B09-140P2024R0050-Amd_8_0008.pdf

PDF 366 KB Posted

Attached to
YELL 310533 Rehabilitate and Improve Old Faithful
Solicitation number
140P2024R0050
Issued by

About this file

This document is an amendment to a solicitation for the YELL 310533 Rehabilitate and Improve Old Faithful Water Treatment System project. The key details are:

The purpose of this amendment is to provide questions and answers received to date, word documents of the Small Business Participation and Subcontracting Plan forms, extend the overall period of performance to 1,078 calendar days after Notice to Proceed, provide as-built drawings, and extend the proposal due date to 2:00 p.m. Mountain Time on December 18, 2024. The solicitation is for rehabilitating and improving the Old Faithful Water Treatment System in Yellowstone National Park and is being issued by the National Park Service. The amendment provides clarification on items such as conduit and wire sizing, flow meter specifications, PLC and SCADA requirements, and other technical details. It also addresses questions related to site access, construction schedules, and contractor trailer accommodations.

View the file

Other files

File Type Posted
B09-140P2024R0050-Amd_11_0011.pdf PDF
Sol_140P2024R0050_Amd_0011.pdf PDF
Amendment_10_140P2024R0050_0010.pdf PDF
Sol_140P2024R0050_Amd_0010.pdf PDF
B09__Amend_09_140P2024R0050_Attachments_0009.pdf PDF
Sol_140P2024R0050_Amd_0009.pdf PDF
Sol_140P2024R0050_Amd_0008.pdf PDF
1980_OF_WTPplans_YELL_101_41195A_0008.pdf PDF
Amendment_8_SubKPlanForm__0008.docx DOCX document
Amendment_8_SMALL_BUSINESS_PARTICIPATION_DOCUMENT_0008.docx DOCX document
B09_Amend_7_140P2024R0050_Attachment_0007.pdf PDF
Sol_140P2024R0050_Amd_0007.pdf PDF
Sol_140P2024R0050_Amd_0006.pdf PDF
Sol_140P2024R0050_Amd_0005.pdf PDF
B09_Attachment_Amend_5_140P2024R0050_0005.pdf PDF
Sol_140P2024R0050_Amd_0004.pdf PDF
B09_Amend_4_140P2024R0050_0004.pdf PDF
Amendment_3_Attachments_0003.pdf PDF
Sol_140P2024R0050_Amd_0003.pdf PDF
Sol_140P2024R0050_Amd_0002.pdf PDF
B09-140P2024R0050-Amd_2_0002.pdf PDF
1_OFmtgOverview_1_0001.pdf PDF
2_OFmtg_1_0001.pdf PDF
Sol_140P2024R0050_Amd_0001.pdf PDF
B08-Attachment_9_-_YELL_WWTPS_Geotechnical_Interpretive_Report_20230804.pdf PDF
YELL-310533_FinalCD_OFWTP_Dwgs_Unsecure_8-16-2024_Part1.pdf PDF
B08_Section_J_Attachment_1_YELL-310533_FinalCD_OFWTP_Specs_8-16-2024.pdf PDF
YELL-310533_FinalCD_OFWTP_Dwgs_Unsecure_8-16-2024_Part2.pdf PDF
YELL-310533_FinalCD_OFWTP_Dwgs_Unsecure_8-16-2024_Part3.pdf PDF
Sol_140P2024R0050.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2024R0050 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

11/19/20240008

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/27/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

YELL 310533 - Rehabilitate and Improve Old Faithful Water Treatment System

The purpose of this amendment is to provide the following:

1. To provide the Questions and Answers received to date.

2. To provide word documents of the Small Business Participation document and the Small

Business Subcontracting Plan form.

3. The overall period of performance for the work is extended to 1,078 calendar days after

Notice to Proceed.

4. To provide the as built drawings for the Old Faith Water Treatment Plant.

5. To extend the proposal due date to 2:00 p.m. Mountain Time, December 18, 2024. There

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Vicki Freese-supler

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2024R0050/0008 is no extension to the cut off date for questions and it remains unchanged at November 18, 2024.

