This document appears to be an addendum to a federal solicitation related to the rehabilitation and expansion of a wastewater treatment plant. The key details are:

The solicitation number is 140P2024R0010 and the project title is "MORU 272051 - Rehabilitate and Expand Wastewater Treatment Plant". The objective is to rehabilitate and expand the existing wastewater treatment plant to increase flow and treatment capacity. The solicitation is issued by the Department of the Interior National Park Service National Office.

The addendum provides a detailed process flow diagram for the solids handling and tertiary treatment systems of the wastewater treatment plant. It identifies key equipment and components, including new centrifuges, conveyors, and polymer makeup units that are offered as a bid option. The base bid excludes replacement of this equipment. The diagram also shows various flow meters, pumps, tanks, and other process equipment that are part of the overall wastewater treatment system.

View the file

Other files

File Type Posted
Sol_140P2024R0010_Amd_0004.pdf PDF
Sol_140P2024R0010_Amd_0003.pdf PDF
Addendum_2_Items_0003.pdf PDF
Questions_and_Answers_for_Solicitation_140P2023R0125_140P2024R0010_0003.xlsx XLSX spreadsheet
Sol_140P2024R0010_Amd_0002.pdf PDF
B08_Solit_PSP_Vol_I_PastPerf_REQD(1)_0002.pdf PDF
MORU_272051_Site-Visit_November_02__23_0001.pdf PDF
Sol_140P2024R0010_Amd_0001.pdf PDF
Attachment_11_Construction_WD_(Davis_Bacon_Wage_Rates)__SD20220032_-_Building.pdf PDF
Sol_140P2024R0010.pdf PDF
Attachment_6_STATEMENT_OF_STRUCTURAL_TESTS_AND_SPECIAL_INSPECTIONS.pdf PDF
Attachment_1a__Specs_VOL_2_CD_FINAL-_Div_1___T_O_C.pdf PDF
Attachment_9_PSP_VOL_I.pdf PDF
Attachment_4_VOLUME_3__South_Bldg__COMPLETE.pdf PDF
Attachment_2_VOLUME_1_Series_00-01__General__Civil.pdf PDF
Attachment_8_WWTP_Closeout-OperationMaintenance-Requirements.pdf PDF
B08_Solit_1442_Clauses_Construction_4_23_24.pdf PDF
Attachment_12__Construction_Contract_Administration_Form.pdf PDF
Attachment_10a_Fillable_-_ContractPriceSchedule_23_6_13_CD.xlsx XLSX spreadsheet
Attachment_3_VOLUME_2__North_Bldg__COMPLETE.pdf PDF
Attachment_10b_PSP_Vol_II_SubKPlan__Apr24.docx DOCX document
Attachment_9a_Bid_Bond__VOL-1-24-16e.pdf PDF
Attachment_10_PSP_VOL_II.pdf PDF
Attachment_5_VOLUME_4__Series_04-09__COMPLETE.pdf PDF
Attachment_1__Specs_VOL_1_CD_FINAL-_Div_1___T_O_C.pdf PDF
Attachment_7_MORUGeotechnical_Report.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RWAS-1

ARP-1

M

FLOW

METER

E

M

FLOW

METER

E

RWAS-2

M

FLOW

METER

E

M

FLOW

METER

E

M

FLOW

METER

ARP-2

M

FLOW

METER

RAS/WAS

SUCTION

(FROM

CLARIFIER 1)

RECYCLE/RAS

DISCHARGE

(RAS FROM

CLARIFIER 1

RECYCLE FROM

BASIN 1B (1OX1a))

RECYCLE

SUCTION

(FROM BASIN 1A

(1OX1b))

(NOT USED)

WAS DISCHARGE

RECYCLE

SUCTION

(FROM BASIN 2A

(2OX1b))

(NOT USED)

RECYCLE/RAS

DISCHARGE

(RAS FROM

CLARIFIER 2

RECYCLE FROM

BASIN 2B

(2OX1a))

