This document is an Amendment (0002) to Solicitation 140P1525Q0072 for the National Park Service, specifically for floor replacement at Salinas Pueblo Missions (SUPA). The amendment includes a questions and answers section addressing three key inquiries: (1) confirmation of an available asbestos report, (2) a floor plan marking asbestos abatement areas, and (3) verification that only loose asbestos tiles will be removed. The accompanying floor plan identifies specific areas requiring asbestos abatement, primarily in the entry/foyer, utility room, and kitchen/dining areas. The asbestos analysis report reveals varied asbestos content in different flooring samples, with some areas containing up to 3% chrysotile asbestos, necessitating careful removal and replacement procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P1525Q0072_Amd_0002.pdf | ||
| Sol_140P1525Q0072_Amd_0001.pdf | ||
| B09-_P1525Q0072_Amendment__1_Questions_and_Answers_0001.pdf | ||
| Sol_140P1525Q0072.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
CONTRACTING OPERATIONS - CENTRAL
1849 C Street
NW Washington, DC 20240
General: No other solicitation clauses or dates change with this Amendment.
Contracting Officer: Taylor Jones, Taylor_A_Jones@nps.gov, 520-780-9294
Solicitation #: 140P1525Q0072
Amendment #: 0002
Replace Flooring – SUPA
Questions and Government Responses listed below:
QUESTIONS:
Question # Question Answer/Response
1. Do you have an asbestos report available for the site?
Yes, see attached asbestos report
2. Can you provide a floor plan with all locations marked where floor tile abatement is required?
See attached floor plan with abatement area circled in red.
3. We read the specific work task to indicate that only loose asbestos tiles are to be removed—can you confirm if this is correct?
This is correct mailto:Taylor_A_Jones@nps.gov
2025-02-23-0808 2/24/2025 Page: 4
Main Level
Living Room
Kitchen/DiningEntry/Foyer
Utility Room
Hallway
Bedroom 1
Closet 2
Bedroom 2
Closet 1
Bedroom 3
Closet 3
Bathroom
Storage Area/Room Hall Closet
Garage
Furnace (A3)
Living Room
Kitchen/DiningEntry/Foyer
Utility Room
Hallway
Bedroom 1
Closet 2
Bedroom 2
Closet 1
Bedroom 3
Closet 3
Bathroom
Storage Area/Room Hall Closet
Garage
Furnace (A3)
Main Level
20' 10"
' 5
' 1
16' 10"
16' 6"
9'
4'
5' 1"
2' 9"
3'
' 8
' 4
9' 4"
6'
2' 6"13' 4"
3'
16'9' 10"
2' 6"
7' 5"
4' 6"
6' 7'
2' 4"
2'5' 5"
2'
3'
' 9
2' 11"
13'
61'
9'
2'
2'10'
1'
0"
3'
5' 2'
2' 6" 2'
5'
2' 6"
2'3'
1' 8"
3'
CAWalker Oval
CAWalker Callout Asbestos abatement required in area circled in red to allow for floor and baseboard repairs.