This document is an amendment to a solicitation for a design-build project to stabilize riverbanks along the Cuyahoga River and Ohio & Erie Canal Towpath Trail within Cuyahoga Valley National Park. The project involves stabilizing eight sites and will be awarded through a competitive solicitation. The amendment provides responses to questions from an earlier pre-bid meeting. It confirms that small businesses are not required to submit subcontracting plans but are required to provide small business participation documents with their proposals. The amendment also includes the pre-bid meeting sign-in sheet and powerpoint presentation as attachments. A pricing template is provided to standardize how offerors break down pricing by project phases in their responses. The closing date is unchanged. The National Park Service is the contracting agency and will award a firm fixed-price contract for the design-build services.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2022R0048 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy DOI, NPS, DSC Contracting Services

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

07/20/20220004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/22/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

CUVA 224822 - Cuyahoga Valley - Riverbank Stabilization Project - Cuyahoga Valley National

Park, Brecksville, Ohio - Design-Build-GAOA

The purpose of this amendment is provide responses to questions received as a result of the

Pre-Bid meeting. In addition, this amendment will provide for the Pre-Bid meeting sign in sheet and power point presentation.

Q1. It was my understanding from the prebid meeting that registered small businesses did not need to submit a Subcontracting Small Business Participation Document (SBPD), Attachment 5. Can you confirm this is correct? If this is correct, can you please elaborate on if specific goals for the various categories of business usage still apply and

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Joseph Halter

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2022R0048/0004 need to be tracked as project goals?

A1. All Offerors large and small must provide the Small Business Participation Document (SBPD), Attachment 5. Large businesses are also required to provide their draft Subcontracting Plan. The specific goals for the various categories of business do not apply to small businesses only large businesses.

Q2. The Pre-Bid Power Point and sign in sheets have not appeared on the Sharepoint site yet.

Would you be able to provide them?

A2. Both documents are included as part of this formal amendment.

Q3. For the Contract Price Schedule, we have

Section B from the solicitation packet; however, we can't find the referenced price proposal spreadsheet from the Denver Service Center's

Workflow website:

Forms/Templates/Samples/Guidelines - (US National

Park Service)(nps.gov) to use as a template to break down our work by phases. Can you provide that template?

A3. The template is being provided. The structure should follow the same CLINs in Section

B from the solicitation package.

All other terms and conditions of the solicitation remain unchanged and in full force and effect.