B09-_P1521R0008_Amendment_Questions_and_Answers_0001.docx
DOCX document 46 KB Posted
- Attached to
- CHIR FARAWAY RANCH HOUSE ROOFING & PAINT
- Solicitation number
- 140P1521R0008
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B09-_P1521R0008_Amendment_2_Questions_and_Answers_0002.pdf | ||
| FARAWAY_RANCH_HOUSE_PEST_MITIGATION_0002.xlsx | XLSX spreadsheet | |
| Sol_140P1521R0008_Amd_0002.pdf | ||
| Sol_140P1521R0008_Amd_0001.pdf | ||
| Sol_140P1521R0008.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
INTERMOUNTAIN REGION
Arizona Major Acquisition Buying Office 1824 South Thompson Street, Suite 200 Flagstaff AZ 86001
Solicitation # 140P1521R0008; Amendment# 1 Questions and Answers from Site Visit held on June 28th, 2021 at 11:00 AM Local Arizona Time
General
1. Question: The scope of work mentions “contractor will be paid on a lump sum payment once all work is complete and accepted by the federal government”. Is there any chance of progress payments through the term of this larger project?
Answer: Yes, progress payments are authorized if required and will be determined once awarded.
2. Question: In the scope of work it mentions (f) “Quotation must be valid for a minimum of 60 days”. With materials being subject to many changes in cost, is there a way for these quotes only be considered valid for 30 days?
Answer: Yes, it will officially change to 30 days valid
3. Question: What does the paint analysis requirement that the NPS is requesting?
Answer: The Park Service has seen, in the past on historical structures, a small square or circle core sample is taken of paint. This will provide the layers of paint for the analysis; this will determine previous colors that had been applied. Contractors will be able to determine the paint composition of the current paint to see what the original color might have been before turning pink. We require contractor to obtain a sample that is not been weathered and send in to be analyzed.
Checklist for quote submittal:
· Signed amendments
NO OTHER SOLICITATION CLAUSES OR DATES WILL BE CHANGED WITH THIS AMENDMENT.