Clean Agent or CO2 System Page 1 of 4 Revised 12/16/15
National Park Service / AKRO
Inspection and Test Report (complete a separate form for each system)
CLEAN AGENT OR CO2 SYSTEM – CLEAN AGENT CO2
Park Alpha Code: ______________________ FMSS Location No.:___________________
Location Description: ______________________
Date of Test:_________________________
Time:_________________
System Make: ______________________ System Model: _____________________
No of Cylinders ______________________ No. of Nozzles _____________________
Control Panel Make ______________________ Panel Model _____________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attach itemized sheet
REPAIRS: All deficiencies have been corrected N/A Yes No
This certifies that the fire and life safety system has been inspected and tested for functional operation in accordance with applicable NFPA standards, and has been properly tagged and/or labeled. Any discrepancies found are noted in this report with code references for corrective action by the Owner/Responsible Person.
Technician Name (printed): ______________________ Company: ______________________________
Signature: ___________________________________ Phone #: _______________________________
State Certification No.: _________________________
National/NICET No.: ___________________________
ENCLOSURE INTEGRITY
1. After visual inspection, there are no unsealed penetrations in walls, ceiling, and floors that would affect enclosure integrity.
Yes No
2. Doors in the protected enclosure are self-closing and provided with sweeps/gaskets Yes No
3. HVAC penetrations in the protected enclosure that could affect agent hold time are provided with low-leakage dampers.
Yes No
NOZZLES, PIPING, AND HOSE
4. All nozzles, piping, and brackets are properly placed and are secured. Yes No
5. All hose was visually inspected and does not have visual defects. Yes No
6. All hose five years old and older has been tested in 5-year intervals in accordance with NFPA 2001 Section 7.3.2 Date for Next Hose Test:
CYLINDERS AND EXTINGUISHING AGENT
7. The quantity loss is <5% and the pressure loss is <10% in each cylinder from the required quantity and pressure of the extinguishing agent.
Yes No
8. There is an up-to-date log containing a record of semi-annual checks for the agent quantity and pressure on each cylinder
Yes No
9. All cylinders with an unacceptable quantity loss were refilled or replaced.
N/A Yes No
10. All cylinders are tested according to NFPA 2001 7.2.1 and 7.2.2 at the proper intervals. Date for next cylinder test________________
Clean Agent or CO2 System Page 2 of 4 Revised 12/16/15
DETECTION AND CONTROL
11. All detection/initiating devices respond properly when tested.
No. of Units Tested Manual Stations ________________ Smoke Detectors ________________ Heat Detectors ________________ Air Sampling Detectors ________________ Tamper Switches ________________ Other ________________
N/A Yes No
12. All alarm functions take place upon receipt of a signal from the detection devices.
N/A Yes No
13. All alerting / notification devices work properly.
No. of Units Tested Pre Discharge Devices ________________ Post Discharge Devices ________________
14. All supervised circuits send the proper signals to the control panel. N/A Yes No
15. All manual release stations are readily accessible, accurately identified, and properly protected to prevent damage.
RELEASE DEVICES
16. The automatic release device(s) work properly, including pre-discharge time delays.
17. All manual release stations used to release agents work properly. N/A Yes No
ABORT DEVICES
18. The manual abort switch is a dead-man type switch and functions properly.
AUXILIARY FUNCTIONS
19. All auxiliary functions such as alarm-sounding or displaying devices, remote annunciators, air-handling shutdown, damper operation, and power shutdown operate properly in accordance with system requirements and design specifications.
N/A Yes No
20. The alarms can be silenced, when allowed, without affecting other system functions.
SYSTEM MONITORING
21. The suppression control panel sends the proper signals to the building FACP.
N/A Yes No
22. The suppression control panel operates on standby power N/A Yes No
23. Signals were received at the monitoring company. N/A Yes No
TRAINING
24. All personnel working in enclosures protected by a clean agent system have received up-to-date training regarding clean agent safety issues.
