GAOA TETON DAM RECONSTRUCTION Federal contract opportunity
Solicitation number
140L0625R0013
Issued by
Department of the Interior Bureau of Land Management National Office

View the file

Other files for this federal contract opportunity

Other files attached to GAOA TETON DAM RECONSTRUCTION, newest first.
File Type Posted
Sol_140L0625R0013_Amd_0004.pdf PDF
Att11_TetonDam_InspRpt_0004.pdf PDF
Sol_140L0625R0013_Amd_0003.pdf PDF
Sol_140L0625R0013_Amd_0002.pdf PDF
Sol_140L0625R0013_Amd_0001.pdf PDF
Att9_TetonDam_SiteVisit_Roster_0001.pdf PDF
Att5_Lim_on_SubK_Breakout.xlsx XLSX spreadsheet
Sol_140L0625R0013.pdf PDF
Att8_25R0013_RFI_Form.xlsx XLSX spreadsheet
Att7_Past_Perf_Questionnaire.docx DOCX document
Att3_WY20250037_20250103.pdf PDF
Att1_Drawings_10022024.pdf PDF
Att2_Specifications_102024.pdf PDF
Att4_Price_Breakout.pdf PDF
Att6_Experience_ProjectDataSheet.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information

Solicitation:

Title:

Company:

Name:

Email:

Inquiry number

Solicitation /

Drawing / Spec /

Other

Section/ Sheet/

Page Question Government Response

1 Drawings

Can AutoCAD files be provided to aid in bidding the project to help verify quantities and help with developing the means and methods for construction?

CAD files will not be provided for bidding purposes.

Quantities shown in the bidding documents are based on

CAD surfaces and should be all inclusive.

2 Solicitation FAR 52.229-3 I want to verify that the project is taxable?

The purchase of construction materials or supplies by a contractor is not usually tax exempt unless there is a state or local law that provides otherwise. It is the responsibility of the contractor to know the sales tax rules of each state where the purchases are made to claim tax exemption, if applicable.

3 Specification

02300-3.06 &

03300-3.11

I want to verify that the CONTRACTOR will be responsible for QC testing and the GOVERNMENT will perform the QA testing?

Contractor is responsible for all testing necessary during production and placement to ensure specifications are achieved; see specification : SECTION 02300 EARTH

DAM; 3.06 QUALITY CONTROL. Government testing will be for the sole purpose of verification and acceptance of placed material; see specification : SECTION 02300

EARTH DAM; 3.07 QUALITY ASSURANCE.

4 Other

Can water from the existing reservoir be used for moisture conditioning embankment material if it is available?

Reservoir water is okay for moisture conditioning for other materials, but not for the use of wetting the filter and drain materials per: SECTION 02300

BLM EARTH DAM; E Filter Sand and Drain Gravel;

Thoroughly wet filter-drain material during placement and compaction. Clean, potable water from a source approved by the

GOVERNMENT is to be used to wet filter zones to avoid contamination from clay fines.

5 Other

Will there be livestock within the construction easement during time of construction where temporary fencing is going to be needed?

The site is currently fenced for the purpose of excluding livestock. Contractor is responsible to verify existing fences will exclude livestock and provide necessary fencing to meet specification section : SECTION 01010

SUMMARY OF WORK; 1.07 LIVESTOCK.

6 Other

Are any CONTRACTOR furnished offices/facilities for GOVERNMENT use required as part of the contract? If so, what are the size and capability requirements for these items?

no; SECTION 01010 SUMMARY OF WORK; 1.08

CONTRACTOR FIELD OFFICES AND SHEDS

7 Solicitation

Can the Governement clarify whether the bid will be submitted electronically to Contracting Officer or hand delivered to the BLM Office in Denver?

The proposal shall be submitted electronically to the

Government points of contact listed in G-4 of the solicitation.

8 Specification 02600-1.03

Is the contractor required to have the coffer dam designed and stamped by a professional engineer or just provide a working drawing for review?

no a PE stamp is not required. Provide working drawing through the submittal process.

9 Solicitation

Would the GOVERNMENT entertain postponing the proposal deadline by a week to account for the Fourth of July Holiday?

The proposal due date has been extended by amendment.

10 Solicitation

Could you please confirm the amount for the liquidated damages?

No Liquidated Damages for this project.

