MORU_219680_RFI_Register_20190222.pdf
PDF 197 KB Posted
- Solicitation number
- 140P2019R0013
About this file
Questions and Answers - February 19th, 2019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_Amendment_2.pdf | ||
| MORU_219680_RFI_Register_20190219.1.xlsx | XLSX spreadsheet | |
| E09_PPT_Pre-Proposalr1.pdf | ||
| SF30.pdf | ||
| MORU_219680_Pre_Bid_Photo_Presentation.pdf | ||
| Prebid_Sign-in_Sheet.pdf | ||
| 4-B08_General_Decision_Bldg.pdf | ||
| 8-B08_PSP_VOL_II_ContractPriceSchedule.xls | XLS spreadsheet | |
| 9-B08_Solit_PSP_Vol_II_SBSubKCalc.xlsx | XLSX spreadsheet | |
| 3-B08_Drwgs.pdf | ||
| 2-B08_Vol_2_SPECS_Div_22_thru_33.pdf | ||
| 5-B08_General_Decision_Heavy-Hwy.pdf | ||
| 7-B08_PSP_VOL_II.pdf | ||
| 1-B08_Vol_1_SPECS_Div_01_thru_21.pdf | ||
| 0-B08_SF1442_Clauses.pdf | ||
| 6-B08_PSP_VOL_1.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REVISION
FINAL
RFI REC'D RETURN
1 2/8/2019 2/19/2019
2 2/8/2019 2/19/2019
3 2/7/2019 2/19/2019
4 2/7/2019 2/19/2019
5 2/13/2019
5 2/7/2019 2/7/2019
6 2/7/2019 2/7/2019
7 2/7/2019 2/7/2019
8 2/7/2018 2/7/2019
RFI REGISTER
The 8'-0" ceiling height in the restrooms is the current height as verified in field in January 2018. The height modification from the original is also recorded in a 1990 set of record drawings.
There is latex-modified thin-set mortar underneath the tile.
Please see 2.3 "Setting Materials" in section 21 96 80 for manufacturers and follow TCNA guidelines for an F115-03 thin-set installation.
Yes. Curries by Assa Abloy may also be considered an approved manufacturer for HM doors.
Proposal submission will be extended to account for shutdown period.
REQUEST RESPONSE
You have Ceco by Assa approved for hollow metal, can Ii also use Curries by Assa?
Can you please advise what hardware groups openings 115A & 124A belong to
Can you tell us if there is a mortar bed underneath the tile in rooms 114, 115, 124 and 125? If so, please clarify what installation will be required by TCNA (Tile Council of North America).
These doors are intended to have hardware set #2, but that set is incomplete. Please anticipate also four stainless steel hinges [basis of design Hager BB1191, 4.5 inch in US32D] and a mortise lock with a deadbolt and lever [basis of design Hager 3810 WTN in US32D] .
CONTRACT No.
Solicitation 140P2019R0013
National Park Service Denver Service Center 12795 West Alameda Parkway Lakewood, CO 80228
PMIS
MORU 219680
PROJECT TITLE
MORU Plaza Paver Replacement and Visitor Center Rehab
DATE
2/22/2019
On the original drawings from the original project, it had the finished ceiling height as 8’6” in the above rooms, and the new plans call for 8’, I just want to verify this.
If the government shuts down, how will it affect this solicitation
600 daysWhat is the duration of the project
Requesting clarification on the Steel Slat Benches (Ref Drawing C16) where it states that the Specification indicates the Model and Manufacturer of these custom benches. Ref Spec section 32 33 00 – Site Furnishings section below. We cannot find the Manufacturer or Model indicated in the specification. Please provide the name of the manufacturer and model so we can procure pricing for the proposal.
Like or equal: Northgate Bench, SKU 2ZT2086-BK (2/14/2019)
What is the extent of access for visitors?
Consult Div. 01 specifications for phasing and restrictions.
Phasing is flexible.
Will the background presentation be provided Yes.
RFI REC'D RETURN
RFI REGISTER
REQUEST RESPONSE
CONTRACT No.
