GAOA_ABA_AT_BIG_SAND_BAY_AND_GREYS_LANDING_SPECIFICATIONS.pdf
PDF 662 KB Posted
- Attached to
- GAOA - ABA at Big Sand and Grey's Landing
- Solicitation number
- 140L2624Q0047
About this file
This document is the specifications for the Architectural Barriers Act (ABA) project at Big Sand Bay and Grey's Landing in Twin Falls County, Idaho.
The project consists of the following work:
- At Big Sand Bay, remove the concrete around the existing toilet and place a new ABA compliant parking pad and sidewalk. Slope and armor the back and sides of the toilet with riprap. Seed all disturbed areas.
- At Grey's Landing, remove the existing parking pad and place a new ABA compliant pad and sidewalk. Seed all disturbed areas.
The work will be completed under a single prime contract. The contract includes bid items for mobilization, earthwork, riprap, concrete, and pavement markings. Unit prices will be used for measurable items, with lump sum pricing for other activities. The contractor is responsible for providing temporary facilities, environmental controls, and safety measures during construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APRIL 2024 TABLE OF CONTENTS
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 1
TABLE OF CONTENTS
SPECIFICATIONS
DIVISION 01 – GENERAL REQUIREMENTS
011000 – SUMMARY
012200 – UNIT PRICES AND SCHEDULE OF VALUES
013100 – PROJECT MANAGEMENT AND COORDINATION
013200 – CONSTRUCTION PROGRESS DOCUMENTATION
013300 – SUBMITTAL PROCEDURES
014000 – QUALITY REQUIREMENTS
015000 – TEMPORARY FACILITIES AND CONTROLS
016000 – PRODUCT REQUIREMENTS
017300 – EXECUTION REQUIREMENTS
017700 – CLOSEOUT PROCEDURES
017839 – PROJECT RECORD DOCUMENTS
DIVISION 03 – CONCRETE
033000 – CAST–IN–PLACE CONCRETE
DIVISION 31 – EARTHWORK
311000 - SITE CLEARING
312000 - EARTH MOVING
312250 - RIPRAP
DIVISION 32 – EXTERIOR IMPROVEMENTS
321723 – PAVEMENT MARKINGS
END OF SECTION
APRIL 2024 SUMMARY
GAOA ABA AT BIG SAND BAY AND GREYS LANDING 011000-1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Use of premises.
3. Specification formats and conventions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identifications: Big Sand Bay, Grey’s Landing.
1. Project Locations:
a. Big Sand Bay 42.11902, -114.73658, Twin Falls County, Idaho.
b. Grey’s Landing 42.13078, -114.72570, Twin Falls County, Idaho.
B. The Work consists of the following:
1. Big Sand Bay: Remove concrete around toilet and place new ABA compliant parking pad and sidewalk. Slope and armor with riprap at back and sides of the toilet. Seed all disturbed areas as directed by the CO.
2. Grey’s Landing: Remove existing parking pad and place an ABA compliant pad and sidewalk.
Seed all disturbed areas as directed by the CO.
C. Project will be constructed under a single prime contract.
1.3 USE OF PREMISES
A. Contractor shall have full use of premises for construction operations during construction period.
Contractor's use of premises is limited only by Government right to perform work or to retain other contractors on portions of work.
B. Schedule operations so that Work is conducted during regular office hours which are 7:00 a.m. to 5:00 p.m.
C. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.
D. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING 011000-2
1. Site toilet and work area will be closed to the public during the duration of the construction project. Access to the reservoir must be maintained for the public.
2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.4 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 16-division format and CSI/CSC's "MasterFormat" numbering system.
1. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
C. Terminology: In Divisions 2 through 33 specification sections, all references to “Owner” have been replaced with the term “Government” or “Contracting Officer” (when referring to the person acting for the Government). All references to “Architect” have been replaced with the term “Contracting Officer”.
D. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the work of all Sections in the Specifications.
E. Contract Times: “Days” referred to in the Specifications are defined as calendar days.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING 011000-3
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
APRIL 2024 UNIT PRICES AND SCHEDULE OF VALUES
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 012200-1
SECTION 012200 - UNIT PRICES AND SCHEDULE OF VALUES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for unit prices and requirements to prepare schedule of values.
