This is a 100% Design Documents specification manual for the Garnet Hill Recreation Area Title I and Title II Pole Line Road project located in Ely, Nevada, under BLM Contract No. 140L0621D0006, Task Order No. 140L0624F0117. The project involves widening an approximately 3.1-mile access road from US 50 to the Garnet Hill Trailhead from 10-14 feet to a minimum of 20 feet to accommodate two lanes of traffic, improving drainage to mitigate seasonal washouts and flooding through riprap ditches, Arizona-crossings, and retaining walls. Additional work includes removal of three limestone rock outcroppings in the first half-mile, construction of a 10-15 vehicle parking area near the NDOT right-of-way, and development of Lower and Upper Garnet Hill Campgrounds and trailhead facilities along the route.
The specifications establish comprehensive administrative and procedural requirements for contract execution, including detailed provisions for project management and coordination through web-based software platforms (Corecon Technologies, Meridian Systems/Prolog, Newforma, Procore, or Viewpoint); construction schedules using Critical Path Method (CPM) networks; submittal procedures with 14-calendar-day review periods; quality assurance and control plans; testing and inspection agency requirements; temporary facilities, stormwater pollution control, and construction waste management. The contract requires a preconstruction conference within 15 days of agreement execution, weekly progress meetings, daily construction reports, and compliance with ASTM testing standards. Work shall occur during normal business hours of 5:00 a.m. to 6:00 p.m., Monday through Friday, with utility notification requirements and environmental coordination through a designated on-site Environmental Manager with minimum three years of construction experience on similar projects.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. BUREAU OF LAND MANAGEMENT
GARNET HILL RECREATION AREA
TITLE I AND TITLE II
Pole Line Road
ELY, NEVADA
CONTRACT NO. 140L0621D0006 TASK ORDER NO. 140L0624F0117
100% DESIGN DOCUMENTS
Project Manual Volume 1
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
January 7, 2026
Garnet Hill Recreation Area Design Documents 1
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 07 SEALS PAGE
BLM PROJECT NO. 140L0621D0006
CONTRIBUTING AUTHORS FOR SPECIFICATIONS
CIVIL ENGINEERING
Daniel Kelley S&B Christ NV # 21134 Consulting
12 Jan 2026
Design Documents 2
SECTION 00 01 10
TABLE OF CONTENTS
DIVISION SECTION TITLE
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 07 SEALS PAGE
00 01 15 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 SUMMARY
01 25 00 SUBSTITUTION PROCEDURES
01 31 00 PROJECT MANAGEMENT AND COORDINATION
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 23 TEMPORARY STORMWATER POLLUTION CONTROL
01 73 00 EXECUTION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 77 00 CLOSEOUT PROCEDURES
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 39 PROJECT RECORD DOCUMENTS
01 79 00 DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS
02 41 19 SELECTIVE DEMOLITION
DIVISION 03 - CONCRETE
03 20 00 CONCRETE REINFORCEMENT
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 31 - EARTHWORK
31 10 00 SITE CLEARING
31 20 00 EARTH MOVING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 20 AGGREGATE BASE
32 13 13 CONCRETE PAVING
32 15 00 AGGREGATE SURFACING
- - - END - - -
Design Documents 3
SECTIONS 00 01 15 LIST OF DRAWINGS
1. GARNET HILL
1.1 GENERAL SHEETS
A G-001 – COVERSHEET
B G-002 – LEGEND ABBREVEATION
1.2 TOPOGRAPHIC SHEET
A V-001 – TOPOGRAPHIC SURVEY – 01
B V-002 – TOPOGRAPHIC SURVEY – 02
1.3 CIVIL SHEETS
A C-100 - GENERAL SHEETS
B 1CS-101 - LACKAWANNA SITE PLAN
C 1CG-101 - LACKAWANNA GRADING PLAN
D 2CR-101 - EGAN CREST DEMOLITION PLAN
E 2CS-101 - EGAN CREST SITE PLAN
F 2CG-101 - EGAN CREST GRADING PLAN
G 3CR-101 - KEYSTONE DEMOLITION PLAN
H 3C-101 - KEYSTONE SITE PLAN
I 3CG-101 - KEYSTONE GRADING PLAN