Solicitation 140P2019R0013
National Park Service Denver Service Center 12795 West Alameda Parkway Lakewood, CO 80228
PMIS
MORU 219680
PROJECT TITLE
MORU Plaza Paver Replacement and Visitor Center Rehab
DATE
2/22/2019
9 2/7/2019 2/7/2019
10 2/7/2018 2/7/2019
11 2/7/2019 2/7/2019
12 2/7/2019 2/7/2019
13 2/7/2019 2/7/2019
14 2/7/2019 2/7/2019
15 2/14/2019 2/19/2019
16 2/14/2019 2/19/2019
17 2/14/2019 2/19/2019
No. This is full and open.
A hydration stabilizer will be considered for approval during the submittal process. Approval of adding a hydration stabilizer will be depending on outdoor temperature.
What is under the stairs?
Concrete structure located under stairs. Stairs and structure are separate
Service road located on Washington side.
NPS staff will be the ONLY individuals allowed to move the cabinets on wheels, due to contents inside. Yellow cabinets DO NOT move.
NPS requests 24 hr. notice to move cabinets out of the way of planned work activities.
How much notice is needed to give NPS to move cabinets in secure archival storage area?
Is the project a set aside for small business?
Limit to 10,000 lbs. Drawings provide further information.
What are the weight restrictions on the visitor center roof?
Yes, a 0.45 water / cement ratio would be considered for approval during the submittal process.
Due to the haul distance will a hydration stabilizer be approved for use to offset the haul time from the plant to the jobsite to effectively start the unload time when the truck arrives on the jobsite?
What construction access is available for the amphitheater?
Who will or who can move the cabinets in archival storage room?
A 0.40 w/c ratio specification will be a difficult mix to produce and haul long distance and achieve a 5-7” slump onsite. It will require more chemicals which in turn can make the mix more difficult to pump, place, and produce consistent air contents. Would a 0.45 w/c cement ratio be considered for approval as most municipalities and DOT agencies recognize for use in our area?
To achieve the design parameters, the specified rock/sand weights appear to considerably over yield which will affect the performance of the mix. Would batch weights provided be allowed to be respectively adjusted to not over/under yield?
Batch weights will be considered and approved for adjustment following submittal of the proposed mix design.
RFI REC'D RETURN
RFI REGISTER
REQUEST RESPONSE
CONTRACT No.
Solicitation 140P2019R0013
National Park Service Denver Service Center 12795 West Alameda Parkway Lakewood, CO 80228
PMIS
MORU 219680
PROJECT TITLE
MORU Plaza Paver Replacement and Visitor Center Rehab
DATE
2/22/2019
18 2/15/2019 2/22/2019
19 2/15/2019 2/22/2019
20 2/15/2019 2/22/2019
21 2/15/2019 2/22/2019
22 2/15/2019 2/22/2019
23 2/15/2019 2/19/2019
Do you have any performance data to provide for the heat exchanger?
Please clarify whether the Site Safety Manager role may be fulfilled by either the Site Superintendent or the Quality Control Manager as long as the individual’s qualifications meet the requirements of both roles.
Please clarify whether the Project Manager must be on site at all times during work activities.
SSHO and Superintendent shall be different people and be available on the site whenever construction is in progress.
IEI - Yes, see attached PDF of HPC-1 performance data based on project conditions.
Far 52.236-6 Superintendence by the Contractor requires "At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor."
The schedule calls for the physical dimension to be 40”x66”x6”. If you scale off of the plans, the OA & EA ducts are each this approximate dimension. The section on sheet M5.0, shows the heat exchanger covering both the OA & EA ducts. Will we need to provide (2) heat exchangers? Provide a larger heat exchanger than the dimension scheduled? Please let me know.
What is your intent for mounting the heat exchanger?
IEI - Only one (1) heat exchanger needed. Existing connection of OSA and relief air duct to unit inlet and outlet to be demoed and reconfigured as show on section 3/M5.1.
Section view 1/M.5.0 provided to show relative location of ERWs and HPC to their respective AHU; refer to schedules for dimensions and M5.1 for detailed configuration of ERWs and HPC to AHUs.