Clean Agent or CO2 System Page 3 of 4 Revised 12/16/15
Type of Extinguishing Agent ___________________
Agent Cylinders #1 #2 #3 #4 #5
Serial No. __________ __________ __________ __________ __________
PSI __________ __________ __________ __________ __________
Gross Weight __________ __________ __________ __________ __________
Agent Weight __________ __________ __________ __________ __________
Tare Weight __________ __________ __________ __________ __________
Liquid Level __________ __________ __________ __________ __________
Hydro Date __________ __________ __________ __________ __________
Clean Agent or CO2 System Page 4 of 4 Revised 12/16/15
Deficiencies
Resolved
Location:
Deficiency:
Recommended Resolution:
NFPA reference:
Dry Chemical Suppression System Page 1 of 3 Revised 12/16/15
DRY CHEMICAL SUPPRESSION SYSTEM
No of Agent Cylinders ______________________ No. of Nozzles _____________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attach
This certifies that the fire and life safety system has been inspected and tested for functional operation in accordance with NFPA 17, and has been properly tagged and/or labeled. Any discrepancies found are noted in this report with code references for corrective action by the Owner/Responsible Person.
Technician Name (printed): ______________________ Company: ______________________________
Signature: ___________________________________ Phone #: _______________________________
State Certification No.: _________________________ National/NICET No.: ______________________
COVERAGE , NOZZLES, AND PIPING
1. The area/hazard to be protected has the required number and type of nozzles to provide adequate fire protection.
Yes No
2. All nozzles are properly positioned. Yes No
3. Piping is installed and supported adequately with no evidence of damage Yes No
4. Fusible link cable conduits are immobilized with proper hangers and brackets. Yes No
SYSTEM CONTROLS
5. All system controls and components are accessible and free from obstructions. Yes No
6. The system is operational from the test link (last fusible link) Yes No
7. All fusible links have been replaced and the year of manufacture and date of installation is marked on the system inspection tag.
Yes No
8. Manual release station(s) are readily accessible, located 42” – 48” above the floor, and identify the hazard they protect
Yes No
9. Manual release stations are configured correctly and operational. Yes No
10. The operation of the fusible link line is not impaired by debris or foreign materials. Yes No
11. Where the system protects a hazard with flowing flammable or combustible fluids or gases, an automatic means to shutoff the fuel upon operation of the extinguishing system is provided.
N/A Yes No
12. Equipment and/or fuel shutoff interlock(s) were tested and are operational N/A Yes No
13. Warning signs are installed where there is a possibility that personnel could be exposed to a dry chemical discharge.
Dry Chemical Suppression System Page 2 of 3 Revised 12/16/15
14. The extinguishing agent in the cylinders conforms to the manufacturer’s requirements for this system.
Yes No
15. Storage cylinders are fastened securely to their mounting brackets. Yes No
16. The cylinders are filled with the correct volume of extinguishing agent.
Required volume ________lbs. or __________gals.
Yes No
17. The cylinder gauge is in the operational range. Yes No
18. The CO2 or Nitrogen cylinder is fully charged.
Design weight _____ lb. Actual Weight _____lb.
N/A Yes No
19. The hydrostatic testing of the agent cylinder(s) is up-to-date.
Date for next hydrostatic test ______________________
MONITORING
20. The system is connected to the fire alarm system. (if an alarm panel exists) N/A Yes No
21. The fire alarm panel receives the proper signals upon suppression system activation.
22. The alarm monitoring company received the alarm signal. N/A Yes No
Dry Chemical Suppression System Page 3 of 3 Revised 12/16/15
NFPA 17 reference:
Fire Alarm Page 1 of 3 Revised 12/16/15
FIRE ALARM SYSTEM – ADDRESSABLE CONVENTIONAL
Off Site Monitoring? Yes No Monitoring Company or Location
Name ________________________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attach
This certifies that the fire and life safety system has been inspected and tested for functional operation in accordance with the current edition of NFPA 72, and has been properly tagged and/or labeled. Any discrepancies found are noted in this report with code references for corrective action by the Owner/Responsible Person.