J 4CR-101 - LOWER CAMPGROUND DEMOLITION PLAN
K 4CS-101 - LOWER CAMPGROUND SITE PLAN
L 4CG-101 - LOWER CAMPGROUND GRADING PLAN
M 4CG-102 - LOWER CAMPGROUND GRADING PLAN
N 5CR-101 - UPPER CAMPGROUND DEMOLITION PLAN
O 5CS-101 - UPPER CAMPGROUND SITE PLAN
P 5CG-101 - UPPER CAMPGROUND GRADING PLAN
Q 5CG-102 - UPPER CAMPGROUND GRADING PLAN
R 6CR-101 - MAIN TRAIL DEMOLITION PLAN
S 6CS-101 - MAIN TRAIL SITE PLAN
T 6CG-101 - MAIN TRAIL GRADING PLAN 1
U 6CG-102 - MAIN TRAIL GRADING PLAN 2
V 5CG-103 - MAIN TRAIL GRADING SECTIONS
W 7CP-101 – POLE LINE ROAD PLAN & PROFILE
X 7CP-102 – POLE LINE ROAD PLAN & PROFILE
Y 7CP-103 – POLE LINE ROAD PLAN & PROFILE
Z 7CP-104 – POLE LINE ROAD PLAN & PROFILE
AA 7CP-105 – POLE LINE ROAD PLAN & PROFILE
BB 7CP-106 – POLE LINE ROAD PLAN & PROFILE
CC 7CP-107 – POLE LINE ROAD PLAN & PROFILE
DD 7CP-108 – POLE LINE ROAD PLAN & PROFILE
EE 7CP-109 – POLE LINE ROAD PLAN & PROFILE
FF 7CP-110 – POLE LINE ROAD PLAN & PROFILE
GG 7CP-111 – POLE LINE ROAD PLAN & PROFILE
HH 7CP-112 – POLE LINE ROAD PLAN & PROFILE
II 7CP-113 – POLE LINE ROAD PLAN & PROFILE
Design Documents 4
JJ 7CP-114 – POLE LINE ROAD PLAN & PROFILE
KK 7CP-115 – POLE LINE ROAD PLAN & PROFILE
LL 7CP-116 – POLE LINE ROAD PLAN & PROFILE
MM 7CP-117 – POLE LINE ROAD PLAN & PROFILE
NN 7CP-118 – POLE LINE ROAD PLAN & PROFILE
OO CD-501 – CIVIL DETAILS
PP CD-502 – CIVIL DETAILS
QQ CD-503 – CIVIL DETAILS
RR CD-504 – CIVIL DETAILS
SS CD-505 – CIVIL DETAILS
Design Documents 5
THIS PAGE INTENTIONALLY LEFT BLANK
DESIGN DOCUMENTS
SUMMARY
SECTION 01 10 00 - 1
SECTION 01 10 00
SUMMARY
PART 1 GENERAL
1.01 SUMMARY
A. Project information.
B. Work covered by Contract Documents.
C. Use of premises.
D. Work restrictions.
E. Specification formats and conventions.
1.02 PROJECT
A. Project Name: Garnet Hill Recreation Area
1. Project Location: Pole Line Road, Ely, Nevada 89139.
B. Web-Base Project Software: Project software administered by Contractor will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 - Project Management and Coordination for requirements for using web-based Project software.
1.03 CONTRACT DESCRIPTION
A. Contract Type: A single prime contract based on a Stipulated Price as described in Document 00 52 00 - Agreement Form.
1.04 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work consists of the following:
1. The project Garnet Hill Access Road begins at US 50 just after the Ruth turnoff. It is approximately 3.1 miles long winding through a series of switchbacks up to the Garnet Hill Trailhead facilities. Along the route are the Lower and the Upper Garnet Hill Campgrounds. The access road itself is between 10 and 14 feet wide in various places with unimproved shallow ditches running down each side of the single lane dirt road.
2. The intended improvements are to widen the road to a minimum of 20-feet to accommodate 2 lanes of traffic, to improve the drainage to mitigate seasonal washouts of the road and temporary flooding. Typical hydraulic tools for this include possible riprap ditches or other means of energy dissipation for higher flows and Arizona-crossings at low points of reoccurring flooding like at the approach from US 50. Further considerations are riprap slopes at potential riling or sloughing slopes on the route up the road in the steeper drop offs.
3. Proposed improvements also include a small 10-15 vehicle parking area at the edge of NDOT right of way at the beginning edge of the access road with signage as close to the turnout as allowable. Overhead power and underground fiber markings were observed in this area. In the first half mile of the road in the first curve up the canyon, three sizable limestone rock outcroppings were observed that limited access road width. An additional geotechnical investigation was performed to determine acceptable methods of outcropping removal to allow for widening efforts. These outcroppings will likely need to be removed and retaining walls will be added to provide hillside stability.
