B12_140L1725Q0021_-_Q_A_2_0002.pdf

PDF 53 KB Posted

Attached to
BLM-CO L07 CABANA INSTALL
Solicitation number
140L1725Q0021
Issued by

About this file

This document is a Questions and Answers (Q&A) file for Solicitation Number 140L1725Q0021, a Bureau of Land Management (BLM) project for Cabana Installation in Colorado. The Q&A addresses key details about the project's scope and requirements, including contractor responsibilities for purchasing a Cabana from Shadesun.com and clarifying installation specifics. The contractor will be responsible for installing the Cabana according to manufacturer's directions, including dirt work and compacted aggregate base, with no concrete floor or picnic tables included in the project.

The solicitation is a small business set-aside for NAICS code 238990, with award based on price and other factors such as technical approach, past government experience, and project history. Vendors must submit a technical narrative, equipment and construction schedule, references demonstrating government and BLM Colorado experience, project details, and company expertise. Proposals must be emailed to the Contracting Specialist Patrick Frost by the closing date, with specific documentation requirements including completion of the 889 form and SAM registration.

View the file

Other files

File Type Posted
A06_UPDATED_Drawings_0002.zip ZIP file
A06_UPDATED_Specs_0002.zip ZIP file
Sol_140L1725Q0021_Amd_0002.pdf PDF
Sol_140L1725Q0021_Amd_0001.pdf PDF
B12_140L1725Q0021_-_Q_A_0001.pdf PDF
Sol_140L1725Q0021.pdf PDF
A04_Schedule_of_items.pdf PDF
B03_Wage_Determination.pdf PDF
A06_Specificaions.pdf PDF
A06_Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140L1725Q0021 - BLM-CO WRFO Cabana Install

Q: We (the contractor) are responsible for purchasing and providing the Cabana from Shadesun.com, correct?

A: Yes

Q: The schedule of Items only has the Cabana listed. Is that all you need on there?

The scope of work is going to require, but not limited to, concrete, rebar, ancillary hardware, and (I thought I read about concrete picnic tables – but I can’t seem to find them on the paperwork right now); these don’t need to be included on the schedule of items?

A: There are no picnic tables, just the cabana and the items required install in accordance with the manufacturer’s directions and the drawings. As well as the dirt work and aggregate that goes around the base.

Q: The drawings show a concrete floor under the Cabana and section 01009 says it will be compressed aggregate, please clarify.

A: The floor will be compacted aggregate. Updated drawings and specs will be included in the attachments.