1.2 DEFINITIONS
A. Unit price is a price per unit of measurement for materials or services added to or deducted from the Contract Sum by appropriate modification, if estimated quantities of Work required by the Contract Documents are increased or decreased.
1.3 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Government reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government expense, by an independent surveyor acceptable to Contractor.
C. List of Unit Prices: A list of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.
1.4 SCHEDULE OF VALUES (Not Required)
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LUMP SUM PAYMENT ITEMS
A. Payment items for the work of this Contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below.
B. Lump Sum items are inclusive of all materials, labor, parts, assembly, and installation in order to produce a functional product. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum payment item, shall be included in the listed lump sum item most closely associated with the work involved.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 012200-2
C. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
3.2 UNIT PRICE PAYMENT ITEMS
A. Payment items for the work of this Contract for which unit price payments will be made are listed in the BIDDING SCHEDULE and described below.
B. Unit price items are inclusive of all materials, labor, parts, assembly, and installation in order to produce a unit of the product. All costs for items of work, which are not specifically mentioned to be included in a particular unit price payment item, shall be included in the listed unit price item most closely associated with the work involved.
C. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
D. Quantities regarding unit prices shall be assumed to follow the quantities listed in the bid schedule. If the Contractor suspects a change in the unit quantities, measurement can be made to adjust the final quantity of an item. If the quantity of an item cannot be measured at final condition the contractor shall produce construction documentation collected during construction to demonstrate the quantity.
3.3 SUMMARY OF BID ITEMS
A. The intent of the following paragraphs is to explain, in general, what is and what is not included in a bid item, and the limits or cut-off points where one bid item ends, and another begins. If no bid item exists for a portion of the work, include the costs in a related bid item.
B. BID ITEM 1 - MOBILIZATION AND CONSTRUCTION MANAGEMENT: This item includes all preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies, and incidentals to the project site; bonds, work layout; other work and operations which must be performed, or costs incurred prior to beginning work on the various items on the project site. Construction management includes ongoing tasks such as environmental controls, temporary facilities and controls, temporary traffic control, and field office operations. Item also includes preparation and installation of erosion control measures and features. It will be paid for as a lump sum.
C. BID ITEM 2 – EARTHWORK: This item includes labor and equipment to clear the areas identified on the plans for construction, excavation of soil materials to subgrade elevations, placement and compaction of subbase materials, and placement and compaction of base course materials in accordance with the plans. Item includes transport locally for disposal of
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 012200-3
unsuitable material and stockpiling material as directed by the Government. Includes backfill, site reclaiming, and seeding of all disturbed areas. Item will be paid for as a lump sum.
D. BID ITEM 3 – RIPRAP: Item includes furnishing and placing riprap for erosion control at back and sides of Big Sand Bay toilet as shown on plans. Geotextile under riprap is also included.
Item includes all materials, equipment, and labor necessary for installation. Installation shall be as directed by the Government and shown on the plans. Item will be paid for as a lump sum.
E. BID ITEM 4 – CONCRETE: This item includes labor, materials, and equipment to install concrete pad and sidewalks in accordance with the plans. This item also includes two (2) ABA Accessible Parking Signs installed in concrete pad. Item will be paid for as a lump sum.
F. BID ITEM 5 – PAVEMENT MARKINGS: This item includes providing all labor, materials, and equipment necessary to install pavement markings per the plans. Item will be paid for as a lump sum.
END OF SECTION 012200
APRIL 2024 PROJECT MANAGEMENT AND COORDINATION
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013100-1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Coordination Drawings.
2. Project meetings.
3. Requests for Interpretation (RFIs).
B. See Division 1 Section "Execution Requirements" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
1.2 DEFINITIONS
A. RFI: Request from Contractor seeking interpretation or clarification of the Contract Documents.
1.3 COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Contracting Officer and separate contractors if coordination of their Work is required.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013100-2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, and civil systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches.
3. Number of Copies: Submit one electronic copy of each submittal. Contracting Officer will return one electronic copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Sections.
