Atch_1_SOW_Replace_Shade_Structures.docx
DOCX document 2 MB Posted
- Attached to
- REPLACE SHADE STRUCTURES IN PICNIC AREAS
- Solicitation number
- 140P1226Q0011
About this file
This is a Scope of Work for a construction project at Chamizal National Memorial in El Paso, Texas. The project involves the demolition and replacement of 9 metal shade structures in the picnic area, with work to be completed within 60 days of the Notice to Proceed. All construction work is restricted to weekday hours between 7:00 am and 3:00 pm, with no work permitted on weekends or National Park Service holidays without prior approval. The contractor must minimize dust, fumes, and construction debris while protecting adjacent areas and maintaining compliance with environmental protection regulations. Staging areas are limited and must be located at the maintenance shop, with all areas restored to pre-construction conditions upon completion.
Each 10-foot by 10-foot shade structure requires installation of four steel posts (3" X 3" X 3/16" square tube, 12 feet long) set 24 inches deep in 4,000 psi concrete, five welded steel rafters (2" X 6" X 3/16" rectangular tube, 10 feet long), and coverage with factory-painted 26-gauge steel roofing panels featuring a pitched design for natural drainage. All structural welds must be ground and cleaned of flux before priming and painting with Behr Premium Semi-Gloss Direct-To-Metal paint per owner specifications. Roof panels are secured with self-drilling, self-sealing rubber washer screws at 24-inch spacing, and all exposed sheet metal edges require 2-1/2" galvanized steel flashing with a one-half inch downstream gap for drainage. The contractor must also repair damaged concrete pads on three existing sites and remove all waste daily. Sustainable and environmentally friendly materials are required throughout the project. The Contracting Officer is Nathan Ziegler (605-574-0480), and the Contracting Officer's Representative is Alejandro Tapia at Chamizal National Memorial (912-532-7273, Ext 119).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch_6_Questions_and_Answers_0002.docx | DOCX document | |
| Sol_140P1226Q0011_Amd_0002.pdf | ||
| Sol_140P1226Q0011_Amd_0001.pdf | ||
| Atch_5_Questions_and_Answers_0001.docx | DOCX document | |
| Sol_140P1226Q0011.pdf | ||
| Atch_2_Technical-Experience_Questionnaire.xlsx | XLSX spreadsheet | |
| Atch_4_DOL_WD_TX20260245.pdf | ||
| Atch_3_Price_Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
CONSTRUCTION
11/20/2025
Chamizal National Memorial El Paso, Texas Replace Shade Structures in Picnic Area
PMIS # 320327
NATIONAL PARK SERVICE
INTERMOUNTAIN REGION
Project Introduction
Project Name: Replace Shade Structures in Picnic Area.
Project Management Information System (PMIS) Number: 320327
Park Name and Address:
Chamizal National Memorial 800 S. San Marcial St.
El Paso, Texas 79905 Superintendent: Fernando Sanchez
1.1 Location and Facilities
This project is located in the Parking Lot at Chamizal National Memorial. The Memorial can be reached by taking the Piedras exit (20) off interstate 10. For more information see the Chamizal NM website http://www.nps.gov/cham
1.2 Short Project Description
The project consists of replacing 9 Shades Structures in Picnic Areas.
See: Detailed Project Description 4.3
0. NPS Points of Contact Contracting Officer Nathan Ziegler 1 Denver Federal Center Building 50 Denver, CO 80225 605-574-0480
Contracting Officers Representative/Facility Manager Alejandro Tapia Chamizal National Memorial 800 S. San Marcial Street El Paso, TX 79905 912-532-7273 Ext 119
2.0 PROJECT Requirements
2.1 Scope of Work and Project Summary/Requirements
The work of this project consists of replacing 9 existing shade structures in picnic areas located in the grounds at Chamizal National Memorial. All supplies and materials used should be the most sustainable and environmentally friendly products.
2.2 Minimize Construction Impacts
Minimize dust and fumes during the construction project. Protect the surrounding areas in the project area from construction debris generated from demolition.
