- YOSE 231409 - Re-Roof the Big Trees Lodge
- Solicitation number
- 140P2022R0132
About this file
This document contains questions and answers related to a solicitation for re-roofing the Big Trees Lodge located in Yosemite National Park. Key details include that the solicitation is for replacing the roofing materials on the main lodge building and addresses questions regarding specifications such as roofing materials, flashing details, environmental considerations including lead abatement, and logistics for performing the work while the facility remains occupied. The period of performance is 120 calendar days from notice to proceed, though this may be adjusted to account for material procurement lead times given current supply chain issues. The National Park Service is the contracting agency.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0005
| Amendment | Number | Question | Response |
| Amd 4 - Issued 9/22/2022 | 1 | The [NAICS] code 238160 - Roofing Contractors is listed. Because there are multiple trades involved outside of just roofing, as a Licensed General B Contractor, can we bid the project? | As long as the Prime Offeror is a Small Business under NAICS 238160, per their SAM.gov Reps and Certs under FAR 52.219-1, they are welcome to Bid on this project requirement / Solicitation. |
| 2 | Is there a clause for winter exclusion in the contract? | No, there is not a specific "winter exclusion" clause in the contract. | |
| 3 | Will Govt. accept CPARS or a Previous PPQ obtained from an already completed project. (Attachment 6)? | Please submit this portion of the Volume I Proposal in accordance with Section L of the Solicitation for Factor 4 - Past Performance. |
As specified in Section M, the Government shall also utilize information obtained from other sources, such as CPARS, in addition to contacting other persons possessing information relevant to the Past Performance evaluation.
| 4 | Will Govt increase number of pages allowed for factor 4? | No, the page limitation for Factor 4 - Past Performance remains unchanged from 9 pages. | |
| 5 | [CONTRACTOR] would like to request a time extension to the proposal due date of at least one week from the time the contractors questions are answered. Please advise if this is feasible. | The Government is granting a 12 day Extension to the Proposal Due Date and Time thru October 12, 2022 (no later than 12pm Mountain Time), in accordance with the submission instructions identified in Section L of the Solicitation. | |
| Amd 5 - Issued 10/4/2022 | 6 | Does the Govt. wish to have all the gutters and downspouts removed and replaced where they currently exist on the hotel. Plan does not address curtain areas where they currently are in place. | Yes, the scope of the project includes new gutters and downspouts. Refer to 01 11 00 - Summary of Work, Para 1.2.4.e. |
| 7 | KTR is being told by manufacturer that there is no guarantee that the product being specified is available or when it might be available. The closet alternative is Barn Cedar Shake, 30” L x6” w x 5/8” thick, premiums, vertical grain. 3 months lead time. Would Govt. accept this alternative? | No, the grades and sizes of the have been reviewed and Approved by the SHPO for this project. | |
| 8 | Surrounding buildings have standard ridge and hip caps. Does Govt. want to match this or go with detail 4/A501? | Refer to the Detail on the Drawings / See: Dtl# 4/A501 & Dtl# 4/A505 | |
| 9 | Is it the Govt. intent to replace all the plywood sheathing on the veranda roof or just where it is removed to allow for fall protection anchors. | No, the Detail is intended to depict reinforcing the anchor location, only. | |
| 10 | For bidding continuity will the Govt. supply a percentage of damaged substrate to be replaced and of wood (posts, fascia, siding etc.) for replacement? | No. | |
| 11 | 7/A201 states contact CO to determine if siding, fascia and trim to be removed is too damaged to reinstall. If so, KTR will be given a mod to the contract for extra cost of material. Can Govt. ensure reasonable response times. | We anticipate no more than 10 business days for government response. | |
| 12 | The lead/ACM report states lead is present in the exterior paint (windowsills, frames and walls). Will the Govt. provide an approx. amount of SF of siding, LF of facia and post and trim to be removed, replaced and disposed of? Abatement company will need to be on site for the siding, ladder and sign on the head wall of the hotel. | No. The Offeror will need to do their take offs (estimating) per the plans and through their respective site visit(s). | |
| 13 | Will the KTR be able to get close to the building with necessary equipment, reach lifts, man baskets etc. Could cause a disturbance to soil and plant life. | Yes, per the specifications; however, any disturbance to existing conditions will need to be restored by the Contractor. | |
| 14 | It appears from the attic that plywood sheathing is not installed on 100% of the building. Would the Govt. like plywood installed where there is currently step sheathing. If so, can Govt. supply approx. SF of plywood desired. | If there are areas where plywood sheathing does not exist, they should be evaluated to determine if they meet the substrate requirements for the Class A roof assembly. If the spaced sheathing meets the requirements given in the manufacturer's instructions, new plywood sheathing is not required. If, for some reason, the spaced sheathing does not comply, new plywood will be necessary. | |
| 15 | Is KTR responsible for repainting existing WAWONA HOTEL sign or the flashing only. | No, to be protected per notation on sheet# A201. | |
| 16 | Are there any site specific environmental issues that the KTR might not know of that the Govt. could supply information on. I.E., nesting birds, animals, endangered or protected plants, vegetation, dust control, run off, etc. | There are possibilities of a number of environmental factors which Offerors will need to address in their respective offers, to include but not limited to Lead, Asbestos, Covid 19 (and, the various strains or variants), Hantavirus, various possible rodents (however, the Government is currently addressing the rodents discovered during the initial site investigations). Offerors will need to review the Governments investigative reports included in the Solicitation. | |