Please provide sizing for the (4) motorized bypass dampers called out on sheet M2.2
IEI - Motorized dampers to match associated duct size and meet performance specification 23 33 00 part 2.7.
1- Mezzanine Mech Rm: Motorized dampers (2) to match 14x8 ductwork serving ERV-2 (OSA & EA Duct). Refer to Section 2/M5.0.
2- Mezzanine Mech Corridor: Motorized dampers (2) to match 10x6 ductwork serving ERV-1 (OSA & EA duct).
Refer to Sheet M2.2.
IEI - Drawings are diagrammatic in nature to reflect the basis of design. Contractors responsibility to provide miscellaneous supports/metals required to install equipment; refer to section 23 00 00 Part 1.5 & Part 3.10. Framing to be reviewed by CO as a deferred submittal. HPC-1 to also follow any manufacturer installation/mounting instructions.
RFI REC'D RETURN
RFI REGISTER
REQUEST RESPONSE
CONTRACT No.
Solicitation 140P2019R0013
National Park Service Denver Service Center 12795 West Alameda Parkway Lakewood, CO 80228
PMIS
MORU 219680
PROJECT TITLE
MORU Plaza Paver Replacement and Visitor Center Rehab
DATE
2/22/2019
24 2/15/2019 2/19/2019
25 2/15/2019 2/19/2019
26 2/15/2019 2/19/2019
27 2/15/2019 2/22/2019
28 2/15/2019 2/22/2019
29 2/15/2019 2/22/2019
30 2/15/2019 2/22/2019
31 2/15/2019 2/22/2019
32 2/15/2019 2/22/2019
33 2/15/2019 2/22/2019
34 2/15/2019 2/22/2019
35 2/15/2019 2/22/2019
Please confirm existing elevators shafts’ wall embeds can be used as attachment points for the new rail brackets without any structural modifications
No. Rail Brackets Shall Be Located As Designed Per Otis Gen 2 Layout.
Please confirm on-center spacing of the existing elevators shafts’ wall embeds
NO Rail Brackets shall Be Located As Designed Per Otis Gen 2 Layouts
The door schedule is correct. Set 2 in the hardware schedule is intended for Doors 115A and 124A but is incomplete.
Please see response to #2 above.
Please confirm Washington Elevator shaft construction is reinforced concrete per S2.0
Information included in the bid documents.
Please confirm Lincoln Elevator shaft construction is reinforced concrete per S2.0
Information included in the bid documents.
Please clarify whether you require only one Flash Drive containing both volumes or if one Flash Drive is required for each Volume (making two Flash Drives total to be submitted).
Provide one flash drive.
Please provide the sign-in sheet, presentation slides, and photos from the February 7 th site visit
Will provide with amendment and RFI responses
Please confirm that Washington Elevator is a three-stop elevator and Lincoln Elevator is two stop.
Yes, Washington is a three-stop elevator and Lincoln is a two stop elevator.
Information included in the bid documents.
Door schedule and hardware schedule do not match, which is correct?
Dimensions included in the bid documents.
Please provide Washington Elevator shaft dimensions to confirm the desired OTIS GEN2 MRE can be installed in the existing shaft
Many of our government projects have already been assessed through the CPARS system or existing Past Performance Questionnaires. May we submit these with our proposal in lieu of requesting a new Past Performance Questionnaires?
Please confirm that the Washington & Lincoln elevators pits are at least four feet deep
Please provide Lincoln Elevator shaft dimensions to confirm the desired OTIS GEN2 MRE can be installed in the existing shaft
Provide past performance questionnaire.
Yes, Washington and Lincoln elevators are at least four-feet depth.
RFI REC'D RETURN
RFI REGISTER
REQUEST RESPONSE
CONTRACT No.
Solicitation 140P2019R0013
National Park Service Denver Service Center 12795 West Alameda Parkway Lakewood, CO 80228
PMIS
MORU 219680
PROJECT TITLE
MORU Plaza Paver Replacement and Visitor Center Rehab
DATE
2/22/2019
36 2/15/2019 2/22/2019
37 2/15/2019 2/22/2019
38 2/19/2019 2/22/2019
39 2/19/2019 2/22/2019
40 2/19/2019 2/22/2019
I would like to propose Josam as an equal to JR Smith on the Trench Drains (TD-1)
No exception taken to providing Josam as an equal to JR Smith for trench drain TD-1.
