This document is an amendment to a solicitation for a federal construction contract. The solicitation is for Phase 4, 5 and 6 of the ROMO HQ E Water Line Rehabilitation project with the Department of the Interior National Park Service Intermountain Region. The amendment provides responses to questions from offerors to clarify requirements. It specifies that an archaeology monitor is required during excavation but no other inspectors need be on site. It also clarifies that offerors are responsible for verifying underground utilities and can determine if an additional Class A or B survey is required. An attachment with a past performance survey questionnaire is included covering a period of performance from September 2020 to August 2021.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P1220R0012 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PIL

Lakewood CO 80228 12795 W Alameda Parkway NPS, IMR - Lakewood MABO

06/26/20200004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/26/2020

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to respond to questions asked and to provide a copy of the past performance survey questionnaire.

Q1. Can the most recent archaeological report of the work area be shared?

A1. No, all archaeology reports are sensitive information and we cannot release them.

Q2. Will an environmental and biological inspector be required to be onsite at all times during construction?

A2. No, and archeology monitor is required onsite during excavation, but no other inspectors will be required to be on site as the Park COR and Inspector will be insuring the environmental safety of construction.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Sherry Packard

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P1220R0012/0004

Q3. Will a SUE Class A or B survey & report be required for this project?

A3. Per specification section 017340.3.1.A it is the responsibility of the contractor to verify and locate all underground utilities prior to the start of site work. The contractor can decide if a Class A or B survey is required for this aspect of work.

Q4. Would the government consider revising evaluation criteria #2 to allow experience of staff while employed with other companies?

A4. No. Evaluation Criteria #2 Prime Contractor

Water Line Construction Qualifications evaluates the construction experience of the prime company.

All criteria will be evaluated as acceptable or unacceptable.

Q5. Could the government provide pictures of the tie-in location to each building?

A5. Photo of building 24 was provided in amendment 3. Other buildings with tie-in references to Detail E, Sheet C13 look similar.

Q6. If available, would government share pictures of trenching of previous water project here?

Q6. Photos can be found ins specification

Section 011100.1.11. These are from the previous phase.

No other changes

Attachment:

Past Performance Survey Questionnaire

Period of Performance: 09/21/2020 to 08/31/2021