1.5 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Contracting Officer of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Contracting Officer, within three days of the meeting.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013100-3
B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Contracting Officer, but no later than 15 days after execution of the Contract. Hold the conference at Project site or another convenient location.
Conduct the meeting to review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified preconstruction submittals.
1. Attendees: Authorized representatives of Government, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Procedures for processing field decisions and Modifications.
f. Procedures for RFIs.
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. Preparation of Record Documents.
l. Use of the premises.
m. Work restrictions.
n. Government occupancy requirements.
o. Responsibility for temporary facilities and controls.
p. Construction waste management and recycling.
q. Parking availability.
r. Office, work, and storage areas.
s. Equipment deliveries and priorities.
t. First aid.
u. Security.
v. Progress cleaning.
w. Working hours.
3. Minutes: Record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. The Contract Documents.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013100-4
b. Options.
c. Related RFIs.
d. Related Modifications.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Possible conflicts.
i. Compatibility problems.
j. Time schedules.
k. Weather limitations.
l. Manufacturer's written recommendations.
m. Warranty requirements.
n. Compatibility of materials.
o. Acceptability of substrates.
p. Temporary facilities and controls.
q. Space and access limitations.
r. Regulations of authorities having jurisdiction.
s. Testing and inspecting requirements.
t. Installation procedures.
u. Coordination with other work.
v. Required performance results.
w. Protection of adjacent work.
x. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Not required for this contract due to short project duration.
1.6 REQUESTS FOR INTERPRETATION (RFIs)
A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.
1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:
1. Project name.
2. Date.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013100-5
3. Name of Contractor.
4. Name of Contracting Officer.
5. RFI number, numbered sequentially.
6. Specification Section number and title and related paragraphs, as appropriate.
7. Drawing number and detail references, as appropriate.
8. Field dimensions and conditions, as appropriate.
9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
10. Contractor's signature.
11. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop
Drawings, and other information necessary to fully describe items needing interpretation.
C. Contracting Officer's Action: Contracting Officer will review each RFI, determine action required, and return it. Allow 14 calendar days for Contracting Officer's response for each RFI.
RFIs received after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for coordination information already indicated in the Contract
Documents.
d. Requests for adjustments in the Contract Time or the Contract Sum.
e. Requests for interpretation of Contracting Officer's actions on submittals.
f. Incomplete RFIs or RFIs with numerous errors.
2. Contracting Officer's action may include a request for additional information, in which case Contracting Officer's time for response will start again.
D. On receipt of Contracting Officer's action immediately distribute the RFI response to affected parties. Review response and notify Contracting Officer within seven days if Contractor disagrees with response.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013100
APRIL 2024 CONSTRUCTION PROGRESS DOCUMENTATION
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013200-1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Daily construction reports.
3. Field condition reports.
B. See Division 1 Section "Unit Prices and Schedule of Values" for submitting the Schedule of Values.
1.2 SUBMITTALS
A. Contractor's Construction Schedule: Submit one electronic copy of initial schedule, large enough to show entire schedule for entire construction period.
B. Daily Construction Reports: Create one electronic copy on days that government official is not on site, submitted weekly.
C. Field Condition Reports: Submit one electronic copy at time of discovery of differing conditions.
1.3 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.4 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013200-2
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Modification.
B. Activities: Treat each separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Contracting Officer.
2. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule.
Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.
4. Substantial Completion: Indicate completion in advance of date established for Substantial Completion and allow time for Contracting Officer's administrative procedures necessary for certification of Substantial Completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule and show how the sequence of the Work is affected.
1. Work Restrictions: Show the effect of the following items on the schedule:
a. Seasonal variations.
b. Environmental control.
2. Work Stages: Indicate important stages of construction for each major portion of the Work.
D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion.
E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
1.5 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Submit a comprehensive, fully developed Contractor's Construction Schedule within 15 days of date established for the Notice to Proceed. Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project.