All other terms and conditions of the solicitation remain unchanged.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

140P2024R0050 YELL 310533 Rehabilitate and Improve Old Faithful Water Treatment System

Question No. Sheet or Reference Question Response Date

Answered Amendment

Number

Is there supposed to be a pressure cleanout on the buried 4” SL in between the Backwash Pond Pumphouse and WTP? Plan dwg 105C401 indicates a pressure cleanout but it’s not shown on profile dwg 105C807-P.

There are two pressurized cleanouts on the 4" SL. Profiles may not show cleanouts, refer to plans for cleanout locations. 10/2/2024

Please confirm the due date for questions is 7 days prior to bid, or October 4th. Our confusion is Amendment 0001 listed October 1st as the cut off date for questions. Please confirm questions are due October 4th.

This date has been changed to November 4, 2024 at 2:00 p.m.

MT. Updated per response to Q66. 10/2/2024

Section L, Factor 2: Please confirm that for Factor 2 the requested descriptions of Teaming Experience, Remote Work, and packaged water plant facilities experience are supposed to be discussed in answering the Project Experience Form, not an accompanying narrative, correct?

Correct 10/2/2024

Section L, Factor 2: Please confirm whether offerors are limited to 3 projects total or if primes may submit up to 3 projects and each key trade (process, mechanical/plumbing, electrical services) may each also submit up to 3 projects (for a total of up to 12 projects)?

This is acceptable. However, please denote those projects which are being proposed for the prime and those of your key subcontractors.

10/2/2024

5 Section L, Factor 3: Please consider providing an updated NTP date beyond the due date of proposals and proposal validity period so presented schedules can be more realistic? This date is changed to Aprl 15, 2024 10/2/2024

6 Where on the SAM.gov link can I find a plan holders list for this project and does the bid date remain October 11, 2024?

Information regarding the solicitation can be found at the following link:

https://sam.gov/opp/1ad7c0f75a2b408bb12d7cb41d591e24/vie w.

10/2/2024

7 Can we get a two week extension on the Old Faithful project please? The business and cost proposals date will be extended to November 12, 2024 at 2:00 p.m. MT. 10/2/2024

8 Can you provide a list of NPS pre-approved weed-free aggregate pit sources that would be acceptable for this project?

The 2024 Yellowstone National Park Gravel Pit Inspection list is attached. This list is updated annually, and a new list will be provided for 2025 when it becomes available.

10/8/2024

The specifications state that a contracting officer’s trailer is required at each site. Can you clarify how many contracting officer’s trailers are required for this project? Is just one required?

Just one contracting officer’s trailer is required for the project. 10/8/2024

10 Please confirm what size conduit should be installed from transformer to the CT cabinet. Sheet 108E301 has duct bank A with EC-6 (3” conduit) & sheet 108E601 has EC-7 (4” conduit).

EC-6 should be used but this conduit size and installation should be closely coordinated with Northwestern Energy. 10/21/2024

11 What size conduit and wire are required from the CT cabinet to the Service Entrance cabinet? Match the wire and conduit size from the Transformer to the CT cabinet. 10/21/2024

Question No. Sheet or Reference Question Response Date

Answered Amendment

Number

Please confirm that the Electric Vehicle Charger is to be provided and installed by Contractor.

The only requirements to be followed for the charger are in Spec 26 05 04 paragraph 2.16 A, B & C .

The breaker and the conduit for the EV charger will remain however the conductors and charger are no longer required. 10/21/2024

Duct banks D, E, F & G are all shown on sheets 108E101 & 102 to enter into the building on the south or south-east portion of the building. Is the intent to run these underground conduits below the building slab? If so where in the lower level should they rise through? Should the before mentioned duct banks wrap around the building and come up at the north-east portion of the building and enter through the wall?

The intent for these ductbanks is to enter the building above grade at an appropriate location where shown and then route to their sources within the building.

10/21/2024

14 Do spare underground conduits need to be capped right at the underground riser or do they need to continue up the exterior wall to the interior of the building then capped?