4. Widening this road will require a significant amount of fill to widen the road, as efforts will look to minimize cutting into the mountainside as much as practical to maintain site stability. Final drainage improvements may include placement of riprap protection and Arizona-crossings (concrete).
5. Additional improvements include the construction of campgrounds and trailheads along the access road per the design documents.
SUMMARY
SECTION 01 10 00 - 2
1.05 USE OF PREMISES
A. Contractor shall have limited use of premises for construction operations as indicated on Drawings by the Contract limits. Government will provide on-site areas for temporary facilities, contractor parking and storage of materials as well as the immediate work area for construction.
B. Schedule and sequence operations necessary to complete the work, including coordination with other crafts relative to the Contractor's requirements. Schedule Work in such manner as to avoid delays in overall construction and permit proper installation of work.
C. Limit use of premises to areas within the Contract limits and as allowed by the COR. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Government Occupancy: Allow for Government occupancy and operations at Project site.
Government personnel will be continuously occupying areas adjacent to the work area.
Conduct work in a manner that will minimize needs for disruption of normal Government operations. Provide minimum 72 hours advance notice to COR of activities that will impact normal Government operations. Secure COR's written approval of activities that will impact normal Government operations to avoid delays in overall construction and permit proper installation or work.
2. Driveways and Entrances: Keep driveways, parking and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials unless coordinated with the COR.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.06 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 5:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.
1. Work Hours outside normal business hours may be allowed as coordinated with the COR.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer/COR. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements shall be displayed on the construction site or within the premises unless approved by the COR.
D. Existing Utilities
1. Existing Utilities: Notify COR and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
E. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify COR not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without COR's written permission.
F. Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
SUMMARY
SECTION 01 10 00 - 3
1.07 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the CSI/CSC's "Masterformat" numbering system.
1. Division 01 – General Requirements: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate.
Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
C. Terminology: All references to “Owner, Architect or Engineer” shall be replaced with the term “Government”.
END OF SECTION 01 10 00
BLM Garnet Hill SUBSTITUTION PROCEDURES
SECTION 01 25 00 - 1
SECTION 01 25 00 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
1.03 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to Contractor or Owner.
1.04 PROCEDURES
A. Approval: Submit substitutions clearly indicating them as such for government approval.
B. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01 25 00
BLM Garnet Hill PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - 1
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions.
2. Informational submittals.
3. Coordination procedures.
4. Coordination drawings.
5. Project meetings.
6. Requests for Interpretation (RFIs).
7. Digital project management procedures.
8. Environmental coordination.
9. Permits.
1.02 DEFINITIONS
A. Request for Interpretation (RFI): Request from Contractor seeking interpretation or clarification of the Contract Documents.
1.03 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
1.04 COORDINATION PROCEDURES
A. Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for COR and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Startup and adjustment and commissioning of systems.
8. Project closeout activities.
1.05 COORDINATION DRAWINGS
SECTION 01 31 00 - 2
A. Coordination Drawings: Prepare Coordination Drawings according to requirements in individual Sections and where installation is not completely indicated on the Shop drawings, where limited space availability necessitates coordination, or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to COR for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
B. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
3. Contracting Officer Representative (COR) will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings prepared by Engineer for use in preparing coordination digital data files.
a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
1.06 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify COR of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements. Distribute the meeting minutes to everyone concerned, including COR, within three days of the meeting.
B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Contracting Officer, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or other convenient location.
Conduct the meeting to review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified preconstruction submittals.
1. Attendees: Authorized representatives of Government, Engineer, and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. The mechanical and electrical subcontractor’s attendance will be required.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Critical work sequencing and long-lead items.
SECTION 01 31 00 - 3
c. Designation of key personnel and their duties.
d. Procedures for processing field decisions and Modifications.
e. Procedures for RFIs.
f. Procedures for testing and inspecting.
g. Procedures for processing Applications for Payment.
h. Distribution of the Contract Documents.
i. Submittal procedures.
j. Sustainability requirements.
k. Preparation of Record Documents.
l. Use of the premises.
m. Work restrictions.
n. Government occupancy requirements.
o. Responsibility for temporary facilities and controls.
p. Construction waste management and recycling.
q. Parking availability, office, work, and storage areas.
r. Equipment deliveries and priorities.
s. First aid.
t. Security.
u. Progress cleaning.
v. Working hours.