I am curious on the TD-1 Trench Drains shown on P2.2 -what are the lengths we are looking for here? On sheet P2.1 it appears we have 13 separate 6' long TD's; yet on P2.2 it appears we have one radiused continuous TD.
However, I suspect they are actually sections which appear to be 12' long each. Please confirm.
SHEET P2.1 - The only trench drains on P2.1 are provided by the civil engineer. These are shown at the bottom of the exterior stair landing. The 6 foot sections you may be regarding to are trench drain units provided by the HVAC installer. Plumbing contractor is installing the condensate lines from the units to the waste line. See detail 6/P4.2 and 9/P4.2.
SHEET P2.2 - The trench drains on P2.2 are drawn from column to column. Most trench drains are approximately 11 foot 9 inches in length with the (2) end trenches, on each side, varying in length. These measurements should be field verified prior to ordering sections.
D. Contract Line Item No. 4, Bid Option 3 – New Finishes in Staff Area of Visitor Center, Lump Sum
This item includes replacing finishes to include flooring, ceilings and wall finishes in the staff area (rooms 105 through 113) of the Visitor Center. It covers finishes demolition and replacement beyond that which will be affected by Mechanical work, which is included in the main scope of work. Item includes vapor-retarding protections for areas to be humidified. Is the electrical work in this are part of this option or the base bid?
For the type ‘SE’ light fixture, please provide the height.
Overall height of column luminaire, Type 'SE', to be 8 feet.
The electrical scope for Safety 106 and Restroom 107 as shown on Drawings E1.1 and E2.1 should be included as part of Bid Alt #3. Bid Alt #3 ceiling revision shown on Drawings AD1.2 and A2.0. Replacement of existing flooring should not effect electrical scope.
The electrical scope for the West Restrooms as shown on Drawings E1.1, E1.3, E2.1, and E3.1 should be included as part of Bid Alt #1.
Contract Line Item No. 2, Bid Option 1 – Washington Side Visitor Center Restroom Rehabilitation, Lump Sum This item consists of rehabilitating the restroom on the Washington side of the Visitor Center referred to on the drawings as “West Restrooms.” Is the electrical work in this are part of this option or the base bid?
RFI REC'D RETURN
RFI REGISTER
REQUEST RESPONSE
CONTRACT No.
Solicitation 140P2019R0013
National Park Service Denver Service Center 12795 West Alameda Parkway Lakewood, CO 80228
PMIS
MORU 219680
PROJECT TITLE
MORU Plaza Paver Replacement and Visitor Center Rehab
DATE
2/22/2019
41 2/19/2019 2/22/2019
42 2/19/2019 2/22/2019
43 2/19/2019 2/19/2019
We are a Lithonia Lighting rep and have been asked to bid a lighting package on the Rushmore Plaza Visitor Center Rehabilitation. Our products are specified on much of the project, but I would be interested in requesting substitution on a few light fixtures that we are not specified on. Will you be accepting substitution requests for this project, and if so, do I send to you?
Variance requests will be entertained during the submittal process.
No exception taken to Josam Pro-Trench Drain in place of the JR Smith product specified in the contract documents.
I see we are asking for a "polymer concrete pre-cast" product. Our experience has NOT been good with this type of product. Deliveries consist of cracked & broken sections due to it's very brittle nature. Once installed, we see cracking & deformation due to the product's poor thermal expansion properties. We have found that the Josam glass-fiber reinforced polyester product has extremely high strength & dimensional stability. It is 1.5 times stronger than polymer concrete & it's thermal expansion is 40% less. I've attached a Josam Pro-Trench Drain Catalog for your review.
Please provide a summary of what days or periods are considered “Off Peak Visitation Days and Hours” as indicated in the RFP. This is important for our development of the phasing and schedules.
Section 01 11 00 1.4 B defines off-peak visitation days as between September 15th and May 16th.