This document contains an amendment to a federal solicitation for the Box Elder Creek Restoration project. The amendment provides the site visit attendance records from a pre-bid site tour, as well as questions and answers received from potential offerors. The project involves instream structures and floodplain roughness features to improve aquatic habitat conditions along six reaches of Box Elder Creek managed by the Bureau of Land Management. Materials for the structures will be provided by the agency and staged near the project area. The contractor will be responsible for designing and implementing actions on a reach-by-reach basis according to the project objectives. Vehicular access is limited to designated two-track routes, though ATVs and UTVs may be used off-road with prior clearing of cultural resource areas. The amendment requires acknowledgement from offerors responding to the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_03_0003.pdf | ||
| Sol_140L3624Q0035_Amd_0003.pdf | ||
| Amendment_02_0002.pdf | ||
| Sol_140L3624Q0035_Amd_0001.pdf | ||
| Sol_140L3624Q0035.pdf | ||
| Attachment_3_-_Past_Performance_Reference_List.doc | DOC document | |
| Attachment_1-_Box_Elder_Restoration_PWS.pdf | ||
| Attachment_2_-_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L3624Q0035 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LMA
BILLINGS MT 59101
5001 SOUTHGATE DR.
BLM MT-STATE OFC(MT935)
02/28/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/28/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Please see page 2 for details on the purpose of this amendment.
Period of Performance: 07/15/2024 to 12/30/2027
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jorge Alvarez
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
PROJECT DESCRIPTION: Box Elder Creek Restoration Solicitation No. 140L3624Q0035
Description of Changes - This amendment incorporates the following information:
1. For informational purposes only, the Government is providing the Site Visit Attendance Records from the organized site visit that the Government held on 14 March 2024.
2. The Government is providing the Questions received from interested offerors and the associated Answers provided by the Government.
Acknowledgement – Ensure that your quote acknowledge this amendment. The Government must receive the acknowledgement of the amendment.
Third Party – If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.
SITE INSPECTION TOUR / PREBID CONFERENCE RECORD
The Government strongly urges offerors to inspect the site to gain a better understanding of the work requirements and to satisfy themselves regarding all general and local conditions that may affect the cost of performance. In no event shall failure to inspect the site constitute grounds for a claim after award.
Solicitation Number: 140L3624Q0035 Project Title: Box Elder Creek Restoration Date and Time: 03/14/2023 Conducted by: Bonny Richard
Attended by:
Name Company
Andie Reeves Olympus Technical Frankie Frielich Anabranch Solutions
Questions and Answers
Question: Are these reaches similar to lower Box Elder where the hardpan clay layer is only 1-3 feet below the surface?
Answer: Potentially. The upper layer is a mix of fine clay with patches of cobble/gravel. Periodically throughout the project reaches, I have seen the “bedrock” clay layer at the surface so there is potential to hit it during installation of structures.
Question: Will there be active livestock grazing?
Answer: It is probable that livestock will be present depending on when and where the contractor is working.
Question: What type of building material will BLM be providing?
Answer: The material will be conifer and staged just off the main two tracks in approximately the locations indicated in the Appendix maps. Most of the material will be pine and juniper though there may be some Douglas-fir. Some material prepping will be necessary as the material will vary from branches to whole 3-6” diameter trees. Wood posts will also be provided. These will be sharpened for easier installation.
On-site harvesting of sagebrush and woodies (cottonwood/willows) is not authorized.
Question: Are there existing beaver dams within the project?
Answer: No, not as of last summer anyway. The last one I knew of was blown out two years ago.
However, beavers are present within the system.
Question: Will there be any headcut structures or floodplain structures? Or will everything be in-channel?
Answer: No there aren’t currently any known headcut structures, though that may change. There are several floodplain roughness structures for areas that are threatened by meander cut-offs. Overall, though, most of the structures will be in-channel. They will be mix of a few BDAs but mostly PALS – including channel-spanning PALS.
The PWS states that the contractor will design and implement actions on a reach-by-reach basis based on the reach objective to ensure that the selected treatments account for the unique, site-specific characteristics, but work together to cumulatively produce the desired outcomes. The structures listed on the maps are an example of minimum numbers and general types suggested. The Appendix provides some structural density ranges to help with anticipated workload estimates.
Question: Is cross-country travel allowed?
Answer: Trucks will not be allowed off two-track routes. However, use of UTVs and ATVs with small trailers are allowed off the designated two-tracks. There are a few areas with cultural resources, and these will be mapped and marked ahead of time so the contractor can find easy routes around them. All routes (two track and suggested off road access routes) shown on the maps in the bid package have been cleared by the Archeologist already. In most places, accessing up and down the channel within 40 feet of the stream bank will be cleared and not impact the cultural sites.
The contractor is not authorized to implement the project prior to July 15th each year due to sage grouse habitat restrictions.
Question: What is the anticipated size of channel-spanning structures?
Answer: The channel width varies. Generally speaking, Reaches 1-3 average 8-15 feet across. Reaches 4- 6 tend to be wider and average 15-25 feet. However, each structure site is different and may change depending on spring flood flows.
Question: How are you providing enough material and what happens if we use up the material?
Answer: One of the requirements in the PWS is for the contractor to provide BLM with a plan of when and what structures/reaches they planned to complete that season. This information must be provided in the spring, so BLM has time to stage material. BLM’s material volumes will be based off of that information.
Question: Can we have a site visit of Reaches 1 and 2?
Answer: Due to the road conditions, we are not able to get into Reaches 1-2 today. However, channel dimensions/conditions are similar to the site we visited in Reach 3.