Spare underground conduits at a building should be brought into the building and capped. 10/21/2024

The Instrument List in Specification 40 90 00 Supplement does not list sizes for the Magnetic Flow Meters for this project and there are no pipe sizes shown on the P&ID drawings. Please provide the pipe size for the following Magnetic Flow Meters:

110-FIT-101, 110-FIT-102, 110-FIT-178, 110-FIT-176, 110-FIT-189

Pipe sizes are on the mechanical (D) drawings. Pipe sizes for these meters are below:

a. 110-FIT-101 – 6” on 110D303

b. 110-FIT-102 – 2” on 110D303

c. 110-FIT-178 – 10” on 110D302

d. 110-FE-176 – 4” on 110D305, note the FIT transmitter is remote for this meter and is shown on 110D402

e. 110-FIT-189 – 4” on 110D307

11/4/2024 7

16 Is the Thermal Flow Meter 110-FE/FIT-186 shown on P&ID drawing 109N018 part of a Vendor package? If not, please provide the pipe size for this meter.

110-FE/FIT-186 shown on P&ID drawing 109N018 is a part of the Vendor package under Specification 22 10 01. 11/4/2024 7

Specification 40 91 00, section 2.04.F.1.a. - F4A Flow Element and Transmitter, Electromagnetic: For the House Water flow; Manufacturers and Products lists Xylem; (includes transmitter) Model Hydroverse, No or equal (tag # 110-FE/FIT-176) however, this flow meter has been discontinued. Would an Endress-Hauser Promag Magnetic Flow Meter be acceptable for the House Water flow meter? If not, please advise on a replacement for the Xylem flow meter.

Yes, an Endress-Hauser flow meter is acceptable. 11/4/2024 7

18 Please confirm that the trenching, backfill & (6) empty 3” conduits for the NWE primary circuit from MWE transformer to new junction box at Grand Loop is by contractor.

NWE will be performing the trenching placing the electrical conduit and backfilling. The Contractor will provide and place the fiber line and conduit in the trench.

11/18/2024 8

19 Please confirm that all work described in Notes 4, 6 & 7 on sheet 100G011 is all provided and installed by MWE.

That’s correct, segments of work and materials indicated by Notes 4, 6, and 7 will be by NWE. 11/18/2024 8

Answered Amendment

Number

20 What type or spec for the innerduct in new 4” conduit for fiber installation? Maxcell Edge Detectable 3-cell innerduct suitable for 4” conduit. 11/14/2024 8

21 Is there any type or spec for the 24-strand fiber called for in ductbank H on sheet 108E301?

To be addressed in Amendment 9

22 Please provide what type of telephone cable is required in the 2” conduit reflected in ductbank H on sheet 108E301 so that all bids can be consistent and equal.

The telephone cable in the indicated conduit will be provided by Lumen 11/18/2024 8

Does the new trench ductbank for NWE new main circuit, note 11 sheet 108E101 & ductbank H sheet 108E301 need to follow General Note #2 on sheet 108E101. The requirement of reinforced concrete encasement?

Where DB line type is used, concrete encasement is not required.

Reference Detail 2605-420 for direct-buried raceway installation.

11/14/2024 8

The PLC Layout drawing 109N023 Bill of Materials implies the plant PLC should be Allen Bradley ControlLogix. Is the intent that all Vendor control panels should also use Allen Bradley ControlLogix PLC’s? If not, we would like to request all Vendor PLC panels use either the Allen Bradley CompactLogix or Allen Bradley MicroLogix for their PLC’s which will allow for easier integration into SCADA and require less time during start-up.

To be addressed in Amendment 9

Specification 40 91 00, Instrumentation & Control Components, Section 2.05 PLC Panel Components, B.3. states that “All discrete and analog I/O modules shall be individually isolated inputs and outputs.” However, in order to isolate digital inputs, each point would require its own power supply, taking a lot of space in the panel. Would the non-isolated 16 point 24VDC module be acceptable for all digital input points?

