At10_BidSchedule_AM01_0001.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- GARNET HILL RECREATION AREA CONSTRUCTION Federal contract opportunity
- Solicitation number
- 140L0626B0006
About this file
This is a Bid Schedule for solicitation 140L0626B0006, issued by the Department of the Interior Bureau of Land Management for Garnet Hill Recreation Area Construction improvements. The schedule presents a tiered pricing structure with a base contract and five optional line items, all priced on a lump-sum (LS) basis.
The base contract consists of three trailhead improvements: Egan Crest Trailhead, Lackawanna Road Trailhead, and Keystone Junction Trailhead. The optional work includes Garnet Hill Main Trailhead, Upper Campground, Lower Campground, and two segments of Pole Line Road improvements (beginning to 97+50 and 97+50 to end). All line item amounts are fully burdened and include overhead, profit, and bond costs, with final amounts rounded to the nearest dollar. The bid schedule requires bidders to provide unit costs and calculate total amounts for each line item, with separate subtotals for base and options work, cumulative total pricing, and declarations of overhead, profit, and bond rates used in the pricing calculations.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule
BID SCHEDULE
140L0626B0006 Garnet Hill Recreation Area Improvements
| Quantity | Unit | Cost / Unit | Amount* | |||
| BASE | ||||||
| 01 | EGAN CREST TRAILHEAD | 1 | LS | $ | ||
| 02 | LACKAWANNA ROAD TRAILHEAD | 1 | LS | $ | ||
| 03 | KEYSTONE JUNCTION TRAILHEAD | 1 | LS | $ | ||
| Base Total |
| OPTIONS | ||||
| 01 | GARNET HILL MAIN TRAILHEAD | 1 | LS | $ |
02 UPPER CAMPGROUND 1 LS $
03 LOWER CAMPGROUND 1 LS $
04 POLE LINE ROAD IMPROVEMENTS BEGINNING TO 97+50 1 LS $
| 05 | POLE LINE ROAD IMPROVEMENTS 97+50 TO END | 1 | LS | $ |
| Options Total | ||||
| Total (Base + Options) |
| RATE ** | ||
| Overhead | % | |
| Profit | % | |
| Bond | % |
| *Amount for each item is fully burdened (includes Overhead, Profit, and Bond). All line items and total amounts rounded to nearest dollar. |
| **Overhead, Profit, and Bond rates used to be provided. |
File details come from the government source that posted it. Updated .