This is a specification document for construction work at Grand Teton National Park's Highlands Housing Area near Moose, Wyoming. The project involves replacing the water and wastewater systems, including extending the existing Moose water transmission line to Highlands, trenching across Cottonwood Creek with diversion and dewatering methods, replacing the internal water distribution system, abandoning the existing well and infrastructure, constructing a new lift station, septic tank, leach field, and collection piping, and decommissioning the old system in place. The work will disturb approximately 2.5 acres within a 4-acre project area.

The specifications establish comprehensive requirements for construction operations within the National Park, including strict limitations on work hours (8 AM to 7 PM), seasonal restrictions, and detailed environmental protections. Instream work is limited to August 1 through October 1 to protect fish spawning and amphibian hibernation. The Highlands Housing Area operates April 15 through October 10, and existing water and sewer service must be maintained during operational periods. Contractors must comply with Grand Teton National Park Standard Mitigations and Stipulations, including wildlife protection protocols (bear country training and reporting requirements), equipment cleaning and inspection before entering the park, topsoil salvage and proper replacement, exotic plant mitigation, and coordination with park staff regarding vegetation management, cultural resources, and utilities. The contractor must maintain spare parts on-site for emergency repairs, submit pre-construction video documentation, obtain required permits, develop traffic control and hazardous spill plans, and coordinate with park facilities regarding utility connections. All staging and stockpiling must occur in previously disturbed areas, and construction boundaries are defined by "Limit of Disturbance" lines on the drawings. The contractor is responsible for final site grading, topsoil installation, and maintaining preparation for seeding, while the National Park Service handles subsequent seeding, weed control, and watering.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 12 00 NATURAL FEATURES PROTECTION

01 27 00 DEFINITION OF CONTRACT LINE ITEMS

01 31 00 PROJECT MANAGEMENT & COORDINATION

01 32 16 CONSTRUCTION SCHEDULE

01 32 33 PHOTOGRAPHIC AND VIDEO DOCUMENTATION

01 33 23 SUBMITTAL PROCEDURES

MATERIAL SUBMITTAL LIST

01 35 23 SAFETY REQUIREMENTS

01 40 00 QUALITY REQUIREMENTS

01 42 00 REFERENCES

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 55 26 TRAFFIC CONTROL

01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION

SWPPP – NOTICE OF TRANSFER AND ACCEPTANCE

01 67 00 PRODUCT REQUIREMENTS

01 73 40 EXECUTION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PROJECT WASTE MANAGEMENT PLAN WORKSHEET

STANDARD SOLID WASTE CONVERSIONS

01 77 00 CLOSEOUT PROCEDURES

PRODUCT EQUIPMENT SPECIFICATION WATER

PRODUCT EQUIPMENT SPECIFICATION WASTEWATER

01 78 23 OPERATION AND MAINTENANCE DATA

01 79 00 DEMONSTRATION AND TRAINING

DIVISION 02 – EXISTING CONDITIONS

02 41 16 STRUCTURE DEMOLITION

DIVISION 03 – CONCRETE

03 30 00 CAST IN PLACE CONCRETE

DIVISION 26 – ELECTRIC

26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 48 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

26 29 13 MANUAL AND MAGNETIC MOTOR CONTROLLERS

DIVISION 31 – EARTHWORK

31 05 13 SOILS FOR EARTHWORK

31 05 16 AGGREGATES FOR EARTHWORK

31 10 00 SITE CLEARING

31 23 17 TRENCHING

31 23 18 ROCK REMOVAL

31 23 19 DEWATERING

31 23 23 FILL

31 23 24 FLOWABLE FILL

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 91 19.13 TOPSOIL PLACEMENT AND GRADING

DIVISION 33 – UTILITIES

33 05 17 PRECAST CONCRETE VAULTS AND MANHOLES

33 11 13 PUBLIC WATER UTILITY DISTRIBUTION PIPING

33 12 16 WATER UTILITITY DISTRIBUTION VALVES

33 12 19 WATER UTILITY DISTRIBUTION FIRE HYDRANTS

33 13 00 DISINFECTING OF WATER UTILITIES

33 14 00 WATER UTILITY DISTRIBUTION EQUIPMENT

33 29 00 WELL ABANDONMENT

33 31 00 SANITARY UTILITY SEWERAGE PIPING

33 36 00 SEPTIC SYSTEMS

END OF INDEX

GRTE – 249645, 330091 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Locating Utilities

9. Work Restrictions.

10. Special Construction Requirements.

11. Protection of Parks and Public Lands.

12. Soils Investigation Report.

13. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Highlands Housing Area, Grand Teton National Park, Moose, Wyoming.

B. The Work consists of the following:

1. The Work includes construction of a new water distribution system, new sewer collection system, new septic system, including septic tank, dosing pump station, and leachfield

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. Phasing will not be required for this project; however, the Contractor is required to schedule Work in accordance with Section 01 32 16 – Construction Schedule, comply with Paragraph 1.11, “Work Restrictions” and the following requirements:

1. Mark construction boundaries and obtain approval of the boundary locations by the

Contracting Officer (CO) prior to commencing with any construction.

