Sol_140P1526Q0018_Amd_0002.pdf
PDF 3 MB Posted
- Attached to
- INSPECT AND CLEAN MOCA/TUZI WATER TANKS
- Solicitation number
- 140P1526Q0018
About this file
This is Amendment 0002 to Solicitation 140P1526Q0018 for inspection and cleaning services of two water tanks located at National Park Service (NPS) sites in Arizona. The amendment is issued by NPS, IMR - Arizona MABO, with effective date 02/02/2026, and extends the solicitation period. The contracting officer is Taylor A. Jones (Taylor_A_Jones@nps.gov) and the contracting specialist is Dennis Zoltak (dennis_zoltak@nps.gov). The period of performance runs from 02/27/2026 to 04/17/2026.
The amendment includes a Questions and Answers section that clarifies key project requirements. Two water tanks require inspection and cleaning: the Montezuma Castle tank (30-foot diameter, steel welded, partially below grade, 10 feet tall with exterior stairway, 24"x24" roof hatch) and the Tuzigoot tank (22' x 44', concrete, below ground, 34"x34" roof hatch). The Montezuma Castle tank has a cathodic protection system requiring inspection. The tanks will remain full during inspection and cleaning operations. All wastewater and solids removed from both tanks must be disposed of at the Montezuma Castle National Monument sewage lagoons. No temporary water supply is required. The amendment notes that the Q&A period is now closed. Supporting documents include site photographs, aerial maps, and detailed images of tank locations, access hatches, service roads, and surrounding areas.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P1526Q0018_Amd_0001.pdf | ||
| Sol_140P1526Q0018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Taylor Jones
See continuation page
NPS, IMR - Arizona MABO 1824 S Thompson St, Ste 200 Flagstaff AZ 86001-2694
PIA
140P1526Q0018
02/02/2026
02/02/2026
1 10
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P1526Q0018/0002
Q&A attached. Q&A period is now over.
CS: dennis_zoltak@nps.gov
CO: Taylor_A_Jones@nps.gov
Period of Performance: 02/27/2026 to
04/17/2026
Solicitation #: 140P1526Q0018
Amendment #: 00002
INSPECT AND CLEAN MOCA/TUZI WATER TANKS
Questions and Answers listed below:
QUESTIONS:
Question # Question Answer/Response
1. Could you provide the specific diameter and height
(or length/width) for the 50,000-gallon tanks at both locations?
dimensions of each tank (pricing is based on square footage of the tank floors)
The Montezuma Castle tank is 30' (diameter) and the Tuzigoot Tank is 22' x 44'.
2. Are the tanks welded steel, bolted steel, concrete, or another material?
The Tuzigoot tank is concrete, below ground and the MOCA tank is steel welded and partially below grade.
3. Is there any external insulation on the tanks?
Additionally, are there specific cathodic protection systems we should be prepared to inspect?
The Montezuma Castle tank has a cathodic protection system.
4. For the internal dive inspections, could you confirm the size and location (side-shell or roof) of the primary access hatches?
Access hatches for both tanks are on the roof. The Tuzigoot hatch is 34" x 34". The Montezuma Castle hatch is 24"x24".
Montezuma Castle is 10 feet tall and has an exterior stairway.
5. Does the park have a designated area for the disposal of sediment/wash water, or is the contractor required to haul all waste off-site?
Disposal requirements for sediment removed from the tanks
Wastewater and solids from both tanks should be disposed of at the Montezuma Castle National Monument sewage lagoons.
6. Could you provide pictures of Tanks and Areas Surrounding?
See attached
7. Can you please provide drawings and pictures of the two tanks.
See attached
8. Clarification on temporary water requirements, including turnover rate and volume needed at each
No temporary water requirements for either park unit.
location
9. Will the tank be full or empty while inspection and sediment is being removed. SOW states in one area to fill and disinfect and in the section after states to drain.
The tanks will be full during inspection and cleaning.
Tuzigoot Tank
Montezuma Castle Tank
Gravel Service Road
Figure 1. Overview of Tuzigoot Tank.
Figure 2. Tuzigoot hatchway.
Figure 3. Overview of Montezuma Castle tank.
Figure 4. Montezuma Castle service road.
Montezuma Castle hatchway.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
| Q&A |
| Tankcleaning |