2.3 Staging Areas
Staging is limited in or near the working area. Equipment and material storage shall be located at the maintenance shop area. All staging areas shall be returned to pre-construction conditions once construction is complete.
2.4 Construction Coordination
The Contracting Officer (CO) will provide all necessary written notification and/or direction to the contractor.
2.5 Quality Control
The quality of all work shall be the responsibility of the Contractor.
2.6 Working Hour Restrictions
All work and deliveries shall be limited to the weekday hours of 7:00 am to 3:00 pm unless otherwise approved by the Contracting Officer. No work shall occur on National Park Service holidays or weekends without prior approval. The field work will need to be completed with 60 days after the Notice to Proceed due to critical park/visitor activities. All material and equipment must be on – hand before any demolition or removal work takes place.
2.7 Hazard Control
Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.
2.8 Smoking
Smoking within buildings or temporary storage sheds is prohibited.
3 Performance Requirements
3.1 Protection
Protect any adjacent areas from debris from the repair operations. Keep dust and dirt to a minimum. Use suitable methods to limit dust and dirt from rising and scattering in air to lowest practical level. Comply with governing regulations pertaining to environmental protection. Ensure safety of persons in the work area. Provide temporary barricades as required to protect personnel and general public from injury due to selective demolition work. Provide adequate fire protection. Keep area clear of hazardous substances and debris.
4 Project Description
4.1 Existing Building and Site Description
The Visitor Center is the focal point at Chamizal National Memorial. The Visitor Center is open to the public seven days a week, Monday through Sunday from 10:00 am till 5:00 pm. A breeze way connects the Visitor Center to the Administration Building. The Administration Building is open Monday through Friday from 8:00 am till 4:30 pm.
4.2 Detailed Project Description:
The project consists of demolition and replacement of 9 total metal shade structures. The demolition will consist of disassembly and removal of existing shade structures including removal of posts anchored in the existing concrete slab. The contractor will restore any concrete slab material damaged during the demolition process, all concrete to be removed must be saw cut to allow for uniform restoration of the concrete slab, the thickness of restored concrete slab will be the same as the existing concrete slab except where post anchoring concrete shall be placed. The replacement will consist of installing 4 structure posts set inground at 24-inch depth in 4,000 psi concrete mixed per manufacturer specification, 5 rafters welded to posts and support frame, all cuts shall be clean saw cuts and joints shall be welded without perforations, ground, cleaned of welding flux and primed. The entire structural assembly of posts and grafters shall be painted per owner’s specification. Behr Premium Semi-Gloss Direct-To-Metal The structure shall be covered with 26-gauge steel roofing panels assembled to provide a 10 foot by 10-foot coverage, the roof panel support structure shall be installed with a pitch to allow for natural drainage of rainfall from the roofing panels. The material for the roofing panels shall be factory painted on both sides to prevent corrosion. The roofing panels shall be secured to the rafter structure by 3/16” X 1-1/2” self-drilling, self-sealing rubber washer screws at 24-inch spacing. A 2-1/2” steel flashing shall be installed around all exposed sheet metal edges; a one-half inch gap shall exist on the downstream side flashing to allow for rainfall drainage. Contractor will be required to repair the damaged areas on 3 of the existing concrete pads.
The contractor shall remove waste and discarded material at the end of each day.
10-foot Outdoor Shade Structure (Required per unit)
| Qty. |
| Description |
| 4 ea. |
| Steel Post, 12 Ft., 3" X 3" X 3/16" Square Tube |
| 5 ea. |
| Steel Rafter, 10 Ft., 2" X 6" X 3/16" Rectangular Tube |
| 4 ea. |
| Roof Panel, 3' X 10', 26 ga., Painted all sides |
| 40 ft. |
| Flashing, Galvanized Steel, 2- inch, white |
| 50 ea. |
| 1-1/4" X 14, Self-Drilling Screws with self-sealing rubber washer |
| 4 ea. |
| High Strength Portland Cement Mix for anchoring, 80 lb., 4,000 psi strength |