Questions_and_Answers_0001.docx

DOCX document 19 KB Posted

Attached to
YELLOWCREEK RANGE LEAD REMEDIATION
Solicitation number
140L3422Q0022
Issued by

View the file

Other files

File Type Posted
B09_Questions_and_Answers__2_0002.docx DOCX document
Sol_140L3422Q0022_Amd_0002.pdf PDF
Sol_140L3422Q0022_Amd_0001.pdf PDF
A04_Schedule_of_Items_0001.docx DOCX document
A04_Statement_of_Work_-_Revised_0001.docx DOCX document
Past_Performance_Questionnaire.doc DOC document
A04_Map_2_of_2_-_Project.pdf PDF
Sol_140L3422Q0022.pdf PDF
A04_Statement_of_Work.docx DOCX document
B03_SCA_Wage_Determination.pdf PDF
A04_Map_1_of_2_-_Vicinity.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YELLOW CREEK REMEDIATION

140L3422Q0022

QUESTIONS AND ANSWERS

Q1: Will the BLM provide measurements for the length of berms and square feet of topsoil that needs to be removed?

A.1:

· From firing line to 100 yard berm is approximately 34,500 (300'x100' and 45'x100') square feet of 2" topsoil removal.

· In front of 200 yard berm is approximately 3,600 square feet (180'x20') of 2" topsoil removal.

· In front of 300 yard berm is approximately 900 square feet (30'x30') of 2" topsoil removal.

· 100 yard berm length: 80'

· 200 yard berm length: 180'

· 300 yard berm length: 30'

Q2:If the BLM estimate is off, how will the contractor be paid for any extra material treated?
A2:The BLM estimate was developed through on-site measurements. The specified quantities in the Statement of Work are believed to be an accurate estimate of what is to be treated. There is a 15% Variation of Quantity that allows for some flexibility in the amount of material completed. Any additional quantities above the estimated amount in the Statement of Work must be pre-approved by the Contracting Officer. A Schedule of Items with quantities for quoting has been included in the amendment
Q3:Will the range be closed while project is taking place?
A3:The range will be closed and signed by the BLM from the time equipment is on site to the time the project is completed.
Q4:What percent of lead should be removed and how will we verify it?
A4:All lead fragments above 3/16" will need to be removed from the specified material. Statement of work has been amended to include this information
Q5:Are we looking at just screening for lead or are we looking for a soil treatment as well?
A5:The contract was written to remove as much lead as possible through mechanical screening of the material from the shooting lane, target locations and berms. Treatment beyond mechanical to remove all traces of lead will not be needed due to the areas continued use as a shooting range. All lead fragments larger than 3/16" of an inch need to be removed and recycled.
Q6:Where do the stockpiles of treated material need to be placed?
A6:The location of the stockpile will be determined by the contractor. The material will be moved by the BLM after this contract is completed.
Q7:Is there any though to a proposed method for how the screening of lead that needs to be conducted? Or is that open to the contractors?
A7:The BLM is requiring for all lead fragments 3/16" and larger to be removed from the material and taken off site. It is up to the contractor how the work is accomplished to meet the requirements.