2. Contractor shall maintain operation of the existing septic system that serves the campground during times of operation. Submit a plan for approval of temporary shutdowns and changeovers to the CO. Do not proceed with service interruptions, without prior written consent from the CO.

3. When practical, complete mowing and mulching of construction corridors. Work shall be completed the fall prior to construction to prevent birds from nesting within the construction corridor the following spring.

GRTE – 249645, 330091 01 11 00 - 2

4. Do not demolish or abandon existing facilities until new facilities are fully operational and approved by the CO. Since construction is to occur during periods of operational shutdown, all water and sewer must be completed and operational prior to operation startup as stated in other locations of the specifications.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

1. Contractor shall be responsible for final site grading, topsoil procurement, topsoil installation, and maintaining prep for topsoil seeding. No vehicles shall be permitted to travel over topsoil after installation. If topsoil is traveled upon, contractor shall be responsible for ripping and loosing topsoil, and removing any rocks. The NPS will be responsible for seeding, weed control, and watering following topsoil installation.

1.5 GOVERNMENT-FURNISHED MATERIALS

A. Government will furnish products indicated.

1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.

2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.

3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.

4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.

5. Contractor is responsible for protecting Government-furnished items from damage during storage, handling and use, including damage from exposure to the elements.

6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.

7. Contractor shall install and otherwise incorporate Government-furnished items into the Work.

1.6 SUBMITTALS

A. Section 01 33 23 - Submittal Procedures: Requirements for submittals.

B. Product Data: Submit data on spare stock pipe and fittings.

GRTE – 249645, 330091 01 11 00 - 3

1.7 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the construction limits indicated on the drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated. Construction limits are defined by the “Limit of Disturbance” boundary shown in the Construction Drawings.

B. Coordinate with CO and Park Staff to minimize disruption of normal Park activities. Inform construction workers and supervisors about the special sensitivity of Park values, regulations, and appropriate housekeeping.

C. Maximize the use of previously disturbed areas for staging and stockpile areas to minimize ground disturbance.

D. Storage of Materials: Confine storage of materials to Contractor Staging Areas and designated Stockpile Areas as shown on the drawings. Acceptable use of each staging area is defined in the drawings.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings located outside construction limits. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with the CO and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

6. Comply with requirements of Section 01 12 00 - Natural Features Protection.

F. Driveways and Entrances: Keep driveways, parking lots, and roadways serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials unless otherwise indicated or approval is given.

1. Schedule deliveries to minimize use of driveways, entrances and accesses.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

G. Construction Camp: Establishment of a camp within the park will not be permitted.

H. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on Park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

GRTE – 249645, 330091 01 11 00 - 4

1.8 PUBLIC USE OF SITE

A. Contractor, shall at all times, conduct his operations to ensure the least inconvenience to the public. All traffic on Park Roads must be permitted to pass. If excavation, backfill, or paving operations require a temporary closure of a street, the Contractor shall route traffic on a clearly signed and marked detour. The Contractor will be required to place and maintain signs for all detours.

B. Comply with requirements specified in Section 01 55 26 - Traffic Control.

C. Implement measures to reduce adverse effects of construction on visitor health and safety.

1.9 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Facilities

1. Government will occupy and/or maintain existing facilities adjacent to the construction

2. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.

3. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing accesses and exits, unless otherwise indicated.

4. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

B. New Facilities

1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of facilities, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational and required tests, inspections and training of Government personnel shall be successfully completed. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of facility.

d. On occupancy, Government will assume responsibility for maintenance and custodial service for accepted portions of the facility.

1.10 LOCATING UTILITIES

A. Comply with Section 01 73 40 – Execution, for location and verification of existing utilities.

1.11 WORK RESTRICTIONS

A. On-Site Work Hours:

GRTE – 249645, 330091 01 11 00 - 5

1. Highlands Housing Area operation runs from April 15 – October 10. The existing water and sewer service is not to be interrupted outside of these dates except for minor disruptions and tie-ins to the new system.

2. Climbers Ranch operation runs from June 8 – October 10. Access must be maintained to Climbers Ranch at all times..

3. The inner park road closes to the public at the Taggart Trailhead and Signal Mountain Lodge between November 1 and May 1. Despite this public closure, contractor access to the site will be allowed when the roads are clear from approximately mid April to mid November.

4. Hours in which equipment can be used is limited from 8AM to 7 PM.

5. Instream work is limited to a period between August 1 and October 1 to avoid fish spawning and critical development and hibernation periods for amphibians.

B. Operation of Existing Facilities: The Contractor is not authorized, except under emergency conditions, to operate any Park-owned water valves or equipment.

C. Construction Limits: “Limit of Disturbance” lines are provided on the drawings to describe construction boundaries. Do not operate equipment outside the construction boundaries as indicated on the drawings. Removal of specific trees and bushes are noted on the drawings. Any unauthorized disturbance may result in Grand Teton National Park issuing the appropriate level of law enforcement to the responsible person, or Contractor.