RAS/WAS

SUCTION

(FROM

CLARFIER 2)

NORTH BUILDING SOLIDS SCHEMATIC FOR ANOXIC-OXIC-ANOXIC-OXIC (AOAO) PROCESS

A

B

CD EF

G

WAS/SCUM FROM

NORTH BUILDING/

CLARIFIERS

TO WINTER

SOLIDS STORAGE

FROM WINTER

SOLIDS STORAGE

SOLIDS

HOLDING

TANK

M

FLOW

METER

M

FLOW

METER

CENTRIFUGE-1

CENTRIFUGE-2

GRINDER

CENTRIFUGE

FEED PUMP-1

CENTRIFUGE

FEED PUMP-2

VENT

VENT

CONVEYOR-2

CONVEYOR-1

TRUCK

LOADING

CONVEYOR

TRUCK BAY

DRAIN

TO EQ BASIN

NPW POLY

SOLIDS DEWATERING SCHEMATIC

TO SOLIDS HOLDING

SAND

FILTER-1

RE-AERATION

COLUMN-1

UV-1 M

FLOW

METER

TO OUTFALL

FILTER FEED FROM

CLARIFIER NO. 1 M

SAND

FILTER-2

SAND

FILTER-3

FILTER FEED FROM

CLARIFIER NO. 2 N RE-AERATION

COLUMN-2

TO NORTH

BUILDING SUMP

UV-2

COMPOSITE

SAMPLER

TERTIARY TREATMENT

VENT

THRU

ROOF

BIOSOLIDS

TANK-1

VENT

THRU

ROOF

2 1/2" Ø

WAS/SCUM FROM

NORTH BUILDING/

CLARIFIERS

WAS/SCUM TO

CENTRIFUGE

FEED PUMP

PUMP TO MANHOLE SMH-1

PROPOSED WINTER SOLIDS BUILDING

P

R

R

S

S

TSS

AIT

NTU

AIT

NO3

AIT

pH

AIT

pH

AIT

NTU

AIT

DO

AIT

NH3

AIT

NO3

AIT

OP

AIT

RECYCLE

SUCTION

(FROM BASIN 1B

(1OX1e))

J

RECYCLE/RAS

DISCHARGE

(TO BASIN 1B

(1OX1c))

(NOT USED)

H

RECYCLE/RAS

DISCHARGE

(TO BASIN 2B

(2OX1c))

(NOT USED)

L

RECYCLE

SUCTION

(FROM BASIN 2B

(2OX1e))

K

ARP-3

(BACKUP)

M

FLOW

METER

NC

NC

NC

NC

NC

NC

NC

NC

NC

NC

NC

NC

TO PROCESS BASINS

FI

LT

ER

BY

PA

SS

CHECK

VALVE

SUMP PUMP

SP-1

WINTER SOLIDS

PUMP-2

WINTER SOLIDS

PUMP-1

BIOSOLIDS

TANK-2

KEYNOTES - GENERAL

# DESCRIPTION

G01 BID OPTION 1, PROVIDE NEW CENTRIFUGES (O3-CEN-1 &

03-CEN-2), SOLIDS CONVEYORS (03-CNV-1, 03-CNV-2, & 03-CNVT-1),

POLYMER MAKEUP UNITS (03-CPB-1 & 03-CPB-2), AND PIPING. THE

BASE BID EXCLUDES REPLACEMENT OF THIS EQUIPMENT.

GXX

G01

GENERAL NOTE

1. SEE SPECIFICATION SECTION 01 27 00 FOR DESCRIPTION OF

BID OPTIONS.

MicroC

INLINE

MIXER

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

OF

TITLE OF SHEET

PROCESS FLOW

DIAGRAMS

186787A

14A 235

CLR

KSP

DJG

06/13/23 MOUNT RUSHMORE NATIONAL MONUMENT

272051 00-

D004

FINAL CONSTRUCTION DOCUMENTS

Sheets and Views
00-D004

File details come from the government source that posted it. Updated .