manager.
Factor 5 – Past Performance: PPQs for the 3 projects submitted under Factor 1.
PROPOSAL CONTENTS
Volume 2 – Business and Price Proposal
• Signed SF1442
• Acknowledgement of Solicitation Amendments
• Completed Contract Price Schedule
• Bid Bond
• Section K: Reps & Certs
• General References
• Proposed Substitutions
• Subcontracting Percentage Worksheet (to track required
15% self performance)
REMINDER
• Questions are due to the CO 10 days prior to bid deadline. It is the Offeror’s responsibility to take notes and submit questions in writing by the deadline.
• Submit questions only to Tony_Jasper@nps.gov and john_kotchian@nps.gov
• Email proposals on or before July 18, 2025.
• Solicitation and project documents are only changed with a formal amendment.
• Direct all inquiries to contracting until contract award. All inquiries will be redirected to contracting.
QUESTIONS?
Thank you for your time and interest in this project!
File details come from the government source that posted it. Updated .