7B08_SACN_Final_CD_Specifications_Ph1_Complete_0001.pdf

PDF 16 MB Posted

Attached to
SACN-244692 Relocate Osceola Landing Boat Launch A
Solicitation number
140P2021R0060
Issued by

About this file

This solicitation is for the relocation of the Osceola Landing Boat Launch Area in Saint Croix National Scenic Riverway in Osceola Landing, Minnesota. The National Park Service seeks to move the boat launch and parking area to a new location that will provide improved visitor safety and access to the river. Offerors should propose designs and construction plans to relocate the launch approximately 500 feet east of the existing site, along with grading, surfacing, fencing and other site improvements. Proposals are due by February 15, 2022 and the contract is to be awarded by April 30, 2022. The anticipated contract period of performance is May 1, 2022 through September 30, 2023.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Saint Croix National Scenic Riverway Osceola Landing, Minnesota

Relocate Osceola Landing Boat Launch Area for Visitor Safety and Enjoyment

SACN

PMIS NO. 244692

Final Construction Documents Phase I

Project Specifications

NATIONAL PARK SERVICE

April 2021

TABLE OF CONTENTS

Phase I

SACN - 244692 TOC - 1

Phase I

DIVISION 01: GENERAL REQUIREMENTS No. of Pages

01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 56 39 Temporary Tree and Plant Protection 01 57 23 Temporary Stormwater Pollution Prevention 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 79 00 Demonstration and Training

DIVISION 02: EXISTING CONDITIONS

02 41 13 Selective Site Demolition 02 41 19 Selective Building Demolition

DIVISION 03: CONCRETE

03 30 00 Cast-in-Place Concrete

DIVISION 04: MASONRY

04 43 13 Adhered stone Masonry Veneer

DIVISION 05: METALS

05 12 00 Structural Steel Framing 05 31 00 Steel Decking 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications 05 52 13 Pipe and Tube Railings 05 70 00 Decorative Metal

SACN - 244692 TOC - 2

Phase I

DIVISION 06: WOOD, PLASTICS & COMPOSITES

06 15 16 Wood Soffit Decking

DIVISION 07: THERMAL AND MOISTURE PROTECTION

07 41 13 Standing Seam Metal Roof Panels 07 62 00 Sheet Metal Flashing and Trim 07 72 53 Snow Guards 07 92 00 Joint Sealants

DIVISION 08: OPENINGS

08 11 13 Hollow Metal Doors and Frames 08 36 13 Sectional Doors 08 71 00 Door Hardware 08 95 16 Wall Vents

DIVISION 09: FINISHES

09 65 13 Resilient Base and Accessories 09 91 00 Painting 09 96 53 Elastomeric Coatings

DIVISION 10: SPECIALITIES

10 14 00 Signage 10 21 13 Stainless-Steel Toilet Compartment Doors 10 28 00 Toilet Bath and Laundry Accessories

DIVISION 13: SPECIAL CONSTRUCTION

13 34 00 Fabricated Pre-Engineered Precast Concrete Structures

DIVISION 22: PLUMBING

22 00 00 Plumbing Basic Requirements 22 05 19 Plumbing Devices 22 05 23 General-Duty Valves for Plumbing Piping 22 05 93 Testing, Adjusting, and Balancing of Plumbing 22 10 00 Plumbing Piping 22 40 00 Plumbing Fixtures

SACN - 244692 TOC - 3

Phase I

DIVISION 26: ELECTRICAL

26 00 00 Electrical Base Requirements 26 05 09 Equipment Wiring 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems and Equipment 26 05 33 Raceways 26 05 34 Boxes 26 05 43 Electrical Vaults and Underground Raceways 26 05 53 Identification for Electrical Systems 26 09 23 Occupancy and Vacancy Sensors 26 09 24 Daylighting Controls 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 00 Overcurrent Protective Devices 26 28 16 Enclosed Switches and Circuit Breakers 26 43 00 Surge Protective Devices 26 51 00 Lighting

DIVISION 31: EARTHWORK

31 10 00 Site Clearing 31 20 00 Earth Moving 31 23 16 Topsoil 31 25 00 Erosion and Sediment Control

DIVISION 32: EXTERIOR IMPROVEMENTS

32 12 16 Asphalt Paving 32 13 20 Site Concrete 32 17 00 Paving Specialties 32 31 13 Gates 32 33 00 Site Furnishings 32 92 00 Turf and Grasses 32 93 00 Plants

DIVISION 33: UTLITIES

33 10 00 Water Utilities 33 40 00 Storm Drainage

SACN - 244692 01 11 00 - 1

091015 SUMMARY OF WORK

SECTION 01 11 00 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Osceola Landing, Saint Croix National Scenic Riverway, Chisago County, Minnesota. Osceola Landing is located along the Saint Croix River just west of the Town of Osceola, Wisconsin and accessed from Highway 243.

