This document is an attachment titled "Limitations on Subcontractor Breakout" related to Solicitation Number 140L0624R0055 for the "SPRNCA BOUNDARY FENCE RECONSTRUCTION PHASE 1A" federal contract opportunity.
The attachment outlines the required self-performance percentage of 25% and provides a table for the contractor to report amounts paid to small business subcontractors (SSS) and large business subcontractors (LBS). The total amount proposed, total material cost, and total labor cost must be provided, along with the limitation on subcontracting percentage, which must be greater than the required self-performance percentage of 25%. The attachment also provides definitions and notes related to the calculation of these values.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L0624R0055_Amd_0001.pdf | ||
| Attachment_8_QuestionsAnswers1_21Aug2024_0001.pdf | ||
| Attachment_9_Site_Visit_Roster_0001.pdf | ||
| Attachment_7_Davis_Bacon_Act_WD_AZ20240009_0001.pdf | ||
| Sol_140L0624R0055.pdf | ||
| Attachment_1_SPRNCA_Boundary_Fence_Specs___Drawings_-_Final.pdf | ||
| Attachment_2_Price_Breakout.pdf | ||
| Attachment_3_Davis_Bacon_Act_WD__AZ20240007.pdf | ||
| Attachment_5_RFI_Form.xlsx | XLSX spreadsheet | |
| Attachment_6_SF1442_Completion_Instructions.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A B C D
Solicitation Number
Type of Set-Aside
Performance Period
Required Self-Performance
(D) Small Business Subcontractor (SSS)
Labor3
Total Amount Paid to [Insert First SSS Name]
Total Amount Paid to [Insert Second SSS Name]
Total Amount Paid to [Insert Third SSS Name]
Total Amount Paid to [Insert Fourth SSS Name]
Total Amount Paid to [Insert Fifth SSS Name]
Total Amount Paid to [Insert Sixth SSS Name]
Total Amount Paid to SSS Companies $0.00
(E) Large Business Subcontractor (LBS)
Labor Total Amount Paid to [Insert First LBS Name]
Total Amount Paid to [Insert Second LBS Name]
Total Amount Paid to [Insert Third LBS Name]
Total Amount Paid to [Insert Fourth LBS Name]
Total Amount Paid to [Insert Fifth LBS Name]
Total Amount Paid to [Insert Sixth LBS Name]
Total Amount Paid to LBS Companies $0.00
$0.00
#DIV/0!
*Note 1: (A) Total Amount Proposed = (B) Total Material Cost + (F) Total Labor Cost
*Note 2: Total Material Cost includes special tooling, special testing equipment, and construction equipment. Additional definition of material cost can be found at 13 CFR 125.1.
Limitations on Subcontracting Breakout
FAR 52.219-14(e)(3) or (4)
(A) Total Amount Proposed¹
(B) Total Material Cost2
140L0624R0055
Small Business
365 plus 90(if additve awarded)
*Note 5: To be compliant, limitation percentage must be greater than the required self-performance percentage.
25%
(F) Total Labor Cost4
(G) Limitation on Subcontracting Percentage5
(Total Labor Cost - Total Amount Paid to LBS Companies) / Total Labor Cost
(C) Self Performed Labor
*Note 4: Total labor costs consist of all contractual costs other than material.