B09_-_140P1221Q0054_-_Amendment_0001_-_Questions_and_Answers_0001.pdf
PDF 84 KB Posted
- Attached to
- ABOVEGROUND FUEL STORAGE TANK PROJECT AT GRSA
- Solicitation number
- 140P1221Q0054
About this file
This document provides answers to contractor questions regarding Amendment 0001 to solicitation number 140P1221Q0054 from the Department of the Interior National Park Service Intermountain Region. The amendment clarifies that the pre-bid site visit was not mandatory. Additionally, the amendment states that if market conditions result in delayed delivery of the aboveground fuel storage tank until December, even if the contract is awarded in June, the contracting agency will work with the awardee to extend the period of performance as necessary. The solicitation is for replacement of underground fuel storage tanks with a new aboveground fuel storage tank at Great Sand Dunes National Park in Colorado.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACE UNDERGROUND FUEL STORAGE TANKS WITH ABOVEGROUND FUEL
STORAGE TANK AT THE GREAT SAND DUNES NATIONAL PARK, CO
RFQ# 140P1221Q0054
AMENDMENT 0001
PRE-BID QUESTIONS & ANSWERS
1. QUESTION: Can the Government verify that the pre-bid walk was not mandatory?
ANSWER: The pre-bid site visit was not mandatory.
2. QUESTION: The Contractor is being told that tank delivery, if contracted in June, is likely to be in December due to market conditions. Is that going to be an issue if the Contractor is not able to finish by 10/26/21?
ANSWER: If the contract is awarded in June and the lead time for delivery of the tank is not until December, then the Government would work with the awardee to extend the contract period of performance, as determined necessary.