B. Osceola Landing is a day use recreational site within the Saint Croix National Scenic Riverway.

C. The Work consists of the following:

1. The Work includes improvements to the existing site including demolition of existing parking lot and driveway pavements; construction of new and rehabilitated parking lots, driveways, walkways, plaza paving, comfort station and vault toilet improvements, new shelter structures, new exhibits, new signage, and new boat ramp; shoreline stabilization;

tree removal; tree pruning; and new utility installation supporting the comfort station and site lighting.

D. Project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have full use of a majority of the site for construction operations during the construction period. The NPS will retain use within the northernmost parking lot (the non-motorized watercraft launch parking lot) as reflected on the contract drawings. Contractor’s use of the site is limited only by the Government’s right to perform work or to retain other contractors on portions of the site and providing access to the public to the non-motorized watercraft launch parking lot. The NPS shall retain use of the entirety of the northernmost parking lot during peak

SACN - 244692 01 11 00 - 2

season for visitation during the contract period – defined as April 30, 2022 to September 5, 2022.

All other dates within the contract period of performance are considered off-season visitation with work required within the northernmost parking lot allowed within this timeframe. Contractor shall maintain public access to both existing boat launches, with one boat launch remaining open at all times during maintenance improvements including within the contract documents. Boat launch maintenance improvements to be completed in the off-season period.

B. Storage of Materials: Confine storage of materials to the contractor limits of work site area.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Preservation of Cultural Resources:

1. The project site is not considered a culturally sensitive area although awareness during excavation and notification of inadvertent discoveries is required.

E. Driveways and Entrances: Keep driveways, parking stalls, sidewalks, parking lot drive aisles, and entrances serving premises clear and available to Government, Government’s employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3. Provide traffic control along the primary entrance drive for public use of the non-motorized watercraft launch parking lot during times of deliveries or other construction activity.

4. Contractor parking will be permitted within the contractor project limits and not permitted within the northernmost parking lot being retained for use by the NPS and the public.

F. Construction Camp: Establishment of a camp within the park will not be permitted.

G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

SACN - 244692 01 11 00 - 3

1.4 PUBLIC USE OF SITE

A. The area within the project limits will be closed to the public during construction. Contractor to provide fencing to control public access to the construction area. An area on-site including the primary entrance drive will be open to the public during construction. The area permanently open to the public is the non-motorized watercraft launch parking lot and launch area. The NPS shall retain use of the entirety of the northernmost parking lot during peak season for visitation during the contract period – defined as April 30, 2022 to September 5, 2022. All other dates within the contract period of performance are considered off-season visitation with work required within the northernmost parking lot allowed within this timeframe. Contractor shall maintain public access to both existing boat launches, with one boat launch remaining open at all times during maintenance improvements including within the contract documents. Boat launch maintenance improvements to be completed in the off-season period.

1.5 OCCUPANCY REQUIRMENTS FOR BUILDINGS

A. No existing buildings shall be occupied by the Government during entire construction period. The primary entry drive and non-motorized launch area including the parking lot will be occupied by the government and be open for public use. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations.

1. Maintain access to existing walkways, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

2. Maintain driveway access from Highway 243 to the non-motorized watercraft launch parking lot and launch area.

1.6 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: No work shall occur on weekends without prior approval from the CO.

SACN - 244692 01 11 00 - 4

2. Early Morning Hours: No work shall occur prior to 7:00 am without prior approval from the CO.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: If utility shutdowns are necessary, the contractor must receive prior approval from the CO for shutdown duration and hours. Any shutdown shall not exceed a duration of 2 hours and shall require authorization from CO and AHJ prior to scheduling shutdown.