140L0625R0013

Teton Dam Reconstruction GAOA WY

11 Spec 2600-1.04

States the reservoir cannot be drawin down below

7005. Does that mean its not possible or not allowed.

The requirement in Specification section 02600;1.04-3 stating "The CONTRACTOR cannot draw down the reservoir below elevation 7005 ft." will be removed.

12 spec 2300 -3.07

Is the Govt performing compaction testing and laboratory testing of the compacted embankment. Is the contractor rquired to perform compaction testing of the compacted backfill. Is the contractor responseable for the proctors and lab testing of Lime fill and compacted backfill materials.

Contractor is responsible for all testing necessary during production and placement to ensure specifications are achieved; see specification : SECTION 02300 EARTH

DAM; 3.06 QUALITY CONTROL. Government testing will be for the sole purpose of verification and acceptance of placed material; see specification : SECTION 02300

EARTH DAM; 3.07 QUALITY ASSURANCE.

13 drawing C1

Drawing c1 shows the borrow and waste area, 20-25 K of borrow fill total could be needed. The borrow site is

1/3 of the area needed. Are any additional borrow sites located.

Based on the size of the designated borrow area and the volume of embankment excavation that will be reused, the shown area should provide enough borrow material.

The shown borrow area can be extended if necessary during construction.

14 drawing C1

Drawing C1 Shows the limits of disturbance and staging area. Is additional space available for Topsoil stockpile, 65 K soil stockpile, Lime amendment area, Aggregate Stockpile Areas. 10-12 acres will be needed minimum. Additional stockpiling areas can be approved as needed.

15 drawing C1

Can Rip Rap and Sand Stockpiles be placed along the access road before reaching the staging area. Additional stockpiling areas can be approved as needed.

Solicitation 4 Is the first name of the Contracting Specialist Ian or

Max?

Ian (Max) Petersen. The Contract Specialist prefers to go by Max. Caution the email address is ipetersen@blm.gov.

SF 1442 1

Will the government consider a 1-2 week extension to the bid date, without an extension of the RFI date, to allow for adjustments based on RFI responses?

The question due and proposal due date have been extended by amendment. The question period has closed.

1060 1.01 9

Please provide all government permits noted in

Specification 01060 1.01 prior to the bid date.

Permits will not be provided by the GOV during the biding process.

1010 1.01 4 Specification 01010 1.01 1 states work included is

“Dewater Reservoir and construction area”. Please confirm the entire reservoir is not to be dewatered.

Correct, dewatering should only include what is necessary for construction and shall consider requirements in the specifications including depths and minimum reservoir elevations that must be maintained.

2240 1.03 34

Specification 02240 1.03 C.1. Lower water table within areas of excavation to a minimum of two feet below the bottom of excavations to facilitate Work being completed on dry and stable subgrade. Please confirm measurable definitions of dry and stable.

Dry and stable conditions shall be defined as soils that can be recompacted to a non-yielding state in accordance with compaction and proof rolling requirements.

2240 3.04A 37

Specification 02240 3.04A. Operate the dewatering system continuously until the construction of foundation elements is complete. Please specify an elevation or specific element this is referring to since

“foundation elements” are not called out anywhere on the plan set.

Foundation elements refer to the bottoms of structures and the bottom of the embankment.

1010 1.01 4

Can the contractor rely on the government provided borrow to meet the specification requirements? If there is not enough government furnished borrow, will there be an adjustment to the contract to make up the shortfall?

There should be adequate on-site borrow materials available, however some on-site processing such as screening, sorting, or blending may be required.

Geotech Data Report 119 What was the reservoir’s water elevation at the time of the Geotechnical Report borehole drilling program?

Water elevation at the time of survey (same general timeframe as the geotechnical investigation) was 7012.3' as shown on Sheet C2.

Geotech Data Report 122

In the Geotechnical report, there is reference to this document: Dam Safety Inspection Report: Teton Dam, 2016. Please provide. Report will be provided.

2300 2.02 40

Spec 02300 2.02 Compacted Embankment. Note C states excavated soil from the spillway it not acceptable for use as compacted embankment. Where does the contractor place that material and what measures should be made to the stockpile?

This material shall be placed in the waste disposal area shown on Sheet C1. Wasted earthen materials are to be graded so that the site can be restored.

2300 2.03 46 Can excavated soil from the spillway be used to blend the lime for the Lime Amended Embankment? If not, does all of the quantity come from the government provided borrow source?

