8-B08_PSP_VOL_II_ContractPriceSchedule.xls
XLS spreadsheet 81 KB Posted
- Solicitation number
- 140P2019R0013
About this file
Fillable form Contract Price Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_Amendment_2.pdf | ||
| MORU_219680_RFI_Register_20190222.pdf | ||
| MORU_219680_RFI_Register_20190219.1.xlsx | XLSX spreadsheet | |
| E09_PPT_Pre-Proposalr1.pdf | ||
| SF30.pdf | ||
| MORU_219680_Pre_Bid_Photo_Presentation.pdf | ||
| Prebid_Sign-in_Sheet.pdf | ||
| 4-B08_General_Decision_Bldg.pdf | ||
| 9-B08_Solit_PSP_Vol_II_SBSubKCalc.xlsx | XLSX spreadsheet | |
| 3-B08_Drwgs.pdf | ||
| 2-B08_Vol_2_SPECS_Div_22_thru_33.pdf | ||
| 5-B08_General_Decision_Heavy-Hwy.pdf | ||
| 7-B08_PSP_VOL_II.pdf | ||
| 1-B08_Vol_1_SPECS_Div_01_thru_21.pdf | ||
| 0-B08_SF1442_Clauses.pdf | ||
| 6-B08_PSP_VOL_1.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| CONTRACT PRICE SCHEDULE | |||||
| SOLICITATION NUMBER: 140P2019R0013 | |||||
| PARK - PMIS: MORU - 219680 | |||||
| DEVELOPED AREA: Mount Rushmore National Memorial | |||||
| PROJECT TITLE: Plaza Paver Replacement and Visitor Center Rehabilitation | |||||
| Notice: Refer to Section H, Special Clause 1, Option for Additional Services—Separately Priced Line Items, offerors are required to submit, at minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. At the option of the Government, the period for exercise of options at the proposed prices shall extend 90 calendar days from the date of award. | |||||
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Base Bid (Plaza Paver Replacement and Visitor Center Improvements) | 1 | Lump Sum | $0.00 | $0.00 |
| 2 | Bid Option 1 – Washington Side Visitor Center Restroom Rehabilitation | 1 | Lump Sum | $0.00 | $0.00 |
| 3 | Bid Option 2 – Partial Grandview Terrace Colonnade Modifications | 1 | Lump Sum | $0.00 | $0.00 |
| 4 | Bid Option 3 – New Finishes in Staff Area of Visitor Center | 1 | Lump Sum | $0.00 | $0.00 |
| 5 | Bid Option 4 – Parking Garage Mini Plaza Replacement | 1 | Lump Sum | $0.00 | $0.00 |
| 6 | Bid Option 5 – Visitor Center Entrance Plaza | 1 | Lump Sum | $0.00 | $0.00 |
| TOTAL BASE PRICE (Contract Line Item Number 1) -------------------------------------------------------------------- | $0.00 | ||||
| TOTAL BID OPTION PRICEs (Contract Line Item Numbers 2 through 6) ----------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE – BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 6) --------- | $0.00 | ||||
| All measurement and payment information is included in the project specifications, Section 012700. |
&RPARK - PMIS
CPS - &P
Design-Bid-Build Sample
| CONTRACT PRICE SCHEDULE | |||||
| SOLICITATION NUMBER: N2011080811 | |||||
| PARK - PMIS: YELL 012345 | |||||
| DEVELOPED AREA: Old Faithful | |||||
| PROJECT TITLE: Johnstonian Visitors Center | |||||
| Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government. | |||||
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identify why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. | |||||
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Visitors Center | 1 | Lump Sum | $0.00 | |
| 2 | Water Line | 400 | L.F. | - 0 | |
| 3 | Sanitary Sewer line | 200 | L.F. | - 0 | |
| 4 | Rock Excavation | 150 | C.Y. | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 4) ------------------------------------ | $0.00 | ||||
| 5 | OPTION A, Geothermal Wells | 1 | Lump Sum | $ - 0 | |
| 6 | OPTION B, Photovoltaic system | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 5 and 6) ------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 6) ------------- | $0.00 | ||||
| All measurement and payment information is included in the project specifications, Section 012700. |
&RYELL - 012345
CPS - &P
Design-Build Sample
| CONTRACT PRICE SCHEDULE | |||||
| SOLICITATION NUMBER: N2011080811 | |||||
| PARK - PMIS: YOSE 012345 | |||||
| DEVELOPED AREA: Yosemite Valley | |||||
| PROJECT TITLE: Design and Build a New Structure | |||||
| Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government. | |||||
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. | |||||
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Design | 1 | Lump Sum | $0.00 | |
| 2 | Construction | 1 | Lump Sum | $0.00 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 2) --------------------------------------------------------- | $0.00 | ||||
| 3 | OPTION A, Photovoltaic System | 1 | Lump Sum | $0.00 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3 ) ----------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 3) ------------ | $0.00 |
&RYOSE - 012345