Technician Name (printed): ______________________ Company: ______________________________
Signature: ___________________________________ Phone #: _______________________________
GENERAL
1. The key to the panel is available at the FACP. N/A Yes No
2. The operating instructions are available at the FACP. Yes No
3. Materials and equipment needed to restore pull stations are available at the main panel, e.g. glass rods, and plates; keys and allen wrenches, etc. N/A Yes No
FIRE ALARM CONTROL PANEL
4. All signals on the FACP operate on AC power. Yes No
5. All signals on the FACP operate on battery power. Yes No
6. All signals on the FACP operate on emergency generator/standby power N/A Yes No
7. A trouble signal activates upon loss of power, ground fault, and open circuit. Yes No
8. Circuit breaker location is identified at the FACP and all booster panels Yes No
INITIATING DEVICES AND NOTIFICATION APPLIANCES
9. All initiating and annunciating devices tested operate properly on AC power. Yes No
10. All initiating and annunciating devices tested operate properly on generator/standby power. Yes No
11. All initiating and annunciating devices tested operate properly on battery power. Yes No
12. 100% of the INITIATING DEVICES were tested per NFPA 72.
No. of Units Tested Manual Pull Stations ________________ Smoke Detectors ________________ Heat Detectors ________________ Sprinkler Waterflow ________________
Fire Alarm Page 2 of 3 Revised 12/16/15
Dry Sprinkler High/Low Air ________________ Duct Smoke Detectors ________________ Tamper Switches ________________ Suppression Systems ________________ Other ________________
13. 100% of the NOTIFICATION APPLIANCES were tested per NFPA 72
No. of Units Tested Horns ________________ Horn/Strobes ________________ Speakers ________________ Speaker / Strobes ________________ Bells (interior) ________________ Exterior Horns/Bells ________________
14. The audible alarm appliances tested operate at the levels designed by the manufacturer. Yes No
15. The audible appliances tested in residential areas generate a minimum of 70 dBA in sleeping areas.
16. The visual alarm appliances tested operate as designed. Yes No
BATTERIES
17. The batteries are rated for: ____ hours standby and ____ minutes alarm
18. Battery voltage (no load) ________ volts
19. Battery voltage (full load) ________ volts (signals operating)
20. Charge circuit voltage ________ volts
INTERFACE DEVICES
The FACP received signals from the following Interface devices: Tested by: Simulation Operation
21. Emergency Generator(s) N/A Yes No
22. Sprinkler Flow Switch(es) N/A Yes No
23. Supervisory Switch(es) N/A Yes No
24. Kitchen Hood Suppression System(s) N/A Yes No
25. Spray Booth Suppression System(s) N/A Yes No
26. Clean Agent System(s) N/A Yes No
27. Fire Pump(s) N/A Yes No
28. Other - N/A Yes No
OTHER EQUIPMENT CONTROLLED BY FACP
The following Fire Safety Functions responded to signals from the FACP. Tested by Simulation Operation
29. Fan controls N/A Yes No
30. Smoke Dampers N/A Yes No
31. Elevator Recall N/A Yes No
32. Elevator Shunt Trip N/A Yes No
33. Door hold release N/A Yes No
34. Fire Pump(s) N/A Yes No
35. Remote Annunciator Panels N/A Yes No
36. Other - N/A Yes No
37. Signals were received at the monitoring company or approved location. N/A Yes No
Fire Alarm Page 3 of 3 Revised 12/16/15
NFPA 72 reference:
Fire Pump System Page 1 of 3 Revised 12/16/15
FIRE PUMP SYSTEM – RESIDENTIAL PUMP COMMERCIAL PUMP
Pump Make: ______________________ Pump Model / SN: _____________________________
Controller Make ______________________ Controller Model / SN _____________________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attach
This certifies that the fire and life safety system has been inspected and tested for functional operation in accordance with applicable NFPA 20 and NFPA 25 standards, and has been properly tagged and/or labeled. Any discrepancies found are noted in this report with code references for corrective action by the Owner/Responsible Person.