3. Minutes: Record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise COR of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs and Related Modifications.
d. Purchases, Deliveries, Submittals.
e. Review of mockups.
f. Possible conflicts and/or Compatibility problems.
g. Time schedules and Weather limitations.
h. Manufacturer's written recommendations.
i. Warranty requirements.
j. Acceptability of substrates.
k. Space and access limitations.
l. Regulations of authorities having jurisdiction.
m. Testing and inspecting requirements.
n. Installation procedures.
o. Coordination with other work.
p. Required performance results.
q. Protection of adjacent work.
r. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
SECTION 01 31 00 - 4
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Conduct progress meetings at weekly intervals. Hold the meetings at the project site and provide a virtual attendance option. Coordinate dates of meetings with preparation of payment requests. Additional progress meetings may be requested by either the COR or Contractor.
1. Attendees: In addition to representatives of Government, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review items of significance that could affect progress. Include as appropriate:
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
13) Status of correction of deficient items.
14) Field observations.
15) RFIs.
16) Status of proposal requests.
17) Pending changes.
18) Status of Modifications.
19) Pending claims and disputes.
20) Documentation of information for payment requests.
c. Reporting: Record the meeting minutes. Distribute minutes of the meeting to each party present and to parties who should have been present.
d. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
DI. Sustainable Design Requirements Coordination Conference: If required, the COR will schedule and conduct a sustainable design coordination conference before starting construction, at a time convenient to COR, Engineer, and Contractor.
1. Attendees: Authorized representatives of Government, Engineer, and their consultants;
Contractor and its superintendent and sustainable design coordinator; major subcontractors; suppliers; and other concerned parties shall attend the conference.
Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
SECTION 01 31 00 - 5
2. Agenda: Discuss items of significance that could affect meeting sustainable design requirements, including the following:
a. Sustainable design Project checklist.
b. General requirements for sustainable design-related procurement and documentation.
c. Project closeout requirements and sustainable design certification procedures.
d. Role and identity of sustainable design coordinator.
e. Construction waste management.
f. Construction operations and sustainable design requirements and restrictions.
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
1.07 REQUESTS FOR INTERPRETATION (RFIS)
A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.
1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:
1. Project name.
2. Date.
3. Name of Contractor.
4. Name of Contracting Officer
5. RFI number, numbered sequentially.
6. Specification Section number and title and related paragraphs, as appropriate.
7. Drawing number and detail references, as appropriate.
8. Field dimensions and conditions, as appropriate.
9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
10. Contractor's signature.
11. Requested date for response.
12. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop Drawings, and other information necessary to fully describe items needing interpretation.
Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFIs: Provided by Contracting Officer
1. Identify each page of attachments with the RFI number and sequential page number.
D. Contracting Officer's Action: Contracting Officer will review each RFI, determine action required, and return it. Allow fifteen calendar days for Contracting Officer's response for each RFI. RFIs received after 1:00p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor’s means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Contracting Officer's actions on submittals.
g. Incomplete RFIs or RFIs with numerous errors.
2. Contracting Officer's action may include a request for additional information, in which case Contracting Officer's time for response will start again.
SECTION 01 31 00 - 6
E. On receipt of Contracting Officer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Contracting Officer within seven days if Contractor disagrees with response.
F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log weekly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Contracting Officer.
4. RFI number including RFIs that were dropped and not submitted.
5. RFI description.
6. Date the RFI was submitted.
7. Date Contracting Officer's response was received.
8. Identification of related bilateral or unilateral modifications, extensions, and changes in scope, as appropriate.
1.08 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Use of Architect's Digital Data Files: Digital data files of Engineer’s CAD drawings will be provided by Engineer for Contractor's use during construction.
1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project record Drawings.
2. Engineer makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.
3. Digital Drawing Software Program: Drawings are available in Civil 3D 2025.
B. Web-Based Project Software: Provide, administer, and use web-based Project software site for purposes of hosting and managing Project communication and documentation until Final Completion.
1. Web-based Project software site includes, at a minimum, the following features:
a. Compilation of Project data, including Contractor, subcontractors, Engineer, engineer's consultants, Government/Contracting Officer, and other entities involved in Project.
Include names of individuals and contact information.
b. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents.
c. Document workflow planning, allowing customization of workflow between project entities.
d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, and Modifications.
e. Track status of each Project communication in real time, and log time and date when responses are provided.
f. Procedures for handling PDFs or similar file formats, allowing markups by each entity.