D. Non-smoking Facility: Smoking is not permitted within the park or any government buildings.

Smoking is only allowed within enclosed personal vehicles.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

1.9 FINAL GEOTECHNICAL INVESTIGATION REPORT

A. A final geotechnical investigation report entitled NPS Osceola Landing Geotechnical Data Report, dated April 17, 2020, has been prepared by Golder Associates.

B. A final technical memorandum entitled Osceola Landing – Pavement Design and Earthwork Recommendations, dated March 20, 2020, has been prepared by Golder Associates.

C. A copy of the report and technical memorandum are available to all plan holders with this package.

D. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

SACN - 244692 01 11 00 - 5

1.10 ADDITIONAL REPORTS

A. Osceola Landing Arborist Report, dated May 21, 2020 prepared by Otak, Inc.

B. A copy of the report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

SACN - 244692 01 26 01 - 1

CONTRACT

031414 MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

SACN - 244692 01 26 01 - 2

031414 MODIFICATION PROCEDURES

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

SACN - 244692 01 26 01 - 3

031414 MODIFICATION PROCEDURES

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct

SACN - 244692 01 26 01 - 4

031414 MODIFICATION PROCEDURES

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule,” for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment,” in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

SACN - 244692 01 26 01 - 5

031414 MODIFICATION PROCEDURES

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented, and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project.

Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead ................ 10% Profit ........................ 9%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

SACN - 244692 01 26 01 - 6

031414 MODIFICATION PROCEDURES

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 26 01

SACN - 244692 01 27 00 - 1

DEFINITION OF

082714 CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No.0001

Osceola Landing Site Improvements – Base Bid

1. This item consists of work to compete improvements to the Osceola Landing site including demolition of existing parking lot and driveway pavements, construction of new and rehabilitated parking lots, driveways, walkways, plaza paving, comfort station and vault toilet improvements, new shelter structures, new exhibits, new signage, new boat ramp, shoreline stabilization, tree removal, tree pruning and new utilities supporting the comfort station and site lighting.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No.0002

New Vault Toilets – Bid Option #1

1. This item consists of work to compete demolition and removal of the two existing vault toilets and installation/construction of two new vault toilets in the same location. This item should also include a deduction for the improvements to the existing vault toilets which is captured in the Base Bid.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item No.0003

New Drinking Fountains – Bid Option #2

SACN - 244692 01 27 00 - 2

082714 CONTRACT LINE ITEMS

1. This item consists of work to compete demolition and removal of the five existing water drinking fountains and installation of five new accessible drinking fountains in locations as noted on the drawings. This item should also include a deduction for the installation and reuse of existing water fountains which is captured in the Base Bid.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item No.0004

Concrete Walkway (Osprey Shelter to Comfort Station) – Bid Option #3

1. This item consists of work to construct a 5-foot wide concrete walkway from the Osprey Shelter to the Comfort Station per the drawings.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item No.0005

Shade Structure – Bid Option #4

1. This item consists of work to construct a shade structure in the interpretive plaza.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

F. Contract Line Item No.0006

Outdoor Recreation Access Route – Bid Option #5

1. This item consists of work to construct a paved walkway to outdoor recreation access standards to access the lower portion of the existing boat launch from the interpretive plaza.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

G. Contract Line Item No.0007

Day Use Parking – West Side of Road – Bid Option #6

1. This item consists of work to construct an asphalt parking area adjacent to the day use road.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

H. Contract Line Item No.0008

Wayfinding/Orientation Elements – Bid Option #7

1. This item consists of fabrication and installation of wayfinding/orientation signage to be placed in distinct locations on the site. This includes fabrication of wayfinding/orientation panels, bases and installation at identified locations.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

SACN - 244692 01 27 00 - 3

082714 CONTRACT LINE ITEMS

I. Contract Line Item No.0009

Walkway Along West Side of Day Use Road – Bid Option #8

1. This item consists of work to construct a paved walkway along the west side of the day use road.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

J. Contract Line Item No.0010

Wayside Exhibits – Bid Option #9

1. This item consists of fabrication and installation of wayside exhibits in distinct locations at the site. This includes fabrication of the exhibit panels, bases and installation at identified locations.

2. Measurement for payment will be percent complete.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

SACN - 244692 01 31 00 - 1

PROJECT MANAGEMENT

091015 AND COORDINATION

SECTION 01 31 00 – PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction: An organization, office, or individual responsible for enforcing the requirements of a code or standard, or for approving equipment, materials, an installation, or a procedure.

