About this file

These are annual inspection reports for fire protection systems at the FDO (Fairbanks Dispatch Operations) building located at 1544 Gaffney Road, Fairbanks, Alaska 99703. The inspections were conducted on August 22, 2025, for the customer BLM Alaska Fire Service. The reports document compliance with NFPA 72 (Fire Alarm System) and NFPA 25 (Sprinkler System) standards.

The Fire Alarm System Inspection Report indicates a Simplex 4100es control panel with System Status 4 (operational). The system includes 8 heat detectors, 9 smoke detectors, 12 duct detectors, 13 manual pull stations, 1 remote annunciator, 12 HVAC controls, 42 horn/strobe units, 10 strobes, and 1 horn expander—all tested and passing. The system operates on 120VAC with dedicated circuit breaker 22 in Panel sb, supplemented by a 12V18Ah sealed lead acid battery. Elevator recall devices (4 units) were not tested due to lack of fire service key. The Sprinkler System Inspection Report documents one wet system with a 4" Ready Riser, one fire pump with city water supply at 140 PSI static pressure, and identified deficiencies including missing chrome recessed escutcheons (3), missing dry head escutchion, sprinkler head spacing issues, and loaded heads throughout—all requiring corrective action. The Fire Suppression System Inspection Report covers a Kidde Aegis 2.0 total flood system protecting the BLM IT room with 3 audible devices, 2 visual devices, 2 release stations, 1 abort station, and 4 smoke detectors, all tested and passing. The system uses a Moved 1230 agent (355 lbs at 360 PSI), with hydrostatic test due and batteries recommended for replacement.

View the file

Other files for this federal contract opportunity

Other files attached to Fire Sprinkler Inspection, newest first.
File Type Posted
Sol_140L6326Q0029_Amd_0002.pdf PDF
B08_140L6326Q0029_-_Attachment_03_-_Questions_Answers_0002.pdf PDF
Sol_140L6326Q0029_Amd_0001.pdf PDF
B08_140L6326Q0029_-_Attachment_02_-_Wage_Determination_0001.pdf PDF
Sol_140L6326Q0029.pdf PDF
B08_140L6326Q0029_-_Attachment_01_-_SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building Name Date:

FDO 08/22/2025

EQUIPMENT / DEVICES

Type TOTAL STATUS TESTED COMMENT

Heat Detectors 8.0 PASS 8.0 Smoke Detectors 9.0 PASS 9.0 Duct Detectors 12.0 PASS 12.0 Manual Pull Station 13.0 PASS 13.0 Remote Annunciators 1.0 PASS 1.0 HVAC Controls 12.0 PASS 12.0 Horn/Strobe 42.0 PASS 42.0 Strobe 10.0 PASS 10.0 Horn Expander 1.0 PASS 1.0 Elevator Recall 4.0 N/A 4.0 No key for Fire service. Not tested.

Sprinkler Bell 1.0 PASS 1.0 Sprinkler Waterflow 1.0 PASS 1.0 Sprinkler Supervisory 2.0 PASS 2.0

INSPECTION DETAILS

Client Signature Technician

Print Name: Date:

08/22/2025

Panels/Batteries

BPS #: Location: Breaker Location:

Breaker

Chargin g:

Standby : Load: Battery

Size: Date:

1 Shop Sb 24 27.1 25.9 24.6 7ah 2021

Panels/Batteries Continued

BPS #: Location: Breaker Location:

Breaker

Chargin g:

Standby : Load: Battery

Size: Date:

Email

Customer Email

Other Email

Photos Image 1 Image 2

Image 3 Image 4

Image 5 Image 6

Image 7 Image 8

Image 9 Image 10

Building Name: Date:

Control Valve

# of Valves Type Easily

Accessible Signs Valve Open Secured

(Sealed?)

(Locked?)

(Supvd.?)

Supervision Operational

Alarm Line

City Conn.

2 BFV Yes No Yes Yes Supervised Yes

Pre Action

Pump Sectional System Dry

System Wet

1 BFV Yes No Yes Yes Supervised Yes

Tank

3. Water Supplies

a. Water Supply source?

City Gravity Tank Fairbanks N/A

Pressure Fire Pump & Tank Pressure Fire Pump & City Pressure Fire Pump & Pond N/A N/A N/A Waterflow Test Results Made During This Inspection Pressure Fire Pump & Pond

Test Pipe Located Size Test Pipe

Static Press.

Before

Flow Pressure

Static Press.

After

Main Drain (wet) 2.0 140 125 140

Image 3 Image 4

Image 5 Image 6

Building Name: Date:

SYSTEM DETAILS:

Occupied As: Protected Area:

BLM IT room Panel Manufacturer: Model Number:

Kidde Aegis 2.0 Software Rev. and Date: Monitoring Entity:

Fairbanks dispatch Initiating Circuits: Notification Circuits:

2 3 Signaling Line Circuits: Auxiliary Circuits:

Suppression Concept: Detection Concept:

Total flood Cross zone

SYSTEM TESTS

PRIMARY (MAIN) SUPPLY:

A/C Voltage: Dedicated Circuit:

120 Yes Breaker Location:

PNL scb sect 2 in server rm

SECONDARY (STANDBY) SUPPLY:

BATTERY VOLTAGES:

Charging: Standby: Load:

26.9 27.2 Type: Size: Date:

SLA 12v8ah Other (Specify):

Image 3 Image 4

Image 5 Image 6