B. Preparation: Indicate each significant construction activity separately.
1. For construction activities that require 3 months or longer to complete, indicate an estimated monthly completion percentage.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013200-3
1.6 REPORTS
A. Daily Construction Reports: Prepare a daily construction report on days that a government official is not on site. Record the following information:
1. Report number, Project title and number.
2. Date and day of week.
3. Weather conditions, including high and low temperatures, and site conditions.
4. List of subcontractors at Project site.
5. Equipment at Project site and work observed.
6. Material deliveries.
7. Accidents.
8. Stoppages, delays, shortages, and losses.
9. Equipment or system tests and startups.
B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Actual Completion percentage for each activity.
B. Distribution: Distribute copies of approved schedule to Contracting Officer, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
END OF SECTION 013200
APRIL 2024 SUBMITTAL PROCEDURES
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-1
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Design Computations, and other submittals.
B. See Division 1 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule.
C. See Division 1 Section "Quality Requirements" for submitting test and inspection reports.
D. See Division 1 Section "Closeout Procedures" for submitting warranties.
E. See Division 1 Section "Project Record Documents" for submitting Record Specifications, and Record Product Data.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Officer's responsive action.
B. Informational Submittals: Written information that does not require Contracting Officer's responsive action. Submittals may be rejected for not complying with requirements.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittals Schedule: Comply with requirements in Division 1 Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities.
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's receipt of submittal. No
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-2
extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.
D. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 6 by 8 inches on label or beside title block to record
Contractor's review and approval markings and action taken by Contracting Officer.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of COR.
d. Name and address of Contractor.
e. Name and address of subcontractor.
f. Name and address of supplier.
g. Name of manufacturer.
h. Submittal number or other unique identifier, including revision identifier.
1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 06100.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 06100.01.A). Work schedule and value schedules shall be numbers
01000.01 and 01000.02.
i. Number and title of appropriate Specification Section.
j. Drawing number and detail references, as appropriate.
k. Location(s) where product is to be installed, as appropriate.
l. Other necessary identification.
E. Cover Sheet:
1. Ensure that cover sheet includes following information:
a. Submittal Number.
b. Contract Number.
c. Specification section number and title, paragraph, and complete description of item being submitted. Be specific and clearly identify what is being submitted. When appropriate, reference a specific sheet and detail of the Drawings. Note multiple items individually.
d. Signature and date.
e. Name and telephone number of individual to contact for further information, if other than Contractor.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-3
2. Submitted Information: Link submittal to cover sheet by contract number, project name, and submittal number. Stamp is recommended, but may be hand-written on each copy;
ensure submittal stamp includes project name and contract number and blank space in which to write submittal number. Stamp or write this information on all copies.
F. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals.
G. Additional Copies: Unless additional copies are required for final submittal, and unless Contracting Officer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
H. Transmittal: Package each submittal individually and appropriately for transmittal and handling.
Contracting Officer will return submittals, without review received from sources other than Contractor.
I. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked "APPROVED."
J. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
K. Use for Construction: Use only final submittals with mark indicating "APPROVED" taken by Contracting Officer.
1.4 CONTRACTOR'S USE OF GOVERNMENT’S CAD FILES
A. At Contractor's written request, copies of Government’s CAD files will be provided to Contractor for Contractor's use in connection with Project.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. Prepare and submit Action Submittals required by individual Specification Sections.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-4
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Printed performance curves.
f. Operational range diagrams.
g. Compliance with specified referenced standards.
h. Testing by recognized testing agency.
4. Number of Copies: Submit one electronic copy of Product Data, unless otherwise indicated. Contracting Officer will return one copy. Mark up and retain returned copy as a Project Record Document.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Shopwork manufacturing instructions.
f. Templates and patterns.
g. Schedules.
h. Notation of coordination requirements.
i. Notation of dimensions established by field measurement.
j. Relationship to adjoining construction clearly indicated.
k. Seal and signature of professional engineer if specified.
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 22 by 34 inches.
3. Number of Copies: Submit one electronic copy of each submittal. Contracting Officer will return one copy.
D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Lot.
e. Style.
f. Color.
g. Locations of use.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-5
h. Number and title of appropriate Specification Section.
3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. Color selections will be made only after all related color samples have been received.
a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Contracting Officer will return submittal with options selected.
5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit one set of Samples. Contracting Officer will retain Sample set.