D. GRTE Mitigation Restrictions

1. Follow all attached Grand Teton National Park and John D. Rockefeller, Jr. Memorial Parkway Standard Mitigations and Stipulations. Where conflicts between the standard mitigations and this contract occur, this contract supersedes requirements of the standard mitigations.

2. Soil: Schedule construction during dry periods and when surface and ground water levels are low to minimize soil compaction outside of trenches.

3. Birds: Coordinate with the NPS two weeks prior to clearing and grubbing or other vegetation disturbing activities during the months of May 1 – August 1 for nesting bird surveys.

4. Birds: An osprey nesting platform is located near to Climber’s Ranch and the water transmission portion of this project. Work is prohibited within ½ mile of this platform when occupied. CO will coordinate with Park wildlife staff prior to and throughout the work period to determine if work restrictions are required.

E. Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify CO not less than one week in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without CO’s written permission.

3. Do not conduct planned utility interruptions outside the days of Monday through

Wednesday.

F. Permitting: Contractor shall obtain all permits required for construction of facilities described in this Contract. Comply with permitting requirements listed in Section 01 31 00, PART 1.9 “Project Management and Coordination”.

GRTE – 249645, 330091 01 11 00 - 6

1.12 SPECIAL CONSTRUCTION REQUIREMENTS

A. There are no seasonal restrictions for this project. Teton Park Road is closed from Taggart Trailhead to Signal Mountain Lodge November 1 to April 30 every year. Administrative travel is allowed for contractor until snow covers road, typically in November. Administrative travel is once again allowed in early April when roads are clear of snow. Contractor shall notify CO if access is required to the project site during Park closure. Costs associated with plowing snow to gain access to the project site outside of typical park plowing times shall be borne by the Contractor.

B. Pre-construction Video: Prior to execution of Work, Contractor shall submit a video recording of the work site in accordance with Section 01 32 33 - Photographic and Video Documentation.

C. Repair Stock: Contractor shall maintain a stock of spare parts and materials at the job site including couplers and pipe for emergency repair of utilities located adjacent to new construction.

Spare parts shall be approved for the intended application and comply with Division 33 of these specifications.

D. Contractor shall be responsible for repairing utilities damaged during construction.

1.13 PROTECTION OF PARKS AND PUBLIC LANDS

A. Equipment and Vehicle Cleaning: All vehicles and equipment including office trailers and residential trailers that enter the Park and are staged in association with this project, will be inspected by the CO prior to the entry into the Park for mud, weeds and other unwanted substances. Pressure wash all vehicles, including earth-moving and mulching equipment for mud and seed. Remove dirt, debris, or plant material that may be in equipment cabs. Comply with the following:

1. The spread of exotic invasive plant species in the Park is a serious concern, and no equipment will be allowed to offload, nor remain within the Park, if dirt or other contaminants with the potential to harbor seeds are apparent. Any equipment which departs the project site (excluding hauling vehicles) must repeat an identical cleaning and inspection process, including formal acceptance by the CO prior to being remobilized and offloaded at the project site.

2. Notify the CO a minimum of 48 hours prior to the entry of vehicles and equipment. The CO will make arrangements for the inspections.

3. Prior to offloading of any equipment, obtain verbal approval from the CO.

4. Clean hauling vehicles before their initial entrance into the Park; subsequent entries will not require cleaning or inspection unless equipment is used at another job site or as requested by CO.

5. Any equipment that is unacceptable to the CO shall be immediately removed from the Park.

B. Construction Limits: Do not operate or park any equipment off the paved or established roadways except in approved areas. Do not operate or store vehicles and equipment leaking oil, gas, or anti-freeze within the Park boundaries. Do not drain oil, hydraulic fluids, anti-freeze, or other chemicals onto the ground within Park boundaries. Completely contain diesel fuel at the work site. Notify CO of any spill and clean up spill immediately. Contractor is required to have a Hazardous Spill Plan in accordance with Section 01 50 00 - Temporary Facilities and Controls.

GRTE – 249645, 330091 01 11 00 - 7

C. Overnight Camping: Sleeping vehicles or camping within the Park Boundaries will not be allowed.

D. Explosives: Do not use explosive materials within the Park boundaries.

E. Wildlife Protection: Do not feed or disturb wildlife within the Park Boundaries. Store and handle food, fuel, food containers, dishes or other attractants, including toiletries, pet food/bowls, and any odorous item in a manner that does not attract bears, i.e., no food, pet food, garbage, drinks, trash including food and drink containers except during actual use. Construction workers shall maintain required distances from all wildlife at all times.

1. All on-site construction personnel will be required to attend and complete Wildlife and

Bear briefing sessions provided by Park personnel, entitled “Working Bear Country”, reference 36 CFR., The Human-Bear Management Plan for GRTE; and the JDR (1989), Interagency Grizzly Bear Committee; 1986 Interagency Grizzly Bear Guidelines, Missoula, Montana. Construction personnel will receive training with regards to the NPS Bear Management Plan safety protocols, sanitation standards, and food storage regulations. Notify CO two (2) weeks before starting Work so the briefing session can be coordinated.