B. Construction Permits – Contractor Provided: Permits that will be applied for and obtained by the contractor.

C. Government Furnished Permits: Permits that will be applied for and obtained by the government.

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

SACN - 244692 01 31 00 - 2

091015 AND COORDINATION

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor’s Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.4 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the

Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Pollution Prevention Plan (TPPP).

11. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

SACN - 244692 01 31 00 - 3

091015 AND COORDINATION

c. Information required from the Government to complete the permit application.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website or CMR provided.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor’s suggested resolution. If Contractor’s suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor’s signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint or CMR provided website as follows:

1. Enter the general information at the top of the form.

2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.

3. Enter the details of the question and attach related documents.

4. Select “Submit Form” at the bottom of the page.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.

CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

SACN - 244692 01 31 00 - 4

091015 AND COORDINATION

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor’s means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect’s actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO’s action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO’s action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT WEB SITE

A. Use the NPS/DSC SharePoint Project or CMR provided website for communication throughout the contract period. The NPS/DSC SharePoint Project or CMR provided website will be used for the following functions:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

16. Permits and addendums

B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website or CMR provided. Documents containing Personal Identifying Information (PII) (i.e.

certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.

C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm. Alternatively, a CMR provided website may be utilized to share communication and documentation with a similar registration process required.

D. All users will be required to have the following software packages:

http://www.nps.gov/dscw/precon_spproj.htm

SACN - 244692 01 31 00 - 5

091015 AND COORDINATION

1. Internet Explorer version 7 or later.

2. Adobe Acrobat Professional (Pro) version 9 or later

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Schedule of Values

9. Payments to Contractor.

10. Payroll reports.

11. Contract time.

12. Liquidated damages.

13. Contractor Performance Evaluation.

14. Display of Hotline posters.

15. Notice to proceed.

16. Correspondence procedures.

17. NPS/DSC SharePoint Project website.

18. Acceptance/rejection of work.

19. Progress meetings.

20. Submittal procedures.

21. Interim Accessibility Inspection Reports.

22. NPS Final Accessibility Inspection.

23. Environmental requirements.

24. Permit requirements.

25. As-constructed drawings/operation and maintenance (O&M) manuals.

26. Saturday, Sunday, holiday and night work.

27. Reference materials.

28. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

SACN - 244692 01 31 00 - 6

091015 AND COORDINATION

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer’s written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of agency(ies) with jurisdiction.

t. Testing and inspecting requirements.

u. Interim Accessibility Inspection Reports.

v. Installation procedures.

w. Coordination with other work.

x. Required performance results.

y. Protection of adjacent work.

z. Protection of construction and personnel.

SACN - 244692 01 31 00 - 7

091015 AND COORDINATION

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.8 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; familiarity with Environmental Management Systems (EMSs) such as ISO 14001; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan (WMP).

c. Implementation of the Stormwater Pollution Prevention Plan (SWPPP).

d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

e. Training for Contractor personnel in accordance with their position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Noise & Acoustics Management.

4. Temporary Storm Water Pollution Prevention.

a. Stormwater Pollution Prevention Plan

5. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Noise & Acoustics Management.

SACN - 244692 01 31 00 - 8

091015 AND COORDINATION

c. Temporary Storm Water Pollution Prevention.

1) Stormwater Pollution Prevention Plan

4. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.

5. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan and Stormwater Pollution Prevention Plan.

E. Environmental Coordination with Park

1. Schedule all vegetation removal, trimming, and grading of vegetated areas outside of the peak bird breeding season (February 1 – September 1) to the maximum extent practicable.

2. When project activities cannot occur outside the bird nesting season (February 1 – September 1), conduct surveys prior to scheduled activity to determine if active nests are present within the area of impact and buffer and nesting locations found during surveys.

3. Review compliance requirements with NPS prior to any site disturbance in the St. Croix River regarding the presence of freshwater mussels and other wildlife.

1.9 PERMITS

A. General:

1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore the Contractor will comply with the appropriate Federal, State and local laws.

B. Government Furnished Permits: During development of the project’s design the permits listed below were identified as necessary prior to any work in regulated aquatic areas. Copies of these permits should be kept on site during construction after issuance.