B12_140L1725Q0021_-_Q_A_2_0002.pdf
PDF 53 KB Posted
- Attached to
- BLM-CO L07 CABANA INSTALL
- Solicitation number
- 140L1725Q0021
About this file
This document is a Questions and Answers (Q&A) file for Solicitation Number 140L1725Q0021, a Bureau of Land Management (BLM) project for Cabana Installation in Colorado. The Q&A addresses key details about the project's scope and requirements, including contractor responsibilities for purchasing a Cabana from Shadesun.com and clarifying installation specifics. The contractor will be responsible for installing the Cabana according to manufacturer's directions, including dirt work and compacted aggregate base, with no concrete floor or picnic tables included in the project.
The solicitation is a small business set-aside for NAICS code 238990, with award based on price and other factors such as technical approach, past government experience, and project history. Vendors must submit a technical narrative, equipment and construction schedule, references demonstrating government and BLM Colorado experience, project details, and company expertise. Proposals must be emailed to the Contracting Specialist Patrick Frost by the closing date, with specific documentation requirements including completion of the 889 form and SAM registration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A06_UPDATED_Drawings_0002.zip | ZIP file | |
| A06_UPDATED_Specs_0002.zip | ZIP file | |
| Sol_140L1725Q0021_Amd_0002.pdf | ||
| Sol_140L1725Q0021_Amd_0001.pdf | ||
| B12_140L1725Q0021_-_Q_A_0001.pdf | ||
| Sol_140L1725Q0021.pdf | ||
| A04_Schedule_of_items.pdf | ||
| B03_Wage_Determination.pdf | ||
| A06_Specificaions.pdf | ||
| A06_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140L1725Q0021 - BLM-CO WRFO Cabana Install
Q: We (the contractor) are responsible for purchasing and providing the Cabana from Shadesun.com, correct?
A: Yes
Q: The schedule of Items only has the Cabana listed. Is that all you need on there?
The scope of work is going to require, but not limited to, concrete, rebar, ancillary hardware, and (I thought I read about concrete picnic tables – but I can’t seem to find them on the paperwork right now); these don’t need to be included on the schedule of items?
A: There are no picnic tables, just the cabana and the items required install in accordance with the manufacturer’s directions and the drawings. As well as the dirt work and aggregate that goes around the base.
Q: The drawings show a concrete floor under the Cabana and section 01009 says it will be compressed aggregate, please clarify.
A: The floor will be compacted aggregate. Updated drawings and specs will be included in the attachments.