To be addressed in Amendment 9

Specification 40 96 00, section 1.05.D., page 3, references notifying the City’s representative of any errors or omissions in the Project Control Strategies. Please clarify that the contact should be the National Parks Contracting Officer for this project.

Confirmed that the Contractor shall notify the Contracting Officer. 11/18/2024 8

We would like to double check that the server requirements, Specification 40 91 00, section 2.06.A. through section 2.06.D., page 47-51, are correct for this job and do not reference a different job.

To be addressed in Amendment 9

We would like to verify that the park is aware of the $100,000 cost commitment for a Stratus server (specification 40 91 00, section 2.06.C.1.a., page 49) with redundant server storage subsystems (specification 40 91 00, section 2.06.D.3., page 50).

The NPS is aware of the costs associated with these items.

11/19/2024

Answered Amendment

Number

We would like to verify that the park really wants thick clients with DVD drives, Specification 40 91 00, section 2.06.E.2, page 51. Current practice leans toward thin clients. Please confirm which is preferred.

To be addressed in Amendment 9

Specification 40 91 00, section 2.06.B.1.a.4, Alarming Software, references GE iFix (currently in use at parks in the Mountain West), but the SCADA software specification 40 91 00, section 2.06.A.1.a calls for a different software, Aveva from Schneider, or equal. Is GE iFix SCADA software acceptable for both the SCADA system and alarming?

To be addressed in Amendment 9

Specification 40 91 00, section 2.06.G.1, calls for server network racks that are 19” by 7-foot style, but there are no network racks in the specification. There are references to Network Panels OLFWTP-NTSW1 and OLFWTP-NTSW2. Please verify that two large cabinets are required.

To be addressed in Amendment 9

32 100G046 Pipe Schedule Please confirm that all EXP INT process pipe is to be banded with no paint coating.

Please refer to the Pipe Schedule for pipe painting requirements including color and banding requirements. Requirements for pipe labeling are shown in Section 10 14 00 Signage. 11/18/2024

33 110D902 2 - ISOMETRIC Are additional supports needed for 12" pipe connected to treatment skid?

Pipe support design requirements are called out in Section 40 05 15 Piping Support Systems, paragraph 1.05. 11/18/2024

110D902 2 - ISOMETRIC Are additional supports needed for 12" BWW pipe connected to filter?

Pipe support design requirements are called out in Section 40 05 15 Piping Support Systems, paragraph 1.05.

11/18/2024

35 Factor 5

Please confirm if the On-Site Safety Manager is allowed to be dual-hatted with the Superintendent and/or the On-Site Quality Control Manager?

No dual hatting, must be separate and apart from each other.

11/18/2024

36 Factor 2

Factor 2, Section L: Please allow projects completed in the last 12-15 years

No, Factor 2 will remains as is.

11/18/2024

37 Factor 2

Factor 2, Section L: The description on page 68 of 106 includes a definition of Prime Contractor experience as "… managing multiple subcontractors on projects the prime self-performed at least 50% of the cost of the contract, excluding materials..." This definition does not fit the industry standard of 10-20% self-perform; reference FAR 52.236-1 Performance of Work by the Contractor on page 40 of 106, which requires 15% self-perform, and does not exclude materials, for this project. Please remove this self-perform percentage from the Factor 2 instructions as it may disqualify otherwise highly relevant experience.

52.236-1 Performance Of Work by the Contractor is changed to 30% from 15%. Factor 2 is reduced to 30% from 50%. Per FAR

36.501 Performance of Work by the Contractor, this percentage may be as high as the contracting officer deems appropriate.

11/18/2024

Answered Amendment

Number

38 Factor 5 Factor 5, Section L: The requirements state "submit resumes for key personnel as identified in Section H." Section H details both "Key Personnel" and "Key Trades." Please confirm that resumes are only required for "Key Personnel" and not for "Key Trades."

