This is a Questions and Answers amendment document for Request for Quotation (RFQ) 140L4026Q0009 issued by the Department of the Interior Bureau of Land Management New Mexico Region for prefabricated picnic shelters. The solicitation is set-aside for small businesses under NAICS code 332311 (Prefabricated Metal Building and Component Manufacturing), with a performance period of July 14, 2026 through December 30, 2026.

The Q&A clarifies critical contract requirements: quoters must submit only the completed price sheet and SF 1449 form without additional proposals; the procurement covers manufacturing, supply, and delivery of picnic shelters only, with assembly, installation, foundation construction, and site work explicitly excluded from contractor responsibility; the Government will handle unloading of delivered components; shelters must be pre-engineered kit buildings tailored to two specific National Conservation Area locations (NCA Joe Skeen Campground and NCA Narrows Picnic Area with provided GPS coordinates); vendors must provide sealed engineering and foundation drawings per SOW requirements; and all dimensional, structural, engineering, and material specifications in the SOW must be met, with approved equal products acceptable if meeting all stated requirements. Quoters must deliver at least five working days' notice before shipment and make deliveries during normal business hours. Quotes must be submitted to lashondra_hubbard@ios.doi.gov and remain valid for 60 calendar days from the offer due date, with award made on an all-or-none basis.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: 140L4026Q0009

Item #
Question
Answers
1
I’m pricing out these picnic shelters now. Should I just fill out the price sheet and solicitation contract or should I attach my own proposal as well?
Fill out the price sheet and solicitation.
2
Please confirm that this procurement is for the manufacture/supply and delivery of the picnic shelters only, and that installation, foundation construction, erection/assembly, and site work are not required under this contract.
This procurement solely covers the manufacturing, supply, and delivery of the picnic shelters. All responsibilities related to assembly, installation, and site work are excluded from this contract and will not be required from vendors.
3
The Statement of Work references site-specific structural design criteria. Please provide the required design wind load (mph) and design snow load (psf) applicable to this requirement, or confirm that offerors should base their quotations on the manufacturer's engineering requirements for the project location.
The Offeror must supply pre-engineered kit buildings specifically tailored for the locations outlined in the Statement of Work (SOW). These sites include the NCA Joe Skeen Campground, situated at latitude 34.943504° and longitude -107.820399°, as well as the NCA Narrows Picnic Area at latitude 34.838193° and longitude -107.912147°.
4
Please confirm that the Government will be responsible for unloading all delivered shelter components at the delivery location.
The Government will be responsible for unloading the shelter components at the delivery location. The selected Offeror must notify the Contracting Officer's Representative at least five working days prior to delivery and deliveries must be made during normal business hours as indicated in the SOW. See "Delivery Notification", "Delivery Times", "Responsibility for Delivery", and "Delivery Destination Addresses" in the SOW.
5
Please confirm whether sealed engineering drawings and foundation drawings are required with the quotation submission or will be required only after award.
See "Structural Members", items 1 & 2 in the SOW.
6
Please confirm whether approved equal products are acceptable provided they meet all stated dimensional, structural, engineering, and material requirements contained in the solicitation.
The Offeror must meet all stated dimensional, structural, engineering, and material requirements as stated in the SOW.