E. Product Schedule or List: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.
1. Number of Copies: Submit one copy of product schedule or list, unless otherwise indicated. Contracting Officer will return one copy.
F. Submittals Schedule: Comply with requirements specified in Division 1 Section "Construction Progress Documentation."
G. Schedule of Values: Comply with requirements specified in Division 1 Section "Unit Prices and Schedule of Values."
H. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design.
1. Number of Copies: Submit one electronic copy of subcontractor list, unless otherwise indicated.
2.2 INFORMATIONAL SUBMITTALS
A. Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit one electronic copy of each submittal, unless otherwise indicated. Contracting Officer will not return copies.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-6
2. Certificates and Certifications: Provide notarized statement that includes signature of entity responsible for preparing certification, signed by officer or other individual authorized to sign documents on behalf of that entity. State that the named product conforms to the Contract requirements. Submit certificate with a certified copy of test results, or certify that such test results are on file with the manufacturer and will be furnished to Contracting Officer upon request. Provide name and address of manufacturer, testing agency, and date of tests. The certificate shall set forth the means of identification which will permit field determination of the product delivered as being the product covered by the certification.
3. Test and Inspection Reports: Comply with requirements specified in Division 1 Section "Quality Requirements."
B. Coordination Drawings: Comply with requirements specified in Division 1 Section "Project Management and Coordination."
C. Contractor's Construction Schedule: Comply with requirements specified in Division 1 Section "Construction Progress Documentation."
D. Conformance Certificates: Prepare written certification that material complies with Contract Documents. Include evidence prior to sampling and testing.
E. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.
F. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
G. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
H. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
I. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
J. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
K. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-7
L. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
M. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
N. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
O. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements specified in Division 1 Section "Operation and Maintenance Data."
P. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.
Include list of assumptions and other performance and design criteria and a summary of loads.
Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
Q. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
R. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include the following, as applicable:
1. Statement on condition of substrates and their acceptability for installation of product.
2. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.
3. Results of operational and other tests and a statement of whether observed performance complies with requirements.
S. Insurance Certificates and Bonds: Prepare written information indicating current status of insurance or bonding coverage. Include name of entity covered by insurance or bond, limits of coverage, amounts of deductibles, if any, and term of the coverage.
2.3 DELEGATED DESIGN
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Contracting Officer.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-8
B. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit one copy of a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.
1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Contracting Officer.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
3.2 CONTRACTING OFFICER'S ACTION
A. General: Contracting Officer will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Action Submittals: Contracting Officer will review each submittal, make marks to indicate corrections or modifications required, and return it. Contracting Officer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:
1. APPROVED: Where submittals are marked “Approved”, that part of the Work covered by the submittal may proceed provided it complies with requirements of the Contract Documents; final acceptance will depend upon that compliance. Approval or comments do not relieve Contractor for compliance with the Contract Documents, field verification of dimensions and responsibility for means, methods, work coordination and safety.
2. APPROVED, SUBJECT TO COMPLIANCE WITH ATTACHED COMMENTS: Where submittals are marked “Approved, Subject to Compliance with Attached Comments”, that part of the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Document;
final acceptance will depend upon that compliance.
3. NOT APPROVED: Where submittals are marked “Not Approved”, do not proceed with that part of the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal in accordance with the notations; resubmit without delay. Repeat if necessary to obtain a different action mark.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 013300-9
C. Informational Submittals: Contracting Officer will review each submittal and will not return it, or will return it if it does not comply with requirements. Contracting Officer will forward each submittal to appropriate party.
D. Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review.
E. Submittals not required by the Contract Documents may not be reviewed and may be discarded.
F. Written approval of submittals is indication that Contractor's submittals have been reviewed for general conformance to Contract Documents and there are no objections, except as noted.
G. Installation of material on basis of written approval of submittals shall not relieve Contractor of responsibility for incorporating material that conforms to requirements of Contract Documents.
H. Written approval of deviations shall apply only to those deviations or omissions from the requirements of Contract Documents brought to Contracting Officer's attention in writing.
I. After written approval of an item, Contractor may submit substitution for approval, if approved item cannot be purchased or delivered in time to avoid delay…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .