B09_PreProposal_TriFold_Handout_Amd3_0003.pdf

PDF 295 KB Posted

Attached to
WRST 248940 - Deficient Water Treatment System
Solicitation number
140P2025R0007
Issued by

About this file

This Request for Proposal (RFP) solicits proposals for replacing the deficient water treatment system at the Glennallen Facility within Wrangell-St. Elias National Park in Alaska. The total small business set-aside contract (Solicitation No. 140P2025R0007) involves constructing a new water treatment building with protected vehicle parking, installing a new well, and relocating/upgrading water process systems to support future facility expansion. The current water system, originally constructed in 1995 and reconfigured in 2013, has infrastructure issues including a potentially compromised well casing.

Key procurement details include a pre-proposal site visit on April 2nd, 2025, proposal submissions due by April 23rd, 2025 at 12:00 pm AKT, and a 365-calendar day completion requirement. The National Park Service will evaluate proposals using a best value continuum trade-off process with equal importance placed on project experience, technical approach, and management approach. The contract will use NAICS Code 237110 for water and sewer line construction, with a maximum potential value of $45 million. Bid, performance, and payment bonds are required, and contractors must perform at least 15% of work with their own organization.

View the file

Other files

File Type Posted
B09_Attachment_3_-_WD_AK20250001_4_18_2025_Amd5Update_0005.pdf PDF
Sol_140P2025R0007_Amd_0005.pdf PDF
B09_Attachment_3_-_WD_AK20250001_3_14_2025_Amd4Update_0004.pdf PDF
Sol_140P2025R0007_Amd_0004.pdf PDF
B09_QR_Tracker_-_WRST_248940_Glennallen_Amd4_0004.xlsx XLSX spreadsheet
Sol_140P2025R0007_Amd_0003.pdf PDF
B09_PreProposal_SiteVisit_SignInSheet_Amd3_0003.pdf PDF
B09_QR_Tracker_-_WRST_248940_Glennallen_Amd3_0003.xlsx XLSX spreadsheet
Sol_140P2025R0007_Amd_0002.pdf PDF
B09_QR_Tracker_-_WRST_248940_Glennallen_Amd2_0002.xlsx XLSX spreadsheet
B09_RFP_Body_-_WRST_248940_Total_SB_Amd1Update_0001.pdf PDF
Sol_140P2025R0007_Amd_0001.pdf PDF
B08_Attachment_1_-_Specifications_WRST_248940_Glennallen_3Mar2025.pdf PDF
B08_Attachment_5_-_General_References.doc DOC document
B08_Attachment_2_-_Drawings_WRST_248940_Glennallen_3Mar2025.pdf PDF
B08_Attachment_4_-_LimitOnSubcontractingWorksheet.xlsx XLSX spreadsheet
B08_Attachment_6_-_Factor_1_PEQ_WRST_248940.docx DOCX document
B08_Attachment_3_-_Wage_Determination_AK20250001_1_31_2025.pdf PDF
Sol_140P2025R0007.pdf PDF
B08_RFP_Body_-_WRST_248940_Total_SB_3_12_2025_Issued.pdf PDF
B08_Attachment_7_-_PP_Factor_PPQ_WRST_248940.docx DOCX document
B08_Attachment_8_-_Detailed_Contract_Price_Schedule.xlsx XLSX spreadsheet
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASIS OF CONTRACT AWARD

• Best Value Continuum Trade-Off Process.

• The NPS DSC Contracting Officer is the Source Selection Authority for this acquisition.

• Alternate Proposals will not be accepted nor evaluated.

• The Government intends to evaluate Proposals and Award a Contract without Discussions with Offerors;

therefore, Initial Proposals should contain Offerors’ best terms from a technical and price standpoint.

• The Government reserves the right to conduct

Discussions, if the NPS DSC Contracting Officer / Source Selection Authority determines them to be necessary.

Request for Proposal (RFP) No.

140P2025R0007 Total Small Business Set-Aside

Pre-Proposal Site Visit:

Wednesday – April 2nd, 2025

@ 11am AKT

Meet-Up Address:

The Copper Center Headquarters Bldg.

Mile 106.8 Richardson Highway Copper Center, AK 99573

Pre-Proposal Site Visit Points-of-Contact:

Kim Eisberg, DSC Project Specialist Chris Wilcox, Chief Facilities Manager

Japheth Heidelberg, WRST Contact

QUESTIONS AFTER THE

PRE-PROPOSAL SITE VISIT

• Direct all questions, in writing via email, to the NPS DSC Contracting Officer and Contract Specialist identified below, ONLY.

NPS DSC Contracting Officer:

Amber Hughes amber_hughes@nps.gov

NPS DSC Contract Specialist:

Abigail Vil lareal abigail_vil lareal@nps.gov

• No answers will be provided on-site, during the Pre-Proposal Site Visit, nor by any other Government Personnel.

• Questions received by the NPS DSC Contracting Officer and Contract Specialist by the date annotated in the Solicitation and below, will be answered and provided to all prospective Offerors via formal Solicitation Amendment(s).

• Questions are due no later than close-of-business on April 16th, 2025.

• Any changes to the Request for Proposal (i.e. Solicitation Document) will only be issued by the NPS DSC Contracting Officer via formal Solicitation Amendment(s) on the www.SAM.gov website.