Technician Name (printed): ______________________ Company: ______________________________
Signature: ___________________________________ Phone #: _______________________________
WATER STORAGE TANK
1. Water level is within normal range Yes No
2. Heating system is functional N/A Yes No
3. Exterior inspection of tank structure, supports, vents, and outlets, shows no evidence of accelerated corrosion or damage.
Yes No
4. Interior inspection was performed and shows no evidence accelerated corrosion, pitting, debris, or biological growth. (required at 5 year intervals)
N/A Yes No
5. Supply valve to fire pump is open Yes No
6. Automatic fill piping valves are open and operational N/A Yes No
ELECTRIC DRIVEN PUMP
7. The pump was started automatically by inducing a drop in pressure Yes No
8. Pressure readings during a no-flow (churn) condition.
Suction PSI: ______ Discharge PSI: _______
Yes No
9. Adjust pump packing glands as necessary for slight discharge Yes No
10. The pump casing relief valve operates properly Yes No
11. Check packing boxes, bearing, or pump casing for overheating Yes No
12. The electric pump ran properly for a minimum 10 minutes. Yes No
Fire Pump System Page 2 of 3 Revised 12/16/15
DIESEL DRIVEN PUMP
13. The pump was started automatically by inducing a drop in pressure Yes No
14. Pressure readings during a no-flow (churn) condition.
Suction PSI: ______ Discharge PSI: _______
Yes No
15. Adjust pump packing glands as necessary for slight discharge Yes No
16. The pump casing relief valve operates properly Yes No
17. Check packing boxes, bearing, or pump casing for overheating Yes No
18. Fuel level is at least 2/3 full. Yes No
19. Oil level is within acceptable range. Yes No
20. Batteries voltage reading are within acceptable range Yes No
21. The fuel filter/strainer has been serviced. Yes No
22. The diesel pump ran properly for a minimum 30 minutes. Yes No
PUMP CONTROLLERS
23. A pump controller regulates a commercial fire pump and is UL listed and operates per NFPA 20
N/A Yes No
24. A pump controller regulates a jockey pump and operates as required by
NFPA 20
N/A Yes No
25. A pump controller regulates a residential-type pump and operates as required by NFPA 20
FLOW TEST - RATED CAPACITY (GPM) ________ RATED SPEED (RPM) ________ RATED PRESSURE (PSI) _________
26. An annual flow test was performed per NFPA 20 at minimum, rated, and peak flows through approved test devices
N/A Yes No
27. The pump runs smoothly without unusual noise or vibration throughout the test. Yes No
28. The gauges passed a 5-year pressure gauge comparison test with a calibrated gauge.
Date for next test:______________
Yes No
29. Defective gauges have been replaced or recalibrated. N/A Yes No
30. The pump performs at its rated capacity and at 150% of its rated capacity (or the maximum capacity the water supply will accommodate)
Yes No
31. Flow readings measured:
Churn (no flow): ______ gpm Rated Capacity: _____ gpm 150% Rated Capacity: _____ gpm
32. Pressure readings - Discharge Gauge Churn (no flow): _______ psi Rated Capacity: _____ psi 150% Rated Capacity: _____ psi
33. Pressure readings – Suction Gauge:
Churn (no flow): _______ psi Rated Capacity: _____ psi 150% Rated Capacity: _____ psi
34. Flow Test device used: Hoses and Pitot Tube FM flowmeter Diffuser/Hosemonster
TRANSFER SWITCH
35. A simulated power failure during peak flow automatically activated the transfer switch within 10 seconds.
N/A Yes No
36. After the automatic connection was made to an alternate power source;
peak flow was redelivered within 30 seconds.
N/A Yes No
37. The manual emergency transfer equipment operated properly during peak flow and peak flow was redelivered within 30 seconds.
SYSTEM MONITORING
38. The pump controller panel sends the proper signals to the building
FACP.