Lime amended soils must meet the requirements of

Section 02300, 2.02. Material may come from the borrow source or excavated embankment provided it meets the specification.

3300 94 Grouted Rip Rap. Besides the properties in Table

03300A – Mix Table, are there any other specifications for the grout to be used for the Grouted Rip Rap? No

2300 2.02 46

Is there enough borrow quantity provided by government to complete the entirety of the embankment operations? How much quantity should contractors expect to import for CLIN 6 Compacted

Embankment? Imported embankment material is not anticipated.

1150 Item 17 16

Clin 17 Salvage and Replace Existing Rock. Can the existing rip rap be re-used? Is so, how much quantity is available for re-use? Does this existing rip rap meet the rip rap specifications? If not, where does the contractor place non-useable rip rap?

As shown on Sheet C2, the intent is to remove and reuse all of the existing upstream rip rap.

2275 2.01 39

Table 02275-1 Riprap Gradation. Please review the gradation table. It shows 85-100 percent passing the

1.5” diameter screen. This is impossible considering 50-

85% is 13” material. 1.5" should be changed to 1.5 feet (18 inches).

Will this project require a PLA ?(Project Labor

Agreement)

Project Labor Agreement (PLA) does not apply to the project, as it falls well below the $35 million threshold established in Executive Order 14063 for mandatory use of Project Labor Agreements on large-scale federal construction projects

32 Specifications 02300-14

01150 G 1.07 Item 7 description refers to "hydrated lime", though specifications refer to the ability to dry mix lime per Method 1. Is 02300 Section C. 3 Method

1 and acceptable incorporation of Dry Lime? It is proposed to use "ASTM C25 Quicklime" with

"Method 1", is this acceptable? Yes, this is acceptable.

Is there any hydrologic information that can be provided regrading the anticipated flows into/out of the reservoir? We would like this information in order to size our water control and bypass systems appropriately. In short, we would like to know what flows that can be anticipated both in terms of peak flow rates (that may need to be passed around the work area via gravity or mechanical pumping) and total volumes (that may need to be temporarily impounded) to prevent the work are from being inundated?

Know information is provided in specification SECTION

02600 DIVERSION AND CARE OF WATER; 1.04

SITE CONDITIONS. Contractor is responsible for the design of cofferdams and diversions including hydrology.

What is the current water surface elevation (post-controlled breach) as compared to the limits of excavation or other benchmark that can be referenced on the plans?

This varies. See Sheet BX2 for breach elevations, which dictate current high water conditions. As indicated in

Section 02600, 1.04, the water elevation due to the breach is about 7009 ft.

Does the existing pool in the reservoir need to be lowered and maintained to an elevation below the vertical limits of excavation for outlet works construction, or can the water surface elevation in the reservoir pool be higher than the elevation of the outlet works excavation(s) during construction? This will be up to the contractor's means and methods.

Can the existing controlled breach “channel” be enlarged by the contractor in order to accommodate water control and dewatering activities (i.e., can the breach area be further excavated to serve as a gravity bypass during construction)?

Yes, however additional excavation and embankment will be the responsibility of the contractor and not paid for separately. Cost should be included in the contractor's cost for Water Control and Dewatering.

Are there any requirements on how much water needs to be passed to the downstream waterway at any time during the construction period? No

Are there any limitations on how much water from within the reservoir and/or stream can be consumed for construction purposes? No

Is there any information available from which to estimate the total volume of water currently in the reservoir pool (acre-feet)?

No. Capacity is estimated at 589 acre-ft at Elev 7019.8 and 1,118 acre-ft at elevation 7025.5'

Are there limits on the borrow area excavation

(horizontal and/or vertical)?

Approximate horizontal limits are shown on Sheet C1.

There are no vertical limits; however excavations should allow for final site reclamation and grading.

Can the CAD file be provided to bidding contractors to assist in earthwork takeoffs?

CAD files will not be provided for bidding purposes.

Quantities shown in the bidding documents are based on

CAD surfaces and should be all inclusive.

Will the government allow contractors to work at times outside of 0700-1900 Monday-Friday (i.e., will work be allowed on non-holiday Saturdays)? yes, with GOVERNMENT approval.

The road gravel requires a PI of between 4-12. I have not located any gravel that will meet the specification.

Can Wyoming Type W gravel be accepted.

Road gravel with PI is desirable to minimize surface raveling. WYDOT Grading W is specified, but with PI.