Provide security features to lock markups against changes once submitted.
g. Creating and distributing meeting minutes.
h. Document management for Drawings, Specifications, and coordination drawings, including revision control.
i. Management of construction progress photographs.
j. Mobile device compatibility, including smartphones and tablets.
2. Provide up to four web-based Project software user licenses for use of Government, Engineer, and Engineer's consultants.
3. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to COR. Provide data in locked format to prevent further changes.
4. Provide the following web-based Project software packages under their current published licensing agreements:
a. Corecon Technologies, Inc.
SECTION 01 31 00 - 7
b. Meridian Systems; Prolog.
c. Newforma, Inc.
d. Procore Technologies, Inc.
e. Viewpoint, Inc.; Viewpoint for Project Collaboration.
f. Approved similar package
C. PDF Document Preparation: PDFs are required to be submitted and shall be prepared as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
1.09 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Ensure compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implement the Waste Management Plan (WMP).
c. Implement the Indoor Air Quality (IAQ) Management Plan.
d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
e. Provide training for Contractor personnel in accordance with their position requirements.
f. Monitor and document environmental procedures.
B. Perform project quality control in accordance with specified requirements including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Indoor Air Quality (IAQ) Management.
4. Noise & Acoustics Management.
5. Temporary Storm Water Pollution Management.
6. Construction Waste Management.
7. Green Building Rating Programs: Submit evidence of familiarity with Sustainable design requirements.
8. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of COR.
C. Green Building Rating Program Documentation:
1. When required, prepare and submit documentation required to demonstrate compliance with Sustainability Requirements. Respond to requests for answers to questions and other information from COR.
2. Evaluate progress toward goals, including green building rating and other goals.
Coordinate work as necessary to meet the goals.
D. Provide documentation for environmental procedures as specified herein.
1.10 PERMITS
A. General:
SECTION 01 31 00 - 8
1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore, the Contractor will comply with the appropriate Federal, State and local laws.
B. Coordinate with local utility agencies as required for all new connections.
C. Coordination with Agencies with Jurisdiction for Utility Connections: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.
PART 2 - PRODUCTS (NOT USED)
END OF SECTION 01 31 00
BLM Garnet Hill CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 01 32 00 - 1
SECTION 01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Submittals Schedule.
3. Daily construction reports.
4. Field condition reports.
1.02 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Float: The measure of leeway in starting and completing an activity.
E. Major Area: A story of construction, a separate building, or a similar significant construction element.
1.03 SUBMITTALS
A. Submittals Schedule: Submit electronic (pdf) copy of schedule. Arrange the following information in a tabular format:
1. Scheduled date for first submittal.
2. Specification Section number and title.
3. Submittal category (action or informational).
4. Name of subcontractor.
5. Description of the Work covered.
6. Scheduled date for Contracting Officer's final release or approval.
B. Preliminary Network Diagram: Submit electronic (pdf) copy, large enough to show entire network for entire construction period. Show logic ties for activities.
C. Contractor's Construction Schedule: Submit electronic (pdf) copy of initial schedule, large enough to show entire schedule for entire construction period.
D. CPM Reports: Concurrent with CPM schedule, submit electronic (pdf) copy of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
E. Daily Construction Reports: Submit electronic (pdf) copy at weekly intervals.
F. Field Condition Reports: Submit electronic (pdf) copy at time of discovery of differing conditions.
SECTION 01 32 00 - 2
1.04 COORDINATION
A. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.05 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.
2. Submit concurrently with the first complete submittal of Contractor's Construction Schedule.
1.06 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule unless specifically authorized by Modification.
B. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule.
2. Submittal Review Time: Include review and resubmittal times.
3. Startup and Testing Time: Include required startup and testing times.
4. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Contracting Officer's administrative procedures necessary for certification of Substantial Completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule and show how the sequence of the Work is affected.
D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion.
E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis to demonstrate the effect of the proposed change on the overall project schedule.
F. Contractor's Construction Schedule Updating: At a minimum of monthly intervals, and at any major occurrence impacting schedule, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
G. Distribution: Distribute copies of approved schedule to COR, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1.07 CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)
A. General: Prepare network diagrams using AON (activity-on-node) format.
B. Preliminary Network Diagram: Submit diagram within 14 days of date established for the Notice of Award. Outline significant construction activities for the first 60 days of construction. Include skeleton diagram for the remainder of the Work.
SECTION 01 32 00 - 3
C. CPM Schedule: Prepare Contractor's Construction Schedule using a computerized time-scaled CPM network analysis diagram for the Work.
1. Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for use no later than 30 days after date established for the Notice to Proceed.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of COR's approval of the schedule.
2. Establish procedures for monitoring and updating CPM schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
3. Use "one workday" as the unit of time. Include list of nonworking days and holidays incorporated into the schedule.
CI. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated time duration, sequence requirements, and relationship of each activity in relation to other activities. Include estimated time frames for the following activities:
a. Preparation and processing of submittals.
b. Mobilization and demobilization.
c. Purchase and delivery of materials.
d. Fabrication.
e. Utility interruptions.
f. Installation.
g. Inspections and approvals.
h. Testing and any required commissioning.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. Format: Mark the critical path. Locate the critical path near center of network; locate paths with most float near the edges.
a. Subnetworks on separate sheets are permissible for activities clearly off the critical path.
CII. Initial Issue of Schedule: Prepare initial network diagram from a list of straight "early start-total float" sort. Identify critical activities. Prepare tabulated reports showing the following:
1. Contractor or subcontractor and the Work or activity.
2. Description and Principal events of activity.
3. Immediately preceding and succeeding activities.
4. Early and late start and finish dates.
5. Total float or slack time.
CIII. Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:
1. Identification of activities that have changed.
2. Changes in early and late start and finish dates.
3. Changes in activity durations in workdays.
4. Changes in the critical path.
5. Changes in total float or slack time.
6. Changes in the Contract Time.
1.08 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
SECTION 01 32 00 - 4
1. List of subcontractors at Project site.
2. Equipment at Project site.
3. Material deliveries.
4. High and low temperatures and general weather conditions.
5. Accidents.
6. Stoppages, delays, shortages, and losses.
7. Meter readings and similar recordings.
8. Orders and requests of authorities having jurisdiction.
9. Services connected and disconnected.
10. Equipment or system tests and startups.
11. Photographs
B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
PART 2 - PRODUCTS (NOT USED)
END OF SECTION 01 32 00
BLM Garnet Hill SUBMITTAL PROCEDURES
SECTION 01 33 00 - 1
SECTION 01 33 00 - SUBMITTAL PROCEDURES
PART 1 – GENERAL
1.01 SUMMARY
A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Design Computations, and other submittals.
B. RELATED SECTIONS– related sections include submittal requirements for those sections.
1. 01 31 00 - Project Management and Coordination
2. 01 32 00 - Construction Progress Documentation
3. 01 40 00 - Quality Requirements
4. 01 77 00 - Closeout Procedures
5. 01 78 23 - Operation and Maintenance Data
6. 01 78 39 - Project Record Documents
7. 01 79 00 - Demonstration and Training for submitting video of demonstration of equipment and training of Government personnel.
1.02 DEFINITIONS
A. Action Submittals: Information that requires COR's responsive action.
B. Informational Submittals: Information that does not require COR's responsive action.
Submittals may be rejected for not complying with requirements.
1.03 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently. COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittals Schedule: Comply with requirements in Section "Construction Progress Documentation" for list of submittals and time requirements.
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on COR's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. COR will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.
D. Submittals Labelling:
1. Label each submittal for identification; include name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately on label or beside title block to record Contractor's review and approval markings and action taken by COR.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor and subcontractor.
d. Name of firm or entity that prepared submittal.
e. Name and address of supplier and manufacturer.
SECTION 01 33 00 - 2
f. Submittal number or other unique identifier, including revision identifier.
g. Number and title of appropriate Specification Section.
h. Drawing number and detail references, as appropriate.
i. Location(s) where product is to be installed, as appropriate.
j. Other necessary identification.
E. Cover Sheet: Use Cover Sheet to transmit Submittal.
1. Ensure that cover sheet includes following information:
a. Submittal Number
b. Contract Number
c. Specification section number and title, paragraph, and complete description of item being submitted. Be specific and clearly identify what is being submitted. When appropriate, reference a specific sheet and detail of the Drawings. Note multiple items individually.
d. Signature and date.
e. Name and telephone number of individual to contact for further information, if other than Contractor.
F. Mechanical and Electrical: Deliver catalogs or pages and tables for mechanical and electrical items in one complete mechanical package and one complete electrical package. Incomplete packages will be retained until all items are received. Shop drawings may be submitted separately. Submit the following additional data:
1. Rough-in data and dimensions.
2. Motor characteristics and wiring diagrams.
3. Performance curves and rated capacities.
4. Operation characteristics.
G. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals.
H. Approved Equals:
1. For each item proposed as an “or approved equal,” submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation,…