N/A Yes No
39. The suppression control panel operates on standby power N/A Yes No
40. Signals were received at the monitoring company. N/A Yes No
Fire Pump System Page 3 of 3 Revised 12/16/15
NFPA 20 or NFPA 25 reference:
Fire Sprinklers Page 1 of 4 Revised 1/14/16
FIRE SPRINKLER SYSTEM – DRY PIPE WET PIPE PREACTION RESIDENTIAL
Riser Valve Make: ______________________ Valve Model: _____________________ Size: ____________________ Serial No: _____________________
Backflow Make: ______________________ Backflow Model: _____________________ Size: ____________________ Serial No: _____________________
Off Site Monitoring? Yes No Monitoring Company or Location
Name ________________________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attach
This certifies that the fire and life safety system has been inspected and tested for functional operation in accordance with the current edition of NFPA 25 and NFPA 13, and has been properly tagged and/or labeled. Any discrepancies found are noted in this report with code references for corrective action by the Owner/Responsible Person.
Technician Name (printed): ______________________ Company: ______________________________
Signature: ___________________________________ Phone #: _______________________________
GENERAL
1. Sprinkler coverage was inspected and is adequate Yes No
2. Sprinkler heads are not blocked or obstructed Yes No
3. Piping is adequately installed with no bent or visibly damaged piping Yes No
4. Hangars and bracing components are not missing or damaged Yes No
5. A backflow preventer is provided and is accessible for maintenance N/A Yes No
6. Sprinkler heads are provided 18” min. clearance above top of storage N/A Yes No
7. Hydraulic design placard is installed and visible on riser N/A Yes No
SPRINKLER HEADS
8. Number of Sprinkler Heads: <20 >20 but < 100 >100
9. All accessible sprinkler heads have been visually inspected and are free of corrosion, paint, obstructions and/or physical damage. (If “no”, list the location of any defective heads in the “Deficiencies” section.)
Yes No
10. Standard Response sprinkler heads are less than 50 years old and do not require sample testing or replacement.
N/A Yes No
11. Fast Response sprinkler heads (quick response and residential) are less than 20 years old and do not require sample testing or replacement.
Fire Sprinklers Page 2 of 4 Revised 1/14/16
12. Dry type sprinkler heads are less than 10 years old and do not require sample testing or replacement
N/A Yes No
13. The proper number of spare sprinkler heads is available, with the proper wrenches for each, at the riser or another designated location.
FLOW TESTS
14. The system main drain is the proper size and discharges to the exterior of the building.
Size of drain _______ Required size ________
Yes No
15. A Main Drain flow test was performed:
Static pressure ____ psi Flow pressure ____ psi Return to static pressure ____min/sec
16. Flow from the inspector’s test valve activates the system alarms within 60 seconds. Yes No
ALARMS AND SUPERVISORY DEVICES
17. All supervisory and alarm devices [i.e. bell(s), flow switches, high/low air switches, valve tamper switches] function properly.
18. A water motor gong/bell is provided on the exterior of the building N/A Yes No
VALVES
19. All system supply and control valves are secured or supervised in the open position. Yes No
20. All supply valves have been lubricated (OS&Y valves) N/A Yes No
GAUGES
21. The maintenance on system gauges is up-to-date. Every 5 years, installed gauges shall be checked against (1) calibrated gauge to determine accuracy. If not within 3% of the calibrated gauge it should be replaced or recalibrated.
Due date for the next comparison test: ____________
OBSTRUCTION INVESTIGATION
22. A 5-year obstruction investigation was performed per NFPA 25.
Date for next obstruction investigation _____________
FIRE DEPARTMENT CONNECTIONS
23. The Fire Department Connection(s) (FDC) is clear of bushes, guards, or other debris and is visible from the fire access road
N/A Yes No
24. FDC inlets have protective caps or covers. (Note: If missing, the pipe shall be visually inspected for debris)
25. FDC inlets have at least 12” clearance for operating wrenches. N/A Yes No
ALARM MONITORING
26. All signals were received by the fire alarm system and the monitoring company.
DRY PIPE SYSTEM
27. The dry pipe valve was trip tested per NFPA 25. System tripped at _______ psi.
N/A Yes No
28. Water was discharged from the inspector’s test connection within 60 seconds of opening the test valve. Water delivery was _______ seconds.
