Questions_for_BLM__-_BLM_Answers_20220725_Sawtooth_0001.docx
DOCX document 6 MB Posted
- Attached to
- TELECOM SAFETY REPAIR SAWTOOTH GAOA
- Solicitation number
- 140L3922Q0068
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L3922Q0068_Amd_0001.pdf | ||
| A04_SOW_SAWTOOTH_Final_0001.docx | DOCX document | |
| WD_NV20220027.pdf | ||
| A06_Bid_Schedule.docx | DOCX document | |
| A04_SOW_SAWTOOTH.docx | DOCX document | |
| A06_Layout_Drawings_revised.pdf | ||
| Sol_140L3922Q0068.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) Are we able to remove part of the rock out cropping’s to get the new Pepro building to site? See pic below.
BLM Answer 7/25/22: This is not the correct location of the new radio infrastructure. See attached pictures. Install new shelter adjacent to the old BLM abandoned tower location. SOW has been updated.
2) Once new Site is commissioned can we disassembly existing shelter onsite for removal? Or does it need to be removed in 1 piece?
BLM Answer 7/25/22: Plan for removal in one piece. If BLM Radio Lead states they do not need the shelter, you may disassemble. Remove and demolish the existing foundation at least 2’ below ground elevation and fill with native material.