Amendment_1_Questions_and_Answers_0001.docx

DOCX document 16 KB Posted

Attached to
YELL FIBER BROADBAND TO GRANT
Solicitation number
140P1426R0014
Issued by

About this file

This file is an Amendment 1 Questions and Answers document for the Yellowstone National Park Fiber Broadband to Grant solicitation (140P1426R0014). The document addresses three key inquiries regarding project scope and deliverables. The Park has clarified that it is seeking a service provider to build and own the fiber network while providing internet services back to Yellowstone National Park, rather than transferring asset ownership to the Park. Regarding fiber mileage, the estimated underground fiber distances are specified in tables within the Statement of Work, and the Park expects contractors to provide detailed design documentation including fiber routes and designated equipment locations in their proposals. NEPA environmental review has been completed for fiber installation throughout developed areas of the park. This Q&A amendment supplements the original solicitation for a negotiated firm-fixed contract valued between $250,000 and $500,000, with work to be performed at Yellowstone National Park in Teton County, Wyoming. Offerors must demonstrate capability to obtain and maintain a valid right-of-way permit from the National Park Service prior to beginning work and must provide annual work plans by April 1st each year for any maintenance, vegetation management, or work activities within the authorized work area.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

· Ownership Model: Is the Park seeking to own the fiber network assets built for this project, or are you looking for a service provider to build and own the network while selling internet services back to the Park? the Park is looking for a service provider to build and own the network while selling internet services back to the Park

· Fiber Mileage: What is the estimated underground fiber mileage expected to be constructed for this project? estimated distances are listed in the tables in the statement of work

· Design Documentation: Does the Park currently have a high-level design document that includes fiber routes, designated locations for core equipment, and a comprehensive list of all locations to be connected? List of all locations to be connected are in the tables. The design is expected to be provided in the proposal. NEPA is complete for fiber installation throughout the developed areas.

File details come from the government source that posted it. Updated .