| 17 | Will there be any special inspections required from the historic or environmental offices that the KTR needs to be aware of during the project? May be a need to halt production at times. | Offerors should anticipate bi-weekly participation by both the environmental and historical representatives of the Government throughout the project. | |
| 18 | As the facility remains open during construction, for safety reasons will KTR be able to divert pedestrian traffic and also temporarily restrict access to the main entrance door. | The Contractor shall coordinate with the Park/Project Team and Hotel Concessionaire regarding any pedestrian traffic diversions or temporary restriction access to the main entrance door. | |
| 19 | Will the Govt. allow KTR to drop a Conex box in the parking lot for tool and material storage | Some parking, laydown and staging space will be provided as agreed to by the Park, Project Team, and CO. | |
| 20 | Drawing A201/A202, #10 Does ladder have historical value. Will KTR be allowed to build completely new ladders and reinstall | The ladder does have historical value and it should be repaired, if necessary, not replaced with a new ladder, since it is merely a feature not to be used as a ladder. | |
| 21 | Detail 1/A503 creates a maintenance issue. Rail should be removed, flashed and rail framed back in place. Details 3,4 and 5 of A502, detail 4 of A503, detail 3 of A506 will create maintenance issues also. Please verify KTR will be able to modify installation of flashing. When sealant becomes the primary method of waterproofing, it must be checked yearly. | The sealant shown on Detail 1/A503 is the first line of defense, of multiple lines of defense against water penetration. This detail was designed to protect the integrity of a historic window assembly, so while we understand that it is possible to replace historic material with new, it was a conscious decision to do otherwise. Bidders should assume that they will not be able to modify the installation of flashing. While the NPS is open to discussion of specific details, for bidding purposes, it should be assumed that the drawings and specifications govern the design's intent. | |
| 22 | Will KTR be responsible for correcting deck flashing around entire building, where water is gathering and decaying posts and trim. | No, deck repairs are not a part of the scope of design or construction for this request. | |
| 23 | Please verify Govt. does not want permanent fall protection installed on the upper roof. Veranda roof only. | The upper roof is not used as a working walking surface, therefore, a fall protection system is not required at this level. | |
| 24 | Can Govt. verify that there is no lighting in or on the ceiling of the veranda roof. | There is likely lighting at the soffit of the veranda roof, however that is not a part of the project's scope. | |
| 25 | Please clarify A-507. Could possibly create obstruction at ring attachment point? | The flashing and fastener heads need to be installed to allow the anchor to be installed in the plate. The fasteners should can be rotated to the side to ensure that the anchor can be roof tie off anchor. | |
| 26 | In S-501 detail 3 it appears lead flashing will cover the vent holes. Is this acceptable? | Yes, however the location of the vent holes is subject to shop drawing review. | |
| 27 | Please confirm that the facility will be fully occupied during construction. | Yes, the facility will be occupied. Although not anticipated, occupancies could be at capacity. | |
| 28 | At the site visit there was some discussions as to the daily work hours of Monday thru Friday 8:00 am to 5:00 pm. If the hotel is occupied with guests, will the contractor be able to start work at 8:00am as stated in the RFP? Please confirm. | Yes, however operations should be performed to minimize interaction with and disturbance of the Hotel Guests. Since on-site activities began at 0800, therefore only quiet activities should be performed between 0800 and 0900. | |
| 29 | Will equipment such as boom lifts and fork lifts be permitted to access the complete perimeter of the building? | Yes, as scheduled to minimize disruption to the Hotel Guests. | |
| 30 | Block 11 of the SF-1442 indicates that the period of performance is 120 calendar days after the NTP and that its mandatory. Due to the current supply chain issues, the construction industry is experiencing very long lead times on materials. Manufactures are not holding their prices or committing to any delivery schedules until the products are approved and released for production. Will the Government allow the contractor to use the FAR Clause 52.216-4 (Economic Price Adjustment) to recover costs incurred due to inflation and the long lead times affecting the construction and manufacturing industries? | FAR Clause 52.216-4 (Economic Price Adjustment - Labor and Material) is not included, nor anticipated to be utilized during performance. The Government recognizes that the procurement leadtimes for some materials/products may take months, therefore, the Notice to Proceed will be issued once all materials/products are on-site/ready for installation and shop drawings/catwalk design are approved. | |
| 31 | Can the period of performance be increased to reflect the long lead times? | The 120 calendar day period of performance reflects the anticipated on-site work, only. Since the material/product procurement leadtimes are unknown, the period of performance noted on the SF-1442 and in FAR Clause 52.211-10 (Commencement, Prosecution, and Completion of Work) remain unchanged at this time. | |
| 32 | Can the NTP be issued after the submittals, shop drawings, and the Catwalk Design drawings are approved, materials are procured, and all materials are on-site? Or, can the period of performance be increased to reflect all of these items (submittals, shop drawings, Catwalk Design, material procurement)? | It is the Government's intent to issue the Notice to Proceed once all material/product submittals and shop/catwalk design drawings are approved, materials/products are procured and on-site/ready for installation, in which then the 120 calendar day period of performance "clock" would then begin. |
B09_QR Tracker YOSE 231409 WAWONA RE-ROOF
SOLICITATION 140P2022R0132