2. Construction personnel are required to report all bear sightings in the work area to the Teton Interagency Dispatch Center (TIDC) and the CO immediately. Contractor shall temporarily suspend Work when a grizzly bear is near an active construction area and creates a potential animal/human conflict.

3. When it is determined by the CO that there is a potential animal/human conflict, stop work at the construction site until the CO determines that it is safe for work to continue. If required by Park staff, Contractor, Subcontractors, and employees may be required to purchase and carry bear pepper spray. The Government will not supply bear pepper spray.

4. Contractor supplied garbage bins placed at the construction site must be bear proof and meet Park requirements. Remove all garbage and food trash from the project site daily.

5. Any mishandling of garbage, trash, food, and other potential bear attractants described above will result in Grand Teton National Park issuing the appropriate level of law enforcement to the responsible person, or Contractor. If mishandling occurs and a specific individual is not determined, the Contractor will be held responsible.

6. In camping, picnic, trailhead, and day-use front country areas, all food items must be attended at all times or stored inside bear resistant food storage lockers and/or inside hard sided vehicles with doors locked and windows closed.

F. Protection natural features including vegetation, soils, streams and wetlands in accordance with Section 01 12 00 - Natural Features Protection.

1.14 SOILS INVESTIGATION REPORT

A. A full soils investigation report was completed for the project. A copy of the report is available at Contractor request.

B. A copy of this report is attached following this Section and provided to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

GRTE – 249645, 330091 01 11 00 - 8

1.15 ADDITIONAL REPORTS

A. The following reports and project information are provided as supplemental information following this specification:

1. GRTE Mitigations and Stipulations

2. Highlands Housing Area geotechnical analysis

B. If conflicts occur between these reports and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

Revised 28 March 2018

Grand Teton National Park (GRTE) John D. Rockefeller, Jr. Memorial Parkway (JODR) Standard Mitigations and Stipulations

NOTE: Some projects and activities are proposed by non-National Park Service (NPS) individuals, groups, partners, officials, agencies, organizations, businesses, etc. These proposals are usually initiated through a special use permit request or are part of an agreement, contract, commercial authorization, or other signed record between the NPS and the non-NPS entity. In these cases, the appropriate NPS employee will serve as the Project Leader and “liaison” to ensure proper compliance procedures are being followed. The “liaison” will be the contact with the non-NPS entity.

The Project Leader is responsible for ensuring the following mitigations and stipulations are followed. The non-NPS entity will contact the NPS Project Leader if any of the mitigations and stipulations reference a specific phone number below. The Project Leader will contact the referenced office or individual and will advise the non-NPS entity.

Congress charged the NPS with managing the lands under its stewardship “in such manner and by such means as would leave them unimpaired for the enjoyment of future generations” (NPS Organic Act, 16 USC 1). As a result, NPS staff routinely evaluate and implement mitigation measures whenever conditions occur that could adversely affect the sustainability of national park system resources.

Mitigation is defined in the Code of Federal Regulations (40 CFR 1508.20) as:

• Avoiding the impact altogether by not taking a certain action or parts of an action.

• Minimizing impacts by limiting the degree or magnitude of the action and its implementation.

• Rectifying the impact by repairing, rehabilitating, or restoring the affected environment.

• Reducing or eliminating the impact over time by preservation and maintenance operations during the life of the action.

• Compensating for the impact by replacing or providing substitute resources or environments.

The following mitigation measures were developed to minimize the degree and/or severity of adverse effects and would be implemented as appropriate during approved project activities. The NPS may need to obtain federal and state environmental permits and, as part of that process, additional mitigation measures could be required by other agencies.

Assessment of Effect

• If previously unknown archeological resources and/or human remains are discovered during construction, all work in the immediate vicinity (600 feet) of the discovery shall be halted until the resources are identified and documented and an appropriate mitigation strategy developed. Contact the Branch Chief of Cultural Resources (307-739-3671).

Assessment of Effect – Cultural Landscapes

• All vegetation modification, including tree removal, at National Register of Historic Places -listed or -eligible properties shall be reviewed and approved by the Section 106 specialists (as well as by wildlife and vegetation specialists).

dlongtin Text Box Attachment 1.D.3 (10 pages)

• All work on or near historic buildings, structures, sites, and landscapes shall be conducted in accordance with the Secretary of the Interior's Standards for the Treatment of Historic Properties in consultation with the Branch Chief of Cultural Resources (307-739-3671). Any deviation from the approved specifications must be submitted for further review.

Assessment of Effect – Historic Structures

• All work on or near historic buildings, structures, sites, and landscapes shall be conducted in accordance with the Secretary of the Interior's Standards for the Treatment of Historic Properties in consultation with the Branch Chief of Cultural Resources (307-739-3671). Any deviation from the approved specifications must be submitted for further review.

• Consult with NPS cultural resource specialists or archaeologists in advance (generally 60 days) of any ground disturbing activities or work on or near buildings, structures, sites and landscapes eligible for or determined eligible for listing in the National Register of Historic Places.