Resumes are required for Key Personnel only. If an offeror wishes to provide resumes for key trades in addition that is acceptable. 11/18/2024

39 Factor 7 Factor 7, Section L: Please provide the Small Business Participation Plan template as a MS Word file, if available.

Attached

11/18/2024

40 Please provide the Small Business Subcontracting Plan template as a MS Word file, if available.

Attached

11/18/2024

The instrument list in Specification 409000 Supplement 03 includes several level switches that are listed with a Comp Code of L18, which is a float level switch in Specification 409100 Section 2.04 K. However, the instrument details on these same line items are either 4091-267 or 4091-265, both of which are tuning fork level switches. What type of switches should be used – float level switches or tuning fork level switches?

To be addressed in Amendment 9

If tuning fork level switches are required, please provide specification for tuning fork level switches. This impacts the following level switches: 105-LSH-103, 110-LSH-190, 110-LSH-

191, 110-LSL-191, 110-LSH-192, 110-LSL-192, 110-LSH-116, 110-LSHH-116, 110-LSHH-

117, 110-LSH-118, 110-LSH-120, 110-LSHH-120, 110-LSHH-121, 110-LSH-122, 110-LSH-

156, 110-LSHH-156, 110-LSH-125, 100-LSHH-126, and 110-LSHH-127.

To be addressed in Amendment 9

The instrument list in Specification 409000 Supplement 03 includes several level elements and transmitters that are listed with a Comp Code of L5, which is an ultrasonic level transmitter in specification 409100 Section 2.04 J. Each of these are listed with instrument details of either 4091-258 or 4091-257, which are both radar level transmitters. Please confirm whether radar level transmitters or ultrasonic level transmitters are required.

To be addressed in Amendment 9

If radar level transmitters are preferred, please provide specification for radar level transmitters.

This impacts the following level transmitters: 105-LET-103, 110-LE/LIT-116, 110-LE/LIT- 117, 110-LE/LIT-120, 110-LE/LIT-121, 110-LE/LIT-156, 110-LE/LIT-157, 110-LE/LIT-126 and 110-LE/LIT-127.

To be addressed in Amendment 9

The House Water Electromagnetic Flow Meter (110-FE/FIT-176) is called out as a Xylem Model Hydroverse with no equals in Specification 409100 Section 2.04 F. Xylem has indicated that the Hydroverse has been discontinued and that the Sensus Cordonel would be the replacement. Please confirm that this an acceptable substitution.

To be addressed in Amendment 9

46 The instrument list in Specification 409000 Supplement 03 and details shown on 110D101 4 appear to show two Clearwell Panels, this conflicts with Drawing 109N004 that only shows one panel. Please confirm whether there are one or two control panels.

There are two clearwell control panels and they are shown on 110D101 on the north wall labelled as 110-LCP-SMPL4-1 and

110-LCP-SMPL4-2. 11/18/2024

Please confirm solenoid valves are normally closed on all panels

The intent is to stop water flowing by gravity through analyzers when plant is not making water. The solenoid valves are normally open if plant is making water.

11/18/2024

Please confirm that the analyzer panels can be made from ½” thick “Natural” (Whiteish) HPDE

Per Drawing 110D501, the analyzer panels shall be made from PVC. No substitutions/alternatives can be considered during the solicitation phase.

11/18/2024

Answered Amendment

Number

49 Please confirm that the service shelves can also be made of ½” thick “Natural” (Whiteish)

HDPE

Per Drawing 110D501, the panel service shelves shall be made from PVC. No substitutions/alternatives can be considered during the solicitation phase.

11/18/2024

50 Are 4’-6’ tube style LED shop lights appropriate for panel light fixtures? What temp should light be? (4000K, etc)

Refer to Specification Section 409000.2.10.F.6 for panel light requirements. 11/18/2024

The Turbidity meters can be ordered with a flow meter which could be wired into PLC via the controller and act as both a meter and flow switch. That would make the external ones redundant. They also come with a needle valve to regulate flow to be installed on the outlet side of the meter. Similarly, the Chlorine analyzer flow through cell has both a needle type flow control valve and a flow switch. Along with a float style flow meter. Is it acceptable to utilize these flow switches and valves, or are the external flow switches and valves also required?