N/A Yes No
29. Air compressor refills system in 30 minutes or less. N/A Yes No
30. The system’s low points were drained and the system was restored to service.
31. A quick opening device (QOD) is used (accelerator or exhauster) N/A Yes No
PREACTION SYSTEM
32. Heat actuation devices were functionally tested. N/A Yes No
Fire Sprinklers Page 3 of 4 Revised 1/14/16
ANTIFREEZE
33. Antifreeze solution has been inspected and checked N/A Yes No
34. Premixed antifreeze solution is used N/A Yes No
PRESSURIZED WATER STORAGE TANK
35. Water level is within the normal range Yes No
36. Heating system is functional N/A Yes No
37. Exterior inspection of tank structure, supports, vents, and outlets, shows no evidence of accelerated corrosion or damage.
Yes No
38. Interior inspection was performed and shows no evidence accelerated corrosion, pitting, debris, or biological growth. (required at 3 year intervals)
N/A Yes No
39. All supply valves are open Yes No
40. Air or nitrogen pressure and quantity is adequate N/A Yes No
RECALLS
41. The technician did not find recalled devices or equipment during the visual inspection.
Fire Sprinklers Page 4 of 4 Revised 1/14/16
NFPA 25 or NFPA 13 reference:
Kitchen Suppression System Page 1 of 3 Revised 12/21/2015
KITCHEN SUPPRESSION SYSTEM – DRY CHEMICAL WET CHEMICAL
No of Agent Cylinders ______________________ No. Appliance Nozzles _____________________
No. Plenum Nozzles: ______________________ No. of Duct Nozzles _____________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attach
This certifies that the fire and life safety system has been inspected and tested for functional operation in accordance with NFPA 96, and has been properly tagged and/or labeled. Any discrepancies found are noted in this report with code references for corrective action by the Owner/Responsible Person.
Technician Name (printed): ______________________ Company: ______________________________
Signature: ___________________________________ Phone #: _______________________________
APPLIANCE COVERAGE , NOZZLES, AND PIPING
1. All cooking appliances that can produce grease laden vapors are completely under the range hood.
Yes No
2. All cooking appliances have the required number and type of nozzles to provide adequate fire protection.
Yes No
3. All nozzles are properly positioned. Yes No
4. Nozzle protective covers are in place. Yes No
5. Multiple hoods installed end to end, back to back, or sharing common ductwork are configured as a single hazard area with simultaneous operation.
Yes No
6. All piping and releasing cable conduit are immobilized with proper hangers and brackets. Yes No
7. The manual (remote) pull station is located 10 - 20 feet from the protected appliances in the path of egress and 42” – 48” above the floor.
SYSTEM CONTROLS
8. All system controls and components are accessible and free from obstructions. Yes No
9. The system is operational from the test link (last fusible link) Yes No
10. All fusible links have been replaced and the year of manufacture and date of installation is marked on the system inspection tag.
Kitchen Suppression System Page 2 of 3 Revised 12/21/2015
11. The manual (remote) pull is configured correctly and is operational. Yes No
12. The operation of the fusible link line is not impaired by grease. Yes No
13. The micro switch that controls shutoff of gas and/or electrical power to the appliances functions properly.
Yes No
14. The gas shuts down upon system activation. N/A Yes No
15. The appliance electrical shutdown device functions properly. N/A Yes No
16. The extinguishing agent in the cylinders conforms to the manufacturer’s requirements for this system.
Yes No
17. The system has adequate supply of extinguishing agent as required to meet the demand for complete coverage of the cooking appliances.
Yes No
18. The cylinders are filled with the correct volume of extinguishing agent.
Required volume ________lbs. or __________gals.
Yes No
19. The cylinder gauge is in the operational range. Yes No
20. The CO2 or Nitrogen cylinder is fully charged.
Design weight _____ lb. Actual Weight _____lb.