Bid, Performance, and Payment Bonds are required under this acquisition.

NAICS Code: 237110 – “Water and Sewer Line Related Structures Construction.” ($45M)

PSC: Y1NE – “Construction of Water Supply Facilities.”

WRST 248940 -

“Replace Deficient Water

Treatment System;

Glennallen Facility” mailto:amber_hughes@nps.gov mailto:abigail_villareal@nps.gov http://www.sam.gov/

52.211-10 – “Commencement, Prosecution, and Completion of Work.”

Work shall commence within 10 calendar days after the Notice to Proceed (NTP) is issued/received and complete the entire work ready for use not later than 365 calendar days.

52.211-12 – “Liquidated Damages – Construction.”

If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,055.00 for each calendar day of delay until the work is completed or accepted.

52.236-1 – “Performance of Work by the Contractor.”

The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15% of the total amount of work to be performed under the contract.

52.219-14 – “Limitations on Subcontracting.”

The prospective Contractor will not pay more than 85% of the amount paid by the Government for contract performance, excluding the cost of materials, to Subcontractors that are not similarly situated entities.

52.225-9 – “Buy American – Construction Materials.”

Applies to this project. Refer to the Clause and Provision 52.225-10 – “Notice of Buy American Requirements – Construction Materials,” for specific requirements and further details.

1452.228-70 – “Liability Insurance.”

The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the CO by an Insurance Company which is acceptable to the CO. The amounts of insurance shall be not less than:

$100,000 each person $500,000 each occurrence

$1,000,000 property damage

Clauses

Section L Instructions for the Submission of Offers and Other Information –

• Proposals are due no later than 12:00 pm

AKT on April 23rd, 2025.

• Proposals shall be submitted in separate Volumes, as follows:

o Volume I – Technical & Past Performance o Volume II – Business & Price

• Proposals shall be submitted, via email, to:

o amber_hughes@nps.gov;

o abigail_villareal@nps.gov; and o CS_DSC_Proposal_Submission@nps.gov

• Submissions shall contain the Solicitation

Number, Park PMIS, and number of total emails. Refer to the example in Section L of the Request for Proposal.

Evaluation Factors

Evaluation Factors 1-3 are of equal importance;

Past Performance is less important than Evaluation Factors 1, 2, and 3.

• Factor 1: Project Experience &

Technical Competency

• Factor 2: Technical Approach & Schedule

• Factor 3: Management Approach

• Past Performance

• Price

Overall, all Evaluation Factors other than Price, when combined, are approximately equal to Price.

Refer to the Solicitation for specific details.

SUBMISSION &

EVALUATION

The scope of work includes construction of a new water treatment building including protected parking for water transportation vehicle, installation of a new well, relocation and upgrades to the water process systems to support projected future needs.

The Glennallen facility consists of multi-unit housing and maintenance facilities. This water system was constructed in approximately 1995 and then reconfigured in 2013 to address elevated iron and manganese. Water is pumped from a 237 foot deep well. The treatment train consists of the following:

• 10, 5 and 1 micron roughing filters.

• Chlorine injection.

• A 430 gallon chlorine contact tank.

• Two 12-inch greensand filters.

• A 1,000 gallon HDPE storage tank.

• Water is circulated in arctic pipe to the housing units to prevent freezing.

Backwash from the greensand filters is discharged into a cone bottom settling tank. The solids are periodically removed from the tank and the clarified water is discharged into an onsite septic system. The water quality from this source appears to be good, when properly operated. The peak water demand for the system is approx.

2,600 gpd.

A problem with this system is the well casing, which penetrates the floor in the water treatment plant, appears to be jacking. It appears that the casing had jacked about 4-in. It is possible that the casing has sheared below grade. At a minimum, this water system must be renovated to accommodate an expansion of a 50-bed bunkhouse at the facility in use.

Refer to the Section J Attachments Specifications and Drawings contain in the Solicitation for full details.

OVERVIEW OF PROJECT

mailto:amber_hughes@nps.gov mailto:abigail_villareal@nps.gov mailto:CS_DSC_Proposal_Submission@nps.gov

QUESTIONS AFTER THE PRE-PROPOSAL SITE VISIT
Direct all questions, in writing via email, to the NPS DSC Contracting Officer and Contract Specialist identified below, ONLY.
No answers will be provided on-site, during the Pre-Proposal Site Visit, nor by any other Government Personnel.
Questions received by the NPS DSC Contracting Officer and Contract Specialist by the date annotated in the Solicitation and below, will be answered and provided to all prospective Offerors via formal Solicitation Amendment(s).
Questions are due no later than close-of-business on April 16th, 2025.
Any changes to the Request for Proposal (i.e. Solicitation Document) will only be issued by the NPS DSC Contracting Officer via formal Solicitation Amendment(s) on the www.SAM.gov website.
WRST 248940 - “Replace Deficient Water Treatment System; Glennallen Facility”
/
Pre-Proposal Site Visit:
Wednesday – April 2nd, 2025 @ 11am AKT
Clauses
Submission & Evaluation
Evaluation Factors
Evaluation Factors 1-3 are of equal importance; Past Performance is less important than Evaluation Factors 1, 2, and 3.
Overall, all Evaluation Factors other than Price, when combined, are approximately equal to Price.

Overview of project

File details come from the government source that posted it. Updated .