As shown on the drawings, external flow switches and valves shall be provided. No substitutions/alternatives can be considered during the solicitation phase.

11/18/2024

1” piping appears excessive given the minimal flows that run through this equipment. ¾” piping is typical for influent, then any branches that feed individual components are typically ½”; the 1” will add unnecessary cost. Examples- turbidity meters require 100-1000ml/min (.0264-.264 gpm) flowrate. The streaming current requires 1.5-2.5 GPM. The chlorine analyzer requires 30-50 liter/hr (.1321-.2201 gpm). Would ¾” and ½” as indicated above be acceptable?

The pipe size change from 1" to 1/2" or 3/4" is acceptable.

11/18/2024

53 What is the icon directly above the two standpipe drain valves at the sedimentation panel?

The icon above the two standpipe drain valves is intended to show pipe mounting clasps. 11/18/2024 8

54 What is shown at the top right region of the sedimentation panel? Is that just two different feed pipes coming into one? If so, please provide the following:

a.) Should they be valved?

B.) What size piping is this?

At the top right region of the sedimentation panel is a forked inlet to the streaming analyzer. The forked inlet comes from each of the sedimentation basin effluents. Operators will have the flexibility to open one, the other, or both to see how each of the basins are performing during commissioning and during regular operation. The forked inlet piping shall be 1".

11/18/2024

What is meant by air blowoff on the Filter Panel? Please clarify is this is one of the following:

a.) Air vac valve b.) Atmospheric vacuum breaker c.) Pressure relief valve

It is a ball valve that can be manually opened and closed to blow off trapped air.

11/18/2024

The detail for the Filter Panel appears to show a lot of tubing with small sections of hard pipe.

Should this be plumbed similar to the other panels with hard piping all through the valving, flow meters, switches, with clear PVC standpiping and overflow? Then go to tubing before it goes into the Turbidity meter?

The Filter Panel should be plumbed as shown on the drawings with tubing throughout the panel and small sections of hard pipe to serve as a tubing conduit only. No substitutions/alternatives will be considered during the solicitation phase.

11/18/2024

Please confirm that all construction personnel, delivery services, consultants, etc. related to this project will be permitted to access the park free of charge.

Yes, all construction personnel, delivery services, consultants, etc. related to this project will be permitted to access the park free of charge. All contractor personnel will receive entrance passes for entry.

11/18/2024

Please confirm that a horizontal cold joint can be located at the step of the Basement level mat slab per the image below?

It has been decided not to add a cold joint at the specified location, as doing so would alter the reinforcement arrangement and necessitate the installation of new waterstops at the joint. 11/18/2024

Answered Amendment

Number

The Coagulant Supply line after the pump on sheet 110D404 is identified as "½" COAG IN CONTAINMENT PIPE TO RAPID MIXER." However, sheet 110D904 Note 5 states, "TRANSITION TO DOUBLE CONTAINMENT PIPING WHERE ILLUSTRATED ON

DRAWINGS. ALL PIPING OUTSIDE OF CHEMICAL ROOMS SHALL BE DOUBLE

CONTAINED." Specification 40 27 00.15 for the Double containment piping calls out a spears product for which the minimum size is 1”.

Please clarify if the requirements is to provide a ½” tube in a regular schedule 80 PVC pipe per Sheet 110D404, or a 1” Double Containment per Sheet 110D904?

Per the drawings, provide 1/2" tubing inside Schedule 80 PVC.

11/18/2024

01 11 00 Paragraph H states that the contractor will have access to 30 trailer sites in 2024, and an additional 30 will be available in 2025 & 2026. Construction is anticipated to occur in 2025, 2026, 2027. Please confirm that the contractor will have 60 RV trailer sites available for the duration of the period of performance.

