B11_140L1726Q0040_Q_A_0001.pdf

PDF 13 KB Posted

Attached to
BLM-NM TFO SCLRA FLOATING COURTESY DOCK REPLACEMEN
Solicitation number
140L1726Q0040
Issued by

About this file

This is a Questions and Answers (Q&A) document for federal contract opportunity 140L1726Q0040. The document addresses a single inquiry regarding the removal of an existing dock at the project site. According to the response provided by the Bureau of Land Management (BLM), BLM staff will be responsible for removing the existing dock, meaning contractors need not include dock removal in their proposals or cost estimates. This clarification indicates that site preparation related to dock removal is outside the scope of work for responding contractors.

View the file

Other files

File Type Posted
B11_140L1726Q0040_Q_A_4_0004.pdf PDF
Sol_140L1726Q0040_Amd_0004.pdf PDF
B11_140L1726Q0040_Q_A_3_0003.pdf PDF
Sol_140L1726Q0040_Amd_0003.pdf PDF
B11_140L1726Q0040_Q_A_2_0002.pdf PDF
Sol_140L1726Q0040_Amd_0002.pdf PDF
Sol_140L1726Q0040_Amd_0001.pdf PDF
A04_BID_FORM_SCLRA_COURTESY_DOCK.pdf PDF
Sol_140L1726Q0040.pdf PDF
A04_SOW_SCLRA_COURTESY_DOCK.pdf PDF
B03_WD_2015-5449.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140L1726Q0040 Q&A 1

1. Is there any information on removing the existing dock?

Q.

A.

1. BLM staff will be removing the existing dock.