• Inform all contractors and subcontractors of the penalties for illegally collecting artifacts or intentionally damaging archeological sites or historic properties.

Night Sky

• Project shall comply with NPS lighting guidelines to reduce impacts to the night sky and wildlife. This will include, but is not limited to, low-level lighting, minimized glare, downward focused light fixtures, and energy efficient light sources.

Park Operations & Mgmt – Aviation

• The following stipulation applies to all unmanned aircraft and aircraft managed by the Department of the Interior and Department of Agriculture in accordance with the Teton Interagency Aviation Management Plan. Coordinate all aircraft activities including unmanned aircraft with the Park's Interagency Aviation Officer (307-739-3339/5524) at least 30 days in advance. Flight requests or flight schedules should be submitted to the Aviation Officer by the requestor and be returned to the requestor if approved from Teton Interagency Dispatch. Flight requests or flight schedules for nonemergency missions need to be submitted allowing enough time for approval of project aviation safety plans, aircraft selection or procurement, and selection of aircraft management and necessary support personnel.

• The following stipulation applies to manned aircraft activities not directly managed by Teton Interagency Aviation and that require a special use permit or scientific research permit. For each day of activity where any type of aircraft is used the permit holder or aircraft operator shall contact Teton Interagency Dispatch (307-739-3630) prior to and at the end of the operation.

Park Operations & Mgmt – Construction General

• Hours of work may be determined by the park to avoid construction disturbance to visitors, park residents, or wildlife.

• The location of all potential utility lines in work areas shall be field located and marked prior to work to avoid disturbance conflict.

• Maintain a safe construction zone. Fence around open holes when personnel are not present and provide for a slope out of the hole such that wildlife trapped in the excavation may be able to escape.

• Control dust during construction by minimizing soil exposure, watering, and using other dust prevention methods.

• Dispose of construction and/or demolition debris (e.g., old water lines, appurtenances, water tanks, valves, packaging materials, trash) at appropriate areas designated by the park. When possible, debris will be disposed of at a materials recycling facility.

• All project zones will be kept trash free at all times.

• To minimize the amount of ground disturbance, staging and stockpiling areas will be located in previously disturbed sites, away from visitor use areas to the extent possible. All staging and stockpiling areas shall be returned to pre-construction conditions following project completion.

Parking of construction vehicles will be limited to these staging areas, existing roads, and previously disturbed areas.

• Identify and define construction zones with construction tape, snow fencing, or other material prior to any construction activity. Use the zone to confine activity to the minimum area required for construction. Construction activities, including material staging and storage, cannot occur beyond the construction zone fencing.

• A traffic control plan for use during construction as approved by the park will be developed and enforced to minimize disruption to visitors and park operations and to ensure safety of the public, park employees, and residents.

Park Operations & Mgmt - Communications

• Inform contractors (construction workers and supervisors) about the special sensitivity of park values, regulations, and appropriate housekeeping.

• Contractors will coordinate with park staff to minimize disruption of normal park activities.

• If the project or activity occurs within or immediately adjacent to park housing areas, coordinate with the park's Housing Program Manager (307-739-3577) at least one week before the project or activity is scheduled to begin and immediately after it is completed.

Park Operations & Mgmt - Utilities

• Notify Park Facilities Management Utility Systems staff (307-739-3366) prior to a contractor connecting to or repairing a water or sewer line in the park. Any repairs to potable water lines must be coordinated with the park, and any potable water line that loses pressure during construction will be required to be placed into Boil Order status until a sample can be collected and tested.

• Following construction, furnish the GRTE GIS Office (307-739-3493) with utility location information, including a shapefile using coordinates NAD83 UTM 12N, company name, and type and number of lines.

Soils, Topography, Geology – Construction

• Avoid rutting or excessive soil compaction caused by vehicles or equipment. Construction activities shall be restricted during saturated soil conditions or severe weather conditions to avoid damage to soils and vegetation. In the event of adverse weather conditions, the project leader will consult with the SRM Vegetation Branch (307-739-3678) to ensure that ground conditions are acceptable for project activities.

Soils, Topography, Geology – Disturbance

• To minimize the amount of ground disturbance, locate staging and stockpiling areas in previously disturbed sites to the extent possible. Return all staging and stockpiling areas to pre-construction conditions following construction.

Soils, Topography, Geology – Erosion Control

• To minimize soil loss/erosion at the project site, erosion control best management practices (BMPs) including protection measures such as sediment traps, silt fences, erosion check screens/filters, jute mesh, will be used if necessary, to prevent the loss of soil.

Soils, Topography, Geology – Topsoil

• Topsoil should be salvaged at the beginning of all ground disturbance activities by scraping the topsoil to the side prior to deeper digging. Topsoil refers to the uppermost layers of soil and includes fine particles, small roots, rocks, and cobbles. It is usually darker in color, and is the layer in which the majority of roots grow and beneficial microorganisms exist. It is usually the top 2-6 inches.