Yes No
21. The hydrostatic testing of the agent cylinder(s) is up-to-date.
Date for next hydrostatic test ______________________
22. The system is connected to the fire alarm system. (if an alarm panel exists) N/A Yes No
23. The fire alarm panel receives the proper signals upon suppression system activation.
24. The alarm monitoring company received the alarm signal. N/A Yes No
CLEANING
25. The surfaces around the cooking surfaces, range hood, and ducting from hood to termination are free of grease deposits.
Kitchen Suppression System Page 3 of 3 Revised 12/21/2015
NFPA 96 reference:
Backflow Preventer Device Page 1 of 2 Revised 2/24/17
Inspection and Test Report (complete a separate form for each system)
BACKFLOW PREVENTION DEVICE
Park Alpha Code:_____________________ FMSS Location No.: _____________________
Location Description: _________________________________________________________
Date of Test: _________________________________ Time: _____________________
Location: Inside Outside Above Ground Pit
Usage: Fire Domestic Irrigation
Type of Device: RP DC DCDA RPDA
Manufacturer: ___________________________ Model No.: ______________________________
Size: ___________________________________ Serial No.: _______________________________
Orientation: Vert Up Vert Down Horizontal Height off Floor: ___________( in/ft)
REDUCED PRESSURE PRINCIPAL ASSEMBLE
*Relief ports on RPZ free of continuous discharge? Yes No
Date Installed:
DOUBLE CHECK VALVE ASSEMBLY
Apparent Pressure Drop
Across First Check
Valve________
Date Rebuilt:
Check Valve #1 Check Valve #2 Relief Valve PVB / SVB
Held at _______PSID
Leaked
Held at _______PSID
Closed Tight
Leaked
Opened at _______PSID
Did not open
AIR INLET
Opened at _______PSID
Did not open
Cleaned
Replaced
Cleaned
Replaced
Cleaned
Replaced
Cleaned
Replaced
________ PSID
Closed Tight
________ PSID Air Inlet _______PSID
Check Valve _______PSID
Leaked
________ PSID
F
IN
A L
R
E P
A
IR
S M
A D
E
IN
IT
IA
L
PASS FAIL No. 2 Shutoff Valve
Closed Tight
Leaked
Supply Pressure ___________
Backflow Preventer Device Page 2 of 2 Revised 2/24/17
Test Kit Manufacturer: __________________ Model: ______________________________
Serial No.: _______________________________ Last Calibration Date: _________________
Certified Tester: _________________________ Certified Tester No.: __________________
Signature: ______________________________________________________________________
FORWARD FLOW TEST—Required by NPS for all backflow preventers where fire sprinkler systems are located downstream of the backflow preventer. The test shall include forward flow test of the system at the designed flow rate, including hose stream demand. For back-flow preventers sized 2 inches and less, forward flow test shall be acceptable to conduct without measuring flow, where the test outlet is a size to flow the system demand.
Forward Flow Test Performed: Yes No
Design Flow Rate: __________________ GPM Actual Flow Rate: ______________ GPM
If not tested, Why:
DEFICIENCIES
Resolved
Location: _____________________________________________________________________
Deficiency: ___________________________________________________________________
Recommended Resolution: _____________________________________________________
Resolved
Location: _____________________________________________________________________
Deficiency: ___________________________________________________________________
Recommended Resolution: _____________________________________________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attached itemized sheet.
REPAIRS: All deficiencies have been corrected: N/A Yes No
| OTHER AKRO NOPMIS Inspection and Test Reports |
| Clean Agent or CO2 - Test Report 2015_1216 |
| Dry Chemical - Test Report 2015_1216 |
| Fire Alarm - Test Report 2015_1216 |
| Fire Pump - Test Report 2015_1216 |
| Fire Sprinkler - Test Report REV 1 |
| Kitchen Suppression - Test Report |
Backflow Prevention Device Testing JAS
File details come from the government source that posted it.