The intent of the wording is that the Contractor will have only 30 sites each year (2025, 2026, and 2027)

11/18/2024

Due to the seasonal road closures from November to April, this only allows for (2) 6.5-month construction seasons in 2025 and 2026 and 3 months to complete the remaining work in 2027 based on the current 822 calendar day performance period starting in April 2025. Based on preliminary schedule projections and input from subcontractors, the 822-day performance period is not feasible. Please allow offers to propose an extended performance period beyond the 822-day specified.

Period of Performance is extended to 1078 days after Notice to Proceed

11/18/2024

Specification section 01 57 19.12 Noise & Acoustics Management includes overly stringent restrictions on allowable noise levels. Due to the nature of the project, the noise level restrictions would severely impact our ability to perform the project work. During project execution, there will be noisy activity associated with work such as demolition, soil nail wall, general excavation, and other heavy equipment operations and construction activities within the project site and in the immediate proximity of the park. Please remove these noise restrictions as they are not realistic with the extent of work required for this project.

To be addressed in Amendment 9

63 Can contractor trailers/RV's be winterized and left in place during the off-season?

No. Contractor RVs cannot be left onsite over the winter. They need to be removed for snow clearing operations and to avoid becoming mice infestations.

11/19/2024

It is understood that water & sewer service hook-ups for RV pads are weather dependent, but please confirm that the 60 RV sites assigned to the contractor will remain available for use by the contractor and subcontractor personnel from April 15- NOV 1 for the project's duration.

Sites are available May 1 to Sep 30 with no issue and weather dependent use for April, October, and November. Water and sewer hookups are available, the water system is winterized based on temperature and generally active May 1 to Oct 30.

Note: 30 sites are available each year (2025, 2026, and 2027), not 60.

11/19/2024

65 Please confirm the approximate location of the contractor-assigned RV Spots and that they are suitable for full-size RVs.

Location for the 30 contractor camps is at Grant Village, lat 44.387, long -110.540, full size RVs/trailers can be utilized, sites are approx. 60’ deep, typical layout included with this Amendment.

11/19/2024

We are still awaiting the finalized scope of supply and equipment pricing from the specified process equipment manufacturer. Due to this and the upcoming Thanksgiving holiday, please consider extending the proposal due date to December 20th.

The proposal due date has been extended to 2:00 p.m. Mountain Time on December 18, 2024. There will be no extension of the date for receipt of questions it stays unchanged at November 18, 2024. 11/19/2024

Are as-built documents available for the existing water treatment plant to be demolished?

Yes, original 1980 plans are included with this Amendment.

11/19/2024

Answered Amendment

Number

The Coagulant Supply line after the pump on Sub Sheet No. 110D404 it says ½” Coag in Containment pipe to Rapid Mixer, however on Sub sheet No. 110D904 note 5 it says the pipe should be Double Containment. In the specifications for the Double containment it calls out a spears product that the minimum size is 1”. Should we be running a ½” tube in a regular schedule 80 PVC pipe per page 158? Or if we need to run the 1” Double Containment per page 163?

To be addressed in Amendment 9

69 The P&IDs show an overflow and drain for the Sodium Bicarbonate Solution Tank, the drawings do not. Please confirm which is correct?

To be addressed in Amendment 9

70 If Contractor is to install the overflow and drain please provide size(s)?

To be addressed in Amendment 9

71 Please confirm the pipe size from the Sodium Bicarbonate Solution Tank to Sodium Bicarbonate pumps.

To be addressed in Amendment 9

Sheet 110D904 (page 163) for the Sodium Hypochlorite Lines States: 1” SHC in Containment Pipe to (2) 1” SHC In Containment Pipe to SSB Influent Box (2) 1” SHC In 6” Containment Pipe to Chemical Injection Vault in Yard. The Same line also call out Note 5 which states, “Transition to Double Containment Piping where Illustrated on Drawings”. Is this drawing requiring us to run these lines as a 1” Double containment system inside another containment pipe? Or do we run 1” tubing inside the PVC Carrier pipe?

To be addressed in Amendment 9

OF WTP Solicitation_Amendment_Questions and Answer Tracker-Updated 11-18-24.pdf
Sheet1