Conserving topsoil will minimize impacts to vegetation and help preserve valuable micro-organisms and the native seed bank.

• Store salvaged topsoil separately from other materials. Limit the height of topsoil stockpiles to 36 inches. Do not stockpile topsoil or subsoil within drip line of remaining trees. Excess soil will be stored only at approved locations.

• Replace topsoil and other excavated soils and rock in the proper order, cobble lowest, then subsoil, then topsoil. Use a trench box if one is needed to reduce disturbance. Spread topsoil as near to the original location as possible.

• During the final stages of project implementation, scarify and loosen compacted subsoils to a minimum depth of 12 inches prior to replacing the salvaged topsoil. Soil decompaction will be done with equipment that has ripping teeth, placed a maximum of 12 inches apart.

• Do not drive or operate equipment on newly replaced topsoil. Do not re-enter the project site once revegetation/restoration work has been initiated and/or completed.

Soundscapes-Idling

• To reduce noise and pollution emissions, construction equipment and all motor vehicles will not idle any longer than is necessary.

Soundscapes-Mufflers

• Ensure that motorized vehicles and equipment have properly functioning mufflers.

Vegetation

• Coordinate all project work with park vegetation specialists regarding invasive, non-native plant

(weed) treatments, revegetation requirements, costs, and scheduling. Contact the SRM Vegetation Branch (307-739-3678).

• Limit ground disturbance to the smallest area possible to reduce disturbance to soil and native plants and reduce the potential for the introduction and/or spread of non-native, invasive plant species.

• Plant survey for rare and/or sensitive species are required prior to ground disturbing activities and must be conducted during growing seasons when these species could be identified.

Vegetation – Exotic Plants

• Seed mixes used for revegetation in roadside corridors will be composed of native species and approved by SRM Vegetation Branch staff.

• Prior to project implementation, SRM Vegetation staff will conduct invasive, nonnative plant surveys in the project area. Invasive weed control measures will be implemented to monitor and mitigate impacts within the first 3 years (minimum) of construction.

• To reduce the threat of nonnative, invasive vegetation being introduced to the park, all imported material (i.e., sand, gravel, rock, rip-rap, etc.) must be obtained from a park approved or county weed district approved source. Teton County Weed and Pest has currently approved as weed-free the various Evans Construction pits in Teton County. If a new material source is requested, park vegetation staff will seek county-approved material source pits and/or perform a nonnative, invasive plant inspection.

• Material sources, including sand, gravel, rock, rip-rap, mulch, etc. that is not attained form a county or park approved weed-free material sources must be precooked (300 degrees) or washed to prevent spread on invasive weeds in the park.

Vegetation – Miscellaneous

• Vegetation beyond the estimated scope of disturbance shall not be damaged or removed without prior approval via the project documents or by park vegetation management staff.

• To facilitate revegetation and non-native, invasive plant management, provide the SRM Vegetation Branch (307-739-3678) via project documents, with an estimate of potential ground disturbance at least 4 weeks prior to work and with the dimensions of the disturbed area after the work is complete.

• Consider minimizing ground and vegetation disturbance by boring or other alternatives to trenching activities.

• Use wooden mats for vehicle and equipment access to the site to limit damage to existing vegetation.

• Avoid destruction of individuals or populations of sensitive plant species or alteration of their habitat when conducting ground disturbing activities. SRM vegetation staff will notify project managers of rare or sensitive plant species for project documents prior to initiation of activities.

• For roadside brush removal activities, parts under 3" in diameter may be "lopped and scattered" into adjacent forested vegetation so that it is 6 inches or less in depth measured immediately after treatment. If chipping, broadcast chips so that chip depth is less than 2 inches measured immediately after treatment.

Vegetation - Trees

• Preserve existing trees to the extent possible, and during trenching operations, avoid damaging the roots of nearby trees.

• Tree/ Slash Removal - When trees are felled as part of project right of way clearing, remove all tree parts greater than 3” in diameter from the site except those pieces (“slash”) needed for revegetation or reclamation of the disturbance. The limbs, tops, and miscellaneous residue left by forest thinning and pruning activities are commonly called slash.

• Tree/ Slash Removal - Tree parts (slash) under 3" in diameter (not chips) may be "lopped and scattered" into adjacent forested vegetation so that it is 6 inches or less in depth measured immediately after treatment. If the <3" slash is chipped, broadcast the chips so that chip depth is less than 2 inches measured immediately after treatment. Chips may also be removed from the park for other uses.

• Stumps resulting from tree removal shall be flush cut level with the ground and no higher than 2” as measured from the uphill side.

Vegetation – Weed/Seed Free

• If a material source does not have an approval for weed-free, or if a material source fails an inspection, then the material must be clean of weed seed materials and dirt debris before entering the park. That typically entails cooking material such as sand and gravel to 300 degrees F. For larger rock and rip-rap, the rock can be separated from smaller dirt materials, and washed prior to entering the park.

