This document appears to be Section 024116 - Structure Demolition from a specification for a federal contract opportunity. The scope includes the removal of concrete pads and sidewalks at Big Sand Bay and Greys Landing locations. The work must comply with relevant regulatory requirements and standards. Key execution details include protecting existing site infrastructure, conducting demolition to minimize disruption, and disposing of demolition waste at an EPA-approved facility. The related federal contract opportunity is solicitation 140L2624Q0047 for GAOA - Architectural Barriers Act (ABA) work at the Big Sand Bay and Greys Landing sites, issued by the Department of the Interior Bureau of Land Management Idaho Region.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APRIL 2024 STRUCTURE DEMOLITION
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 024116-1
SECTION 024116 - STRUCTURE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Removal of concrete pads and sidewalks
1.2 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.3 PREINSTALLATION MEETINGS
A. Pre-demolition Conference: Conduct conference at Project site.
1.4 FIELD CONDITIONS
A. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.
2.2 SOIL MATERIALS
A. Satisfactory Soils: Comply with requirements in Section 312000 "Earth Moving."
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 024116-2
PART 3 - EXECUTION
3.1 PROTECTION
A. Temporary Protection: Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction and as indicated.
Comply with requirements in Section 015000 "Temporary Facilities and Controls."
1. Protect existing site improvements, appurtenances, and landscaping to remain.
2. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
3. Provide protection to ensure safe passage of people around building demolition area and to and from occupied portions of adjacent structures.
B. Remove temporary barriers and protections where hazards no longer exist. Where open excavations or other hazardous conditions remain, leave temporary barriers and protections in place.
3.2 DEMOLITION
A. General: Demolish indicated structures completely. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Do not use cutting torches until work area is cleared of flammable materials. Maintain portable fire-suppression devices during flame-cutting operations.
2. Maintain fire watch during and for at least 1 hour after flame-cutting operations.
B. Site Access and Temporary Controls: Conduct structure demolition and debris-removal operations to ensure minimum interference with roads, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct streets, walkways, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed trafficways if required by authorities having jurisdiction.
2. Use water mist and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.
C. Explosives: Use of explosives is not permitted.
D. Promptly repair damage to adjacent buildings caused by demolition operations.
E. Backfill after vault removal and grade to existing contours at Backwaters site.
3.3 CLEANING
A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.
GAOA ABA AT BIG SAND BAY AND GREYS LANDING. 024116-3
B. Clean adjacent structures and improvements of dust, dirt, and debris caused by demolition operations. Return adjacent areas to condition existing before demolition operations began.
END OF SECTION 024116