• All vehicles and equipment shall arrive at the job site in a condition free of mud, dirt, and plant material. A method such as pressure washing prior to transport will be needed to comply with this requirement. Prior to offloading of any equipment, inspection and verbal approval must be obtained from the park resource management representative or delegated representative. The spread of non-native, invasive plant species in the park is a serious concern, and no equipment will be allowed to offload or remain within the park if dirt or other contaminants with the potential to harbor seeds or other plant material is apparent.

Fish and Wildlife

• Work that includes influence or direct disturbance to a wetland or stream should not be conducted during fish spawning periods. Spawning phenology by species is dependent on location of waterway, so please contact the SRM Fish and Wildlife Branch Fisheries Biologist (307-739-3666) for specifics.

• Consult with SRM Fish and Wildlife biologists (307-739-3666) regarding culvert design to allow for fish and wildlife passage where applicable.

• To prevent introduction of terrestrial or aquatic invasive species, all equipment, including rubber-tired land and tracked land vehicles, construction and facility equipment, watercraft, and personal use equipment such as diving gear, must be thoroughly cleaned, and inspected by park personnel before being operated or launched in the park.

• Unless otherwise noted (i.e., elk rutting and near sage grouse leks), limit routine construction activities to 30 minutes after sunrise to 30 minutes prior to sunset to avoid disturbance to wildlife.

• To protect special status species:

o Inform staff about the potential for special status species in or near the area of the proposed activity. Work will cease if a special status species is discovered in the project area, until park staff re-evaluates the project. Protective measures, including potential modification of the work or the work schedule, could be determined necessary.

o Ensure that all mitigations/conservation measures determined through Endangered Species Act Section 7 consultation with the U.S. Fish and Wildlife Service (USFWS) are followed.

o In circumstances when it is deemed necessary to conduct activities near sites known to support threatened or endangered species, such work will be performed in a way (specified by the park biologist) to minimize impacts to the listed species (e.g., working quietly on-site, and minimizing time in or near habitats en route to their work sites).

• All project activities must comply with GRTE’s Superintendent’s Compendium related to food storage and park recommended best management practices for living and working in bear country.

Bear “attractants” include food, drinks, garbage, cooking utensils, dirty / soiled pots/pans/plates, stoves, grills (charcoal or gas), empty or full coolers, storage containers with food or previously holding food (except approved bear resistant canisters), beverage containers, pet food/bowls, and any odorous item that may attract a bear such as toiletries.

o At all times in all locations, including the backcountry, all staff (NPS, Volunteers-in-Parks (VIPs), contractors, etc.) must ensure that all bear attractants are attended at all times. All unattended attractants must be stored securely inside a building, a bear resistant food storage locker (if available), in a hard sided vehicle with doors locked and windows closed, or in an Interagency Grizzly Bear Committee (IGBC) approved portable bear resistant food storage canisters; or disposed of properly in a bear-resistant garbage receptacle. Backpacks and/or daypacks containing unsecured attractants (i.e. not in a canister) must not be left unattended.

o All personnel must attend a briefing on proper food/attractant storage and bear safety presented by a qualified member of the park's bear management team or their designee.

Please contact the park's Bear Management Office (307-739-3673) at least two weeks prior to the desired start date to schedule a briefing.

o All human-bear conflicts must be reported to Teton Interagency Dispatch Center immediately (307-739-3301). All bear sightings must be reported to the park’s Bear Management Office (307-739-3673) within 24 hours.

o Provide for proper storage and disposal of materials that may be toxic to bears. All potentially toxic attractants, including petroleum products, must be stored or disposed of in such a way that they are not available to bears.

o Construction debris must be separated from human food garbage and disposed of in dumpsters that can be closed at night. No open dumpsters are allowed. A request for an exception to the open dumpster stipulation, however, can be made to the project manager who will consult with the park’s Bear Management Office to determine if such use will be authorized. The use of open dumpsters will only be considered if the following conditions can be met: the open dumpster must be stored behind a locked fence out of view and inaccessible to the public, will be labeled construction debris only, and be inspected daily to ensure that no human food garbage is in the dumpster.

• For all projects occurring within the Grizzly Bear Primary Conservation Area (PCA), coordinate with the Bear Management Office (307-739-3673) to ensure that all project activities comply with habitat standards in the Final Conservation Strategy for the Grizzly Bear in the Greater Yellowstone Area (USFWS 2016, http://igbconline.org/yellowstone-subcommittee/), and to the extent practicable, that projects occurring in occupied grizzly bear habitat outside of the PCA adhere to the spirit of standards in the Final Conservation Strategy (USFWS 2016).

• Conservation recommendations (CR) provided in the USFWS 2016 biological opinion on the Historic Properties Management Plan to protect minimize or avoid effects to grizzly bear::

o CR1. Minimize human interaction and potential grizzly bear mortality by continuing the Park’s hazing strategies to prevent grizzly bears from becoming habituated to human residences.

o CR2. Grizzly bears concentrate in certain areas during specific time periods to take advantage of concentrated food sources or because the area provides a high seasonal food value due to diversity in vegetation and plant phenology (e.g., important spring or fall range). Where grizzly bear use is known or likely to occur and where practicable, delay disturbing activities during the spring in spring habitats to minimize displacement of grizzly bears.

o CR3 Manage building construction/removal and other activities in a manner that will minimize noise and visual disturbances and facilitate safe movement through habitat by grizzly bears.

o CR4. Control speed, traffic, and parking to minimize negative impacts to grizzly bear activity, including active enforcement of speed limits.

http://igbconline.org/yellowstone-subcommittee/ http://igbconline.org/yellowstone-subcommittee/

• All project activities will adhere to all relevant conservation measures outlined in the Lynx Conservation Assessment and Strategy (USFWS revised 2013). In particular, harvest of trees on site for the proposed activities within Lynx Analysis Units and/or in Critical Lynx Habitat will not be authorized without further review and analysis in consultation with USFWS.

• All project activities will comply with GRTE’s Superintendent’s Compendium closures implemented around wolf den/rendezvous sites. Should a den or rendezvous site not previously known be found within 1 mile of the proposed activity a seasonal area closure would be implemented as needed, typically between 15 April and 15 August.

• Prohibit construction activities before 8 a.m. and after 6 p.m. during the elk rutting and migration period (typically from September 1 to December 1, or as recommended by the park biologists).

• Avoid construction, maintenance, or other disturbing activities in crucial ungulate winter ranges (15 December to 15 April) and in identified ungulate parturition ranges (15 May - 30 June). See mitigation reference maps.

• Fencing (including temporary fencing for construction projects and permanent fencing) used in projects will comply with wildlife friendly fencing standards. Consult with the SRM Fish and Wildlife Branch Ungulate Biologist (307-739-3488) for assistance with specifications and appropriate design.

• For all herbicide applications, to the extent possible please conform to best management practices for wildlife. This includes following MSDS label instructions and avoiding sensitive times/areas for wildlife (e.g. bird nesting, fawning, den sites, bloom periods for pollinators).

• All wildlife-vehicle collisions must be reported to Teton Interagency Dispatch as soon as possible.

• A bat mitigation plan must be developed prior to initiating preservation, maintenance, or other activities in park structures that could negatively affect bats, their roosts, or hibernacula and/or if bat sign (bat vocalizations, smell of a bat roost, bat droppings on floors or walls, bat carcasses or skeletons, oily marks (from fur) around possible access points and roost areas, lack of cobwebs along beams, feeding remains such as moth wings or other insect parts, or other sign) is observed at any site. Buildings with any of the following characteristics (largely undisturbed; large roof void; large dimension roof timbers with cracks, joints and holes; uneven roof covering with gaps; ; hanging tiles or wood cladding; setting close to woodland and/or water; early 20th century or older construction; or roof warmed by the sun) may have a high probability of being used by bats.

- It is the responsibility of the park project lead to notify park biologists proposed work activities, and to schedule surveys with enough lead time to minimize project implementation delays. If roosting bats are found in buildings, work on those structures will be delayed until after the roosting period. Qualified personnel must perform a survey within the appropriate timeframe (i.e., spring surveys for maternity roosts, summer surveys for summer roosts, winter surveys for hibernacula) prior to initiating work and, if bats are found, develop a mitigation plan.

Wildlife – Amphibians

• Care will be taken not to disturb any wildlife species (amphibians, reptiles, migratory birds, mammals, raptors, or bats) found nesting, hibernating, estivating (in an inactive dormant state during hot, dry periods), or otherwise living in, or immediately nearby, worksites.

• Prior to work in or near wetlands or waterways the area will be assessed for its importance to amphibian species and prohibitions and limitations shall be set in order to protect these species.

Wildlife – Birds

• All project activities must comply with the Migratory Bird Treaty Act of 1918 (MBTA; 16 U.S.C.

703) and Executive Oder 13186. Under the MBTA, it is illegal to "take" migratory birds, their eggs, feathers or nests. “Take” is defined (50 CFR 10.12) to include “pursuing, hunting, shooting, wounding, killing, trapping, capturing, or collecting.” The MBTA does not distinguish between “intentional” and “unintentional” take. Migratory birds include songbirds, waterfowl, shorebirds, and raptors. All project activities must also comply with GRTE’s Superintendent’s Compendium seasonal closure regulations for raptors, trumpeter swans, great blue herons, and other sensitive bird species.

o In general, park biologists recommend that to prevent impacts to nesting migratory birds and to avoid project delays, schedule work involving vegetation clearing, tree felling, fill placement, excavation, or other construction activities for outside of the nesting season. The breeding season is generally as follows for migratory songbirds (1 May to 1 August), or as dictated by nesting chronology.

o Before commencement of any activities that involve removal or manipulation of vegetation including large trees, grasses, and shrubs during the breeding season (see above) contact park biologists to schedule a survey for nesting birds. Surveys must be conducted by qualified personnel before tree removal and/or ground disturbing activities begin. To the extent possible, schedule surveys prior to 1 March the year of the proposed work.

o Inspect hazard trees for potential nest sites.

This is